Sealing measures at Sedrun almost complete
Feb 14, 2007
In the southward drive of the Sedrun section, injection work has been in progress since the end of October 2006. These sealing measures are to prevent further water from being drawn out of the rock. By Christmas, the water ingress was reduced by half to 5 litres per second. By mid-February 2007, the injection campaign should be complete. Driving to the south will then be resumed.
Challenging tunnel construction
Whenever a tunnel is driven, water seepage from ground level must always be expected. Even in deeply lying drives such as the Gotthard Base Tunnel, water ingresses are unavoidable. This drainage of water causes fissures in the rock to close to a certain extent, which can lead to deformations on the surface. Such phenomena were detected in Switzerland during construction of the exploratory drive for the Rawil tunnel near the Zeuzier reservoir, and in the area affected by the Gotthard road tunnel.
The overriding goal of AlpTransit Gotthard Ltd is therefore to secure the tunnel drive in such a way that the reservoirs lying above it are not damaged. So that this goal can be accomplished, AlpTransit Gotthard Ltd has initiated various measures: Advance explorations and injections at the tunnel drive as well as a unique automatic monitoring system for the Curnera, Nalps and Santa Maria reservoirs.
Monitoring system has proved itself
Experience to date in the Sedrun drive to the south shows that construction of the tunnel has caused deformations in the range of millimetres in the surface terrain. In view of the limited settlement, no damage has been detected so far.
More surprising to technical specialists is the fact that the observed deformations have already occurred with very limited volumes of water. The ingresses to the Gotthard Base Tunnel encountered so far are much less than those formerly observed in the Rawil exploratory drive and the Gotthard road tunnel. After several years experience, it can now be said that the monitoring system installed in 2000, as well as the close and cooperative collaboration with the power station operators and the controlling bodies of the Swiss government, have proved themselves very well.
Work status
On January 1, 2007, of the total of 153.3 km of tunnels, shafts and passages making up the Gotthard Base Tunnel, 102.07 km, or approximately two thirds, had been excavated. In 2006 alone, more than 17 km of the tunnel system under the Gotthard were excavated.
With the foundation stone laying ceremony in Camorino, construction of the Ceneri Base Tunnel officially started on June 2, 2006. Besides other work, preparations for the installation sites at Camorino and Sigirino for subsequent construction of the tunnel are proceeding at full speed.
Further information:
AlpTransit Gotthard AG
Zentralstrasse 5
CH-6003 Luzern
Tel: +41 (0)41 226 06 06
Fax: +41 (0)41 226 06 00
Email: info@alptransit.ch
Web: www.alptransit.ch
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …