Twin Robbins Crossover TBMs to Bore on Mumbai Metro Line 3
Aug 06, 2018
Massive Metro Project Will Improve Traffic and Rail Congestion in One of India’s Largest Cities.
On June 11, 2018, a Robbins Crossover XRE destined for Line 3 of India’s Mumbai Metro arrived in Mumbai port following a successful factory acceptance test in April. The machine, combining features of a hard rock Single Shield TBM and an Earth Pressure Balance Machine, is one of two 6.65 m (21.8 ft) Crossover machines that will bore under contract UGC-01.
Operation of these two machines will be carried out by Larsen & Toubro, part of the Larsen & Toubro -Shanghai Tunnel Engineering Co Joint Venture (L&T-STEC JV).The Robbins Company will provide key personnel for the initial boring phase.
“During the factory acceptance testing, we observed that the machine and back-up system are robust enough for hard rock tunneling,” stated Palwinder Singh, Head of Tunnel Operations for L&T-STEC JV.
During the bores, consisting of parallel 2.8 km (1.7 mi long) tunnels, geologic conditions will include mixed ground and possible water pressures up to 2 bar. According to Singh, “A Crossover XRE was chosen because of the expected geology,” which includes basalt rock and transition zones consisting of black carbonaceous shale, tuff, and breccia.
Rock strengths are anticipated to range between 15 MPa and 125 MPa (2,200 and 18,100 psi) UCS. The machines will bore with only 15 to 20 m (50 to 70 ft) of cover above the tunnel and the structure will be lined with reinforced concrete segments in a 5+1 arrangement.
The metro tunnels will run between the Cuffe Parade Station and Hutatma Chowk station, passing through the Vidhan Bhavan and Church Stations. Both Crossover machines will be launched from the same 25 m (82 ft) deep by 22 m (72 ft) long shaft at the Cuffe Parade Station.
“The limited length of the shaft requires running the TBMs for the first 100 m (328 ft) with some or all the back-up decks at the surface,” said JP Bayart, Robbins Project Engineer. “The TBMs and back-up systems are connected with umbilical cables and hoses.”
The TBMs will begin their excavation in hard rock mode. “Each cutterhead is optimized for operation in rock, as this is what is expected. The machines can also operate in soft ground thanks to the screw conveyor with bulkhead gate and discharge gate,” said Bayart. “The Robbins Torque-Shift System, consisting of two-speed shifting gearboxes coupled to the main drive motors, allows for the high cutterhead torque required for soft ground operation.”
The face of each machine is equipped with six muck buckets and six large internal muck loading plates. This design, in combination with the screw conveyor located at the centerline of each machine, will allow for the option of fully emptying the cutterhead chamber, resulting in minimal wear when EPB mode is not required. Muck will be removed from the tunnels via muck cars.
Assembly and launch preparations for the first XRE TBM began on 20 June and are estimated to take about six weeks. The second Robbins XRE TBM underwent factory acceptance testing at the end of May and will arrive at the jobsite at the end of July for its assembly. “Our target is to achieve an average of 250 m (820 ft) of boring per month,” said Jim Clark, Robbins Projects Manager India.
“The target to complete the boring operations is 20 months, which includes the additional time required for the short start-up using umbilicals on the initial drives, dragging the machines and re-launching through three stations.” Contractor L&T plans to work crews on double shifts to cover a full day of operations in order to keep to this timeline.
The machines will join two Robbins Slurry machines boring a separate contract of the Mumbai Metro Line 3. The first of those machines will be launching in August 2018. The Metro Line 3 project is estimated to be completed by 2021.
More News and Articles
May 10, 2024
News
A master in customised pipes
Australian Custom Pipes no longer needs an introduction. The independent, Australian-owned polyethylene pipe manufacturer has been making waves for more than 20 years.
The company’s quality polyethylene (PE) pipes …
May 08, 2024
News
Improving trenchless installations with Riteline
Riteline spacers have been successfully appraised by the Water Services Association of Australia, providing a new option for pipeline installations that complies with WSA PS-324 for casing spacers.
May 06, 2024
News
Redefining relining in Wodonga
In a step towards enhancing stormwater infrastructure, M. Tucker & Sons recently completed a challenging relining project for the Wodonga City Council.
The relining project, commissioned by the Wodonga City Council …
Apr 29, 2024
News
Minimising cultural impacts with trenchless
Through the benefits of trenchless technology, Yarra Valley Water is minimising impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe in Epping, …
Apr 26, 2024
News
Bothar’s cutting head innovation
The trenchless industry in Australia continues to grow and the need to provide customised solutions becomes vital for a leading subsurface contractor.
Recognising the need for advanced solutions to meet the growing …
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Contact
The Robbins Company
29100 Hall Street
OH 44139 Solon
United States
Phone:
+1 440 248 3303
Fax:
+1 440 248 1702