BE-15 Pipes and Materials: Welding of Plastic Pipes

Heating element butt welding

Preparatory work for welding

Before the welding procedure starts, the temperature of the heating element that is required for welding has to be controlled. This is carried out e.g. by means of a temperature measuring device with a fast display used for surface measurements. The control measurement has to be carried out within the area of the heating element that corresponds with the semi-finished product. In order to create a thermal balance, the heating element must have had the desired temperature for at least 10 minutes before it may be used.