Robbins EPB and Conveyors Complete Complex Lot 5 at Emisor Oriente
Apr 02, 2019
Powerful TBM proves itself in both soft ground and hard rock.
On February 28, 2019 a ceremony was held to mark the breakthrough of a machine proven in both soft ground and hard rock. The 8.93 m (29.3 ft) diameter Robbins EPB and continuous conveyor system completed what is arguably one of the most difficult legs of the complex Emisor Oriente tunnel, an epic 62 km (39 mi) long conduit that will revamp wastewater treatment for more than 21.2 million people in Mexico City.
The 6 km (3.7 mi) long Lot 5, one of six lots at Emisor Oriente, required the Robbins machine to be launched from the deepest civil works shaft in Mexico, at 150 m (492 ft), and excavated mixed face conditions as well as abrasive basalt rock. “I am proud of concluding the excavation successfully given that this is the section with the greatest depth on the project,” said José Adolfo Méndez Colorado, Superintendente de Maquinaria for contractor Ingenieros Civiles Asociados (ICA).
“Robbins Field Service had an important contribution in satisfactorily concluding this section. The machine operation was of primary importance: Field Service personnel know how to operate the equipment accurately for favorable results. The speed with which they detect a problem is a favorable point to reduce downtime on the excavation.”
The complexity of the ground conditions, continued Méndez, required the correct concentration and selection of polymers, a large challenge in itself. Field Service assisted with other issues and with equipment operation: “There were some issues with the screw conveyor conveying mixed ground and also in the articulation system, which were overcome with Field Service experience. They also knew the correct operation of the continuous conveyor system, which kept us to expected performance.”
“We are very proud of this machine as it has worked in two very different worlds,” said Roberto Gonzalez, General Manager for Robbins Mexico. In 2011 the machine originally slated for Lot 5 was fast-tracked to bore a 3.9 km (2.4 mi) long section of Lot 1b—a critical part of the line that needed to become operational right away to prevent chronic seasonal flooding. “The EPB proved itself while using conveyors in the sticky clays of Mexico City with very high percentages of water content, up to 400%.”
The machine achieved rates of up to 592.5 m (1,944 ft) in one month—considered a record among the six EPBs (three of them Robbins) used on the project. After completing the bore in just 15 months, the machine was sent to the Lot 5 site, where modifications were made for a section of mixed ground and rock.
Modifications included a high-pressure man lock capable of withstanding 7 bars, chromium carbide wear plates added to the screw conveyor, and grizzly bars added to the cutterhead along with heavy duty cutting tools.
The machine was assembled in a 28 m (92 ft) long assembly chamber at the bottom of the launch shaft and commissioned in August 2014, requiring all back-up gantries to remain at the surface. Two months later in October 2014, after advancing 150 meters (492 ft), the machine and its back-up gantries were completely assembled in the tunnel.
One month later, the continuous conveyor system was installed and running. “The assembly of the EPB at Lot 5 has the record of the deepest assembly of a TBM in Mexico. It required great coordination of ICA engineers, high capacity cranes for the assembly and human resources in order to keep to the ten-week schedule for assembly,” said Gonzalez.
With tunneling at Lot 5 now officially concluded there is one more breakthrough remaining before the Emisor Oriente line is complete: An 8.93 m (29.3 ft) Robbins EPB operating at Lot 4 is scheduled to break through this spring. A third Robbins EPB operating at Lot 3 completed its tunnel in 2018.
The Túnel Emisor Oriente (TEO) is the answer to more than 100 years of sinking in Mexico City as the result of drained lake beds and general lowering of the water table. The city’s buildings, main streets and other structures have sunk more than 12 m (39 ft) in that time, and much of the area is vulnerable to flooding. At the same time the area’s gravity-fed wastewater lines have lost their slope and are severely under capacity.
Once tunneling is complete, the resulting TEO will expand capacity, adding 150 m3/sec (5,297 ft3/sec) to the Valley of Mexico system, as well as alleviating the risk of flooding in critical areas. It will also convey wastewater to the country’s largest wastewater treatment plant. The massive tunnel includes 24 shafts, ranging from 23 meters to 150 meters (75 to 492 ft) in depth, plus an exit portal at the treatment plant in the Municipality of Atotonilco, in the state of Hidalgo.
The News in Brief:
- The Robbins 8.93 m (29.3 ft) diameter EPB and continuous conveyor system completed the Lot 5 tunnel at Emisor Oriente on February 28, 2019.
- The 6 km (3.7 mi) long Lot 5 is one of the most challenging on the 62 km (39 mi) long Emisor Oriente, including soils, mixed face conditions, and basalt rock.
- The Robbins EPB was assembled in just 10 weeks in 2014 and launched from the deepest TBM launch shaft ever constructed in Mexico, at 150 m (492 ft) deep.
- The breakthrough is the second one for the machine, which was also fast-tracked to bore a 3.9 km (2.4 mi) long section at Lot 1b in 2011, where it achieved a project record of 592.5 m (1,944 ft) in one month.
- With tunneling at Lot 5 now officially concluded there is one more breakthrough remaining: An 8.93 m (29.3 ft) Robbins EPB operating at Lot 4 is scheduled to break through this spring.
More News and Articles
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Mar 18, 2024
News
Global Student Innovation Challenge Calls on Next-Generation Leaders to Tackle Water Security
High School and University Students Worldwide Invited to Expand Water Access and Community Resilience
Mar 15, 2024
News
New water treatment wins Prestigious Award
Introducing a advancement in water treatment, developed by Cardiff University researchers in collaboration with Origin Aqua, the FreeOxTM technology has garnered acclaim by winning a prestigious challenge award at the World Water Tech Innovation Summit. This single-step process not only …
Mar 13, 2024
News
Satellite-based river monitoring technique could provide early warning of flooding
A satellite-based method for monitoring the flow of rivers from orbit could provide a valuable early warning system for flood risk, University of Glasgow researchers have claimed.
Mar 11, 2024
News
Revitalising infrastructure with HDD
Through the use of horizontal directional drilling, TasWater is delivering a new sewer pipeline to improve sewer and stormwater transfer capacity in Launceston, Tasmania.
Mar 06, 2024
News
Picking up the pace on climate action: Building momentum from COP28
At the halfway point of the Paris Agreement, the legally binding international treaty on climate action, average global temperatures are already hitting 1.8°C above pre-industrial levels and future projections are stark. At COP28 in December, we could not escape the reality …
Mar 01, 2024
News
Luminescent sensor detects ‘forever chemical’ pollution in water
Researchers in the UK and Germany have developed a new approach for detecting pollution from ‘forever chemicals’ in water through luminescence.
Feb 28, 2024
Article
BETT installation demonstrating GHG emissions reduction of wastewater treatment
This study presents BioElectrochemical Treatment Technology (BETT) as a new wastewater management solution toward the Net-Zero future. The results reported herein were collected from a BETT pilot system installed at a large brewery in Los Angeles, CA, United States processing …
Contact
The Robbins Company
Desiree Willis
Technical Writer
29100 Hall Street
OH 44139 Solon
Germany
Phone:
+1 253 872 4490