VMT guidance system aids pipejack record for the southern hemisphere
McConnell Dowell Corporation Limited recently announced the successful completion of the Pringle Hill Pipejack which forms part of the construction work on the Northern Pipeline Interconnector project being undertaken by the Northern Network Alliance (NNA) in South East Queensland, Australia. The NNA consists of LinkWater Projects, McConnell Dowell, Abigroup and KBR.
| Nov 07, 2011 |
|
|
|||
|
The Herrenknecht AVND- 2000AB microtunnelling system at Pringle Hill. (Source: VMT GmbH) |
|||
Whilst there are longer completed pipejacks in Europe the Pringle Hill installation is different in that it includes a significant vertical curve contributing to a 60 m climb from the tunnel launch position to the final target destination.
Construction works
After careful consideration of the options available for the Pringle Hill installation, the pipejack technique was chosen with a state-of-the-art guidance system to control the navigation around the curves and the necessary elevation change over the course of the drive.
The tunnelling machine chosen was a Herrenknecht AVND-2000AB microtunnelling system. The unit would be jacked through the drive using the 3 m long, 2,100 mm internal diameter reinforced concrete pipes that would form the final installed tunnel.
During the course of the installation a total of 10 interjack stations were deployed throughout the pipe string alignment to keep jacking forces within the necessary limits of the jacking pipe through the curves and alignment changes and the designed capacity of the launch shaft. Ground conditions over the course of the drive comprised silt stone and partial sandstone.
|
|
|||
|
The laser theodolite set up in the launch shaft. (Source: VMT GmbH) |
|||
The microtunnelling system worked very well throughout the course of the installation which started on 25 August 2010. One of the most important aspects of the construction was the required alignment and navigational control. The construction plan called for the drive to cover some 1,030 m in a straight line in the horizontal plane. In the vertical plane, the first 50 m were straight followed by 780 m curve on a radius of 8,000 m. The drive was to be completed with the final 215 m being straight but with a +10% grade. This meant that the navigation utilised for the drive would be a key element in the success of the tunnel.
All services and products used for the navigational control system were provided by tunnel navigation systems specialist, VMT GmbH, with the unit used on the Pringle Hill installation being supplied through the company’s Australian subsidiary, VMT Tunnel Guidance Pty, which is based in Brisbane.
|
|
|||
|
The control and navigational panel for the microtunnelling system. (Source: VMT GmbH) |
|||
Given the level of directional control required for the installation at Pringle Hill, the correct choice of navigational equipment and technique was vital. After considering the options available, it was decided to operate the microtunnelling machine with a VMT SLS-Microtunnelling LT – Laser Total Station system.
The SLS-Microtunnelling LT guidance system was chosen because, according to VMT, it offers significant advantages for longer or curved tunnelling projects. The ability to determine, continually update and display the tunnel boring machine’s (TBM) current position, independent of drift or refraction, guarantees optimum control in long pipeline excavations and in complex curves.
|
|
|||
|
A schematic representation of the VMT SLS-Microtunnelling LT – Laser Total Station system. (Source: VMT GmbH) |
|||
Control measurements for system adjustment are taken in intervals of between 60 m to 120 m, depending on the route. A surveyor requires only minimal time and effort for supervision during the project. Reduced machine down time therefore makes this high performance system very cost-effective, especially for quick excavations.
Daily remote monitoring services offered by VMT allowed for smoothing of the reference track of the guidance system. The navigation technique allows the TBM measurement to determine precisely the laser target position and offsets.
The PLC Communication Link also offers data logging of TBM data. All of this means that the DTA can be calculated and verified fully. The systems also allows for real time internet visualisation of the relevant TBM data including both navigation and machine performance data. All survey surface network measurements on the project were completed by Surex Pty Ltd.
|
|
|||
|
On target – holing out on the Pringle Hill tunnel. (Source: VMT GmbH) |
|||
Ultimately the pipejacking section of the tunnelling works was completed on 1 November 2010, some five weeks ahead of program. Breakthrough was achieved to a very high accuracy with the drive being less than 50 mm off the target point in both horizontal and vertical planes.