Trenchless sewer pipe renovation using the new tight-in-pipe method in the congested streets of the City of Dortmund, Germany
Jun 05, 2008
This paper introduces the Tight-in-Pipe Method. Tight-in-pipe is the term of a method for renovating sewer pipes and laterals with new, slightly smaller pipes in the same path without the need for filling the annullus between new pipe and host pipe. Deformation and misalignment can be compensated to a certain extent during pipe installation. Excavations can be abandoned almost completely when working from one manhole to the next. By this means, slight to medium deformations and misalignments are compensated, leaving circular pipes underground. The Tight-In-Pipe method is mainly used in projects for which a slight reduction of the original diameter is acceptable.Furthermore, this paper describes the application for this method on a larger project in the German City of Dortmund, 2006, where 4 sections of sewer pipe in Hertastraße had to be renovated, over a complete length 186 m. Installation with open trenches was impossible due to narrow site conditions and congested streets. Furthermore, this application method saved approximately 2/3 of the initially calculated costs had the project been carried out by open trenching. The contract was awareded to Paul SPEECK Rohrleitungs- und Tiefbau GmbH from Dortmund.
- minimal reduction of original pipe cross section,
- use of pre-fabricated pipes,
- completely fusion welded pipe string (PE, PP, PVC),
- plastic pipe liners have smooth inner walls and show high resistance against mechanical
- wear or chemical reactions,
- liners can also be utilized on sites with groundwater infiltration,
- independent of soil cover depth and soil conditions if laterals are connected from inside,
- short installation times with little traffic disturbance,
- structural load capacity if the dimensions are sufficient (material, wall thickness),
- long service life if the dimensions are sufficient (material, wall thickness).
- minimising the reduction of the original pipe cross section compared to sliplining,
- no annulus to fill up,
- no starting pit requirement when using the deformation method (U-, C-Liner)for pipes up to
ND 450 mm / 18”
- can only be used for circular host pipes,
- sags cannot be compensated for,
- blockage debris needs to be removed,
- possible movement of the liner in temperature fluctuations,
- exact knowledge of the location of the laterals is crucial for trenchless re-connection, otherwise connection of the laterals, particularly in the non-accessible nominal diameter range, is very elaborate and has to be carried out with open-trench methods,
- no sufficient long term experience about the re-shaping of the pre-formed pipe,
- movement of the liner under temperature fluctuations possible,
- sewer has to be taken out of service for the duration of the project.
method, to additional wrinkling of the liner. On the other hand, nominal diameter expansions can form an annular gap between the liner and the sewer. The liner may become overstretched during installation whereby later on, longitudinal shrinkage could be the outcome.
use are slid onto QuickLock rods and pushed into the host pipe with the help of a guiding head and a pulling rig already known from pipe bursting. By this arrangement, slight to medium deformations and misalignments of the host pipe are compensated, leaving circular pipes underground. The Tight-In-Pipe method is mainly used in projects for which a minimal reduction of the original diameter is acceptable. For example, a new pipe OD 192 x 12.0 mm (7.6”x0.47”) can be pushed into a host pipe ND 200 mm (8”) (Fig. 1). The new installation is carried out from manhole to manhole over lengths of up to approx. 70 m (230 ft).
fabricated, circular pipes, there is no need to investigate long-term effects caused by the relaxation of the pre-shaped pipes (e.g. U-Liners, C-Liners). Additionally, the filling of the annulus which is sometimes necessary when operating sliplining or short-pipe-lining can be disregarded.
- cracks, fractures, breakages, slab-outs (missing pipe fragments),
- corrosion, roots (remove, if necessary), leakages,
- deformations up to a maximum of 15% of the host pipe diameter,
- misalignment up to a maximum of 10 % of the host pipe cross section,
- can only be used for circular host pipes,
- a relatively straight course of the existing defective pipe line is a pre-condition. The method is not suitable for sewers with several different invert levels in the same renovation sections,
- sags cannot be compensated for,
- trenchless connection of laterals is possible from host pipe ND 250 mm / 10” or larger,
- blockage debris needs to be removed,
- misalignments of the manhole bases must be compensated for,
- mounting the pulling device into a manhole is not always possible (due to misalignment of the entry and emerging angles of the pipe line).
- Re-shaping of a circular profile: slight to medium deformations and misalignments are compensated for by the guide head, thus re-shaping the circular form of the pipe. This improves the hydraulic properties compared to the defect host pipe.
- The new pipe lies tight inside the host pipe (without annulus): there is no annulus over the entire length of the pipe required to be filled . Only the end sections of the mains (manholes) require sealing.
- Trenchless connection of laterals: the laterals can be connected without working pits using common trenchless re-connection methods (robot).
- Load bearing properties of a new pipe: the load bearing performance of the new pipe does not depend on the host pipe (Fig. 2), that is, the structural calculation is carried out without relating to the remaining bearing capability of the host pipe.
- Long service life: the pipes are industrially produced under the best conditions possible. The pipe materials of highest quality, according to the manufacturer, offer a long service life of 80-100 years (DIN 8078, appendix B). With this solid wall pipe, the defective sewer system is renovated for the coming generations.
- Smooth pipe walls: short pipes have dense, stable, plug-in joints, smooth inside and outside. The inner pipe walls are regular and very smooth, deposits are avoided. Due to the improved hydraulic properties, the frequency of flush cleaning, among others, can be reduced, which also results in reduced operation costs.
- operating from manhole to manhole (short pipe installation only),
- operating from pit to manhole (short pipe installation from manhole),
- operating from pit to pit (long or short pipe installation from pit).
Short pipes up to OD 585 mm (23”) can be installed applying the “Tight-In-Pipe” method from manhole to manhole with the aid of a manhole pipe bursting rig (fig. 3); section lengths of up to 70 m (230 ft) in one go can be achieved. Concrete host pipes with massive corrosion of the inner pipe walls, require more pulling power compared to smoother vitrified clay host pipes.
The Tight-In-Pipe method can also be used in relatively small pits, just like the static pipe bursting method. Here, too, the short pipe sections are pulled with QuickLock rods (Fig. 4). This kind of application is recommended when higher demands are made regarding the equipment, e.g. when working on corroded concrete sewers or when laterals are beyond repair and have to be renewed using an open trench method (key hole). The working pit can be used both for the pulling rig and for installing longer pipes. As before, the maximum installation lengths are 70 m (230 ft) for new pipes up to OD 585 mm (23”).
Long pipes can also be pulled “Tight-In-Pipe“ into an host pipe. The method is similar to the principle of the static pipe bursting method with QuickLock rods. Of course, if the renovation section is shorter, then short pipes can be installed from an existing launch pit (Fig. 5). The advantage of an installation from existing pits is in the utilization of longer pipes and a wider application range. When using this installation method, pipes up to OD 585 mm (23”) can be laid over maximum lengths of 100 m (330 ft).
Manhole bursting rigs, already known from static pipe bursting, operate with pulling forces between 200 and 400 KN (45,000 – 90,000 lbs), depending on pipe size and also use QuickLock rods. The rig can be used for bursting as well as calibre pipe bursting and the Tight-In-Pipe method.
After the rig has been fixed inside the manhole (target manhole), the QuickLock rods are pushed into the host pipe to the launch manhole. Here, the guide cone (Fig. 8) and the following new pipe segments are slid over the rods and tensioned with a pre-tensioning system, for example, Burstfix (Fig. 7).
The Burstfix tensioning system (Fig. 7) ensures a safe pipe pulling-in process behind the guide cone and tight socket connections. It forms a unit consisting of the rod guiding system with slide rollers and the tensioning unit itself with pipe adapter, locking plate and pressure ring. The Burstfix tensioning system is operated with a portable hydraulic power unit – the functions are activated via remote control. The permissible tensioning force for each pipe can be preset at the hydraulic unit.
Working principle: First of all the bursting rod is extended and the new short pipe segment is fitted into the short pipe already pulled-in. The tensioning unit then automatically drives over the tensioning rods to the rear, the pipe adapter with the locking plate is inserted and the pressure ring is fixed in place with a bolt inside the rod. With the pipe adapter any size of short pipe modules can be adapted. The cylinders are now driven out up to a maximum length via a remote control. The pipe pulls itself together to form a string and can be tensioned up to max. 200 kN. Gradually, as the renovation progresses, all short pipes are pulled in.
The guide cone (Fig. 8) is the key to successfull installation by means of the Tight-In-Pipe Method. The rollers in the front of the guide cone align it centrally in the host pipe and assist to restore the circular profile of the host pipe. The new pipe can then follow along in a relatively friction-free environment.
- excellent material properties,
- uniform wall thickness,
- precise dimensional accuracy of the pipes and pipe joints,
- reliable impermeability,
- proven suitability for sewer applications.
1842: Construction of the first sewer system in the Hanseatic City of Hamburg (Fig. 10). Start of the sewer works in Dortmund.
1853 to 1879: The first single sewer systems are installed beneath streets with extremely terrible sanitary conditions.
1880 to 1907:Installation of the first coherent sewer system for the old central city of Dortmund in the river basin of the Emscher. The sewerage was collected in the sewer system and thus quickly disposed off. In this way, the plight was shifted from the city to the area of Huckarder Bruch.
1887: Construction of a mechanical sewer system in the Franziusstraße with 2 slurry tanks and 4 Dortmund wells (6.50 m diameter and 12 m deep).
1889: Two additional Dortmund wells are built. However, industries and population are growing so quick that the new purifying plants are unable to stop the increasingly deplorable state of affairs.
1891: A commission of officials of government visits Dortmund. At that time, the regulation of the river Emscher was considered to be impossible, therefore the commission decreed: “The supervisory authorities must strive with emphasis towards coercing the city to carry out a project which had formerly been planned, the installation of sewage farms on the outskirts of the city" (Fig. 11).
1894/97: The 13.5 km long inlet system of the sewage field is built (Fig. 12). The profile ND 90/135 cm was calculated for the waste water of 150.000 inhabitants at a dilution factor of 2.5.
1898/99: The eastern part of the sewage farms is put into operation. The waste water of the city centre is lead from its natural drainage area (river Emscher) into the river Lippe area via inlet system of the sewage farm (Fig. 13).
1904: The Prussian king confirmed the law for forming a cooperative society for the regulation and sewage clarification in the Emscher area (Emscher Law). All parties involved in the area (communities, mining companies and other commercial enterprises) are forced into membership. Their contributions are needed to pay for the tasks of the cooperative.
1926: In an attempt to achieve a uniform regulation of the waste water conditions and to prevent the extreme soiling of the river Lippe and its side branches, the Lippegesetz (Lippe law) was passed and the Lippeverband (Lippe alliance) was founded on the 19th of February 1926. Adjacent communities, mines and other industrial enterprises are also forced to become members here. The tasks of the Lippe alliance are the same as those of the Emscher cooperation. Both associations are managed in administrative and personal union.
1935 to 36: An 1800 m long deep sewer is installed between the quayside railway in the Brackeler Street and Borsigplatz. The sewer is 420 cm in diameter and lies as deep as 15 m beneath the level of the terrain. At the time, the sewer was excavated using the shield tunnelling method, a procedure which attracted the greatest attention of the experts because of the difficult site conditions.
The sewer conditions in the north of Dortmund were particularly precarious. Destruction and break-down of the sewer pumping stations caused the lowest points of the northern part of the city to be flooded by waste water. The threat of epidemics caused severe worries, the authori- ties even considered evacuating the population living in the endangered regions. Beating all the odds, the civil engineering authorities, powerfully assisted by the Hoesch Bergwerke AG, managed to reactivate the waste water pumping station in Borsig street in a provisional fash-ion in the summer of 1945. The main damage of the sewer network could not be repaired be- fore 1948, after the currency reform, when sourcing of material improved and work was accel- erated considerably. On the 1st of July 1949, approximately 90 percent of the damage was repaired.
Open trench renewal of the sewer net in Dortmund means higher building costs and definitely higher indirect costs due to the management of the heavy traffic in the city. Therefore, the civil engineering department is increasingly inclined towards the application of trenchless sewer renewal methods.
In May 2006, tenders were invited for the installation project Klosterbredde / Hertastreet, using the Tight-In-Pipe method. The job site is located in the centre of Lütgendortmund, a suburb of Dortmund (Fig. 14 - 16).
The sections (Fig. 16) 74 / 121, 121 / 120, 120 / 119, 119 / 221 to be renovated using the trenchless Tight-In-Pipe method. The complete length was 186 m (610 ft). According to Dr. Christan Falk, head of the sewer department of the municipality of Dortmund and GSTT Board member, installation with open trenches was impossible because of narrow site conditions and the risk for a 2 m high house wall, which was in danger of collapsing. Also, the project would have taken much longer.
On the first section, the bursting rig Grundoburst 400 S was installed in a manhole and the QuickLock rods were pushed into the starting pit in a distance of 64 m. The patented QuickLock connection forms a flexible rod string which followed even slightly curved paths.
The Grundoburst was placed on top of a height-adjustable working platform, 1 m above the bottom of the manhole and was secured against the manhole walls. In the starting pit, a guide cone was connected to the rod string (Fig. 17). The first new pipe section was then attached to the guide cone and safely tensioned using the Burstfix (Fig. 18). The Burstfix kept the short pipe sections safely together during the pulling-in operation. The rollers in the front of the guide cone aligned it centrally in the host pipe and assisted to restore the circular profile of the host pipe. The new pipe could then follow in a relatively friction-free environment.
The municipality of Dortmund and the contracting company PAUL SPEECK Rohrleitungsbau und Tiefbau GmbH have recognised the advantages of this method and want to utilise it in their networks wherever it is possible. According Dr. Christan Falk, in addition to the advantages mentioned before also saved approximately 2/3 of the initially calculated costs had the project been carried out by open trenching
More News and Articles
Apr 29, 2024
News
Minimising cultural impacts with trenchless
Through the benefits of trenchless technology, Yarra Valley Water is minimising impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe in Epping, …
Apr 26, 2024
News
Bothar’s cutting head innovation
The trenchless industry in Australia continues to grow and the need to provide customised solutions becomes vital for a leading subsurface contractor.
Recognising the need for advanced solutions to meet the growing …
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Contact
Meinolf Rameil (TRACTO-TECHNIK GmbH & Co. KG)
57368 Lennestadt, Germany
Phone:
+49 (0)2723 808187
Fax:
+49 (0)2723 808216