Perforator® auger system aids motorway crossings project
Oct 06, 2010
Anyone driving around the UK at the moment using the motorway system will have noticed that there is a lot of work underway to install a huge automated traffic management system and information sign network. Part of this operation, organised by client The Highways Agency and its consulting engineer A.One+, one project has recently been underway on the M56 motorway between Junctions 9 and 16 under the ‘Triple Package Advanced Works’ designation.
The main contractor appointed to complete the project was A E Yates Ltd, with its sister company, A E Yates Trenchless Solutions Ltd, being awarded the trenchless installation works.
The majority of the crossings, some 25 out of 26, were completed using various HDD drilling rigs as per the project plan. The HDD bores varied in length between 40 and 100 m and comprised the installation of 4-way 110 mm diameter conduit pipes. However, at one particular crossing location near Helsby, the work site was very restricted in space, both on the launch and reception sides of the motorway, which meant that the use of the HDD technique was not possible, so another installation option had to be found.
Investigation of the options available led engineers at A E Yates to select the pilot auger microtunnelling technique for the limited-space site.
With the auger crossing site comprising ground conditions of very compact sand and weathered sandstone, the correct choice of installation technique was vital, whilst still being able to operate in the confined spaces on either side of the motorway.
Again careful consideration of the options available led to the choice of a Perforator PB85V pilot auger microtunnelling system as the best choice system for the situation in hand.
The auger crossing comprised the installation of a 45 m long, 300 mm diameter ‘lost steel tube’ which was to act as a carrier pipe for four 110 mm diameter purple PE80 MDPE conduit pipes, manufactured to DIN 8074/8075 specification and supplied by Drain Centre of Wigan, into which the fibre optic cables of the traffic management system would be installed.
However, for the M56 crossing project the contractor chose the PBA85V unit because the one very specific difference between the standard PBA85 rig and the PBA85V system is that, on the ‘V’ version, a gearbox normally used in the Perforator® PBA150 rig is fitted. This allows the ‘V’ unit to boast double the torque capacity of the basic unit. This would enable the bore to be completed efficiently in the harder ground conditions of the crossing site under the M56.
To complete the crossing first the rig is established in the start shaft on the line and level required for the crossing. As the pilot bore progresses the use of the Optic Electronic Navigation System (OEN), which is a laser based system, enables the pilot bore to be driven along the required route of the bore towards the target point.
With the bore at the correct size the pipe installation can then be completed by jacking the necessary pipe into place behind the auger chain whilst removing the displaced auger units at the reception shaft.
The PBA85V can also be utilised as an HDD rig where circumstances warrant and allow with a directional drilling system which can be fitted to the system which utilises the twin wall pilot rods of the standard PBA 85 system which are designed to accept high pressure HDD fluids, to create the initial bore. Subsequently, the high pressure drilling fluids are delivered to special rotary reamers using a purpose built pump, tank and mixer unit with a 2,000 litre capacity. Towing attachments and swivels have been specially designed to work within the PBA85V’s 65 tonnes of pullback capacity to enable the pull-in of the product pipe.
Installations on the M56 project as a whole, including the HDD works, started in January 2010 and were completed by March 2010. The HDD installations took an average of two restricted-hours night shifts each to complete. These were carried out in this manner because of traffic management constraints, restricted working space, and a requirement to dig the HDD rigs in at each site as each set-up was working adjacent to or under the live and open M56 motorway. Works on the auger crossing installation took 5 day shifts subsequent to shaft construction and site preparation.
According to Graham Smedley, managing director of Perforator® Ltd: "Using Perforator’s PBA guided boring systems on this auger crossing enabled the completion of what might otherwise have been a difficult installation to complete given the restrictions on the site in terms of both working close to an operational motorway and in the limited space available. We were very pleased to be able to provide a solution that proved so effective for the contractor. The PBA85V, and other members of the PBA family of pilot auger systems, enables the installation of pipes in straight-lines to grade in a wide variety of situations. Because of the system’s accuracy, installation of other utility pipe networks such as gas mains, water mains and drainage pipelines can also be achieved in areas surrounded by other services and known obstacles."
Commenting on the project for A E Yates site manager Sven Till said: "A difficult challenge was successfully undertaken by AEY Trenchless Solutions, in providing a solution to a problem for the Highways Agency by the use of the Perforator machine. A job well done"
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …
Contact
Perforator Limited
S13 9NP Sheffield
Phone:
+44 (0)1142 693258
Fax:
+44 (0)1142 889380