NORDIPIPE as pull-in version for trenchless rehabilitation of drinking water pipes
Jul 08, 2014
Renovation » Lining with pipes
Pilot project with CIPP technology of SEKISUI SPR in Shumen, Bulgaria - The challenges often involved in drinking water rehabilitation projects are the available time window, residual flow capacity after the rehabilitation, diameter and length to be renewed. Other factors are the capacity to negotiate bends and local contruction site conditions.
In Shumen the Water Supply and Sewerage Company trusted the CIPP technology and instructed the rehabilitation of four sections in its water network. One section was a pilot project: For the rehabilitation of a 328 m long and 920 mm diameter large drinking water pipe the CIPP liner system NORDIPIPE™ was used as pull-in version for the first time.
Shumen is a city in northeastern Bulgaria whose drinking water supply is managed by the Shumen Water Supply and Sewerage Company. The region is supplied by 94 individual and independent water supply systems, covering 8 towns and 143 villages. There are 1,450 km of local distribution pipelines with 56,159 lateral connections. Water is supplied by pumping along 890 km of pipelines to the 72,209 households. Most of them are made of asbestos-cement and were constructed between 1950 and 1970. Others were made of steel that need to be rehabilitated because of leakages to guarantee an immaculate 24-hour drinking water supply for the next decades.
In autumn 2013 the Shumen Water Supply and Sewerage Company commissioned Stroitelna Mehanizatsia, a construction partner of SEKISUI SPR in Europe, with the rehabilitation of a deteriorated steel pipe with a length of around 3000 m and diameters of 544 - 920 mm. The project included four sections, three of them where rehabilitated by trenchless NORDIPIPE™ CIPP technologies of SEKISUI SPR. For the rehabilitation of a 328-metre long drinking water pipe section with diameter of 920 mm, the CIPP liner system NORDIPIPE™ as pull-in version was deemed to be the ideal technological solution.
Open construction would not have been possible due to the challenging construction site conditions. The 920 mm diameter steel pipe lies in an unstable ground with soft, loamy soil which meant limited accessibility, particularly during persistent rainfall. Therefore only a fast trenchless technology solution was considered for which excavation pits as start and end point and less equipment was sufficient. Further difficulties that the technology had to compete with were the high groundwater level, a strong gradient of 6-8%, a 15° bend and an operating pressure of 16 bar.
NORDIPIPE™ pull-in liner and its advantages
NORDIPIPE™ consists of a main hose and a calibration hose whose material combination has been approved in conjunction with NORDIPOX D resin for potable water under various approval schemes in several countries. The main hose is a fiberglass-reinforced needle-felt liner with a number of glass layers, selected according to internal pressure and diameter. Its durable PE outer coating protects the liner from external influences during installation and operation.
The calibration hose, a needle-felt liner with PE coating, raises the main hose into position within the old pipe and provides a smooth surface with increased hydraulic performance compared to the old host pipe.
Both hoses are impregnated with NORDIPOX D, a two-component epoxy resin, to receive a homogenous material combination as well as a consistent liner structure in the cured state. The pull-in version allows an accurate calculation of the resin material and a consistent resin distribution. Its particular material composition of glass-fiber, needle-felt, resin and PE coating makes it a fully structural liner. It can be thus called a "stand-alone pipe" for the purposes of DIN EN ISO 11298 Class A.
The installation process
Three construction pits provided access to the 328 m long pipe section at a depth of 3 m beneath a field alongside a main road. The installation length of 328 m would normally have been no problem. However, due to the poor bearing capacity of the loamy soil, for weight reasons the liner had to be divided into two lengths of 164 m. The impregnation process took place on a road near the construction site. Long distance was needed for laying out the liner while being impregnated by a mobile impregnation setup and directly wound onto a transport spool. The main and calibration hose were impregnated with the specially designed NORDIPOX D epoxy resin at about 4°C.
After pipe cleaning, the main hose was gradually drawn into one of the two 164 m long pipe sections by means of a 20 tonne capacity winch. Afterwards, the calibration hose was inverted with low pressure and a speed of 3–5 m/min by means of a pressure drum to position the main hose in the old pipe. The hoses were steam cured at a laminate temperature of 70°C and a new stand-alone pipe was created within a period of two hours. The insulating PE outer coating of the main hose allowed a reduced curing time despite the challenging construction site conditions and the high water level.
The rehabilitation process was concluded after sealing the four ends of the two 164 m long liner sections within two weeks. Following a pressure test, the pilot project for the NORDIPIPE™ pull-in liner for a 920 mm diameter pipe was successfully completed. The pipe was put back into 24-hour, seven-day operation to supply the city of Shumen safely with drinking water.
More News and Articles
Apr 29, 2024
News
Minimising cultural impacts with trenchless
Through the benefits of trenchless technology, Yarra Valley Water is minimising impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe in Epping, …
Apr 26, 2024
News
Bothar’s cutting head innovation
The trenchless industry in Australia continues to grow and the need to provide customised solutions becomes vital for a leading subsurface contractor.
Recognising the need for advanced solutions to meet the growing …
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Contact
SEKISUI SPR Group
Lena Zemke
Julius-Müller-Str. 6
32816 Schieder-Schwalenberg
Germany
Phone:
+49 (0) 52 84/705-405
Fax:
+49 (0) 52 84/705-410