Perforator® auger system aids motorway crossings project
Oct 06, 2010
Anyone driving around the UK at the moment using the motorway system will have noticed that there is a lot of work underway to install a huge automated traffic management system and information sign network. Part of this operation, organised by client The Highways Agency and its consulting engineer A.One+, one project has recently been underway on the M56 motorway between Junctions 9 and 16 under the ‘Triple Package Advanced Works’ designation.
The main contractor appointed to complete the project was A E Yates Ltd, with its sister company, A E Yates Trenchless Solutions Ltd, being awarded the trenchless installation works.
The majority of the crossings, some 25 out of 26, were completed using various HDD drilling rigs as per the project plan. The HDD bores varied in length between 40 and 100 m and comprised the installation of 4-way 110 mm diameter conduit pipes. However, at one particular crossing location near Helsby, the work site was very restricted in space, both on the launch and reception sides of the motorway, which meant that the use of the HDD technique was not possible, so another installation option had to be found.
Investigation of the options available led engineers at A E Yates to select the pilot auger microtunnelling technique for the limited-space site.
With the auger crossing site comprising ground conditions of very compact sand and weathered sandstone, the correct choice of installation technique was vital, whilst still being able to operate in the confined spaces on either side of the motorway.
Again careful consideration of the options available led to the choice of a Perforator PB85V pilot auger microtunnelling system as the best choice system for the situation in hand.
The auger crossing comprised the installation of a 45 m long, 300 mm diameter ‘lost steel tube’ which was to act as a carrier pipe for four 110 mm diameter purple PE80 MDPE conduit pipes, manufactured to DIN 8074/8075 specification and supplied by Drain Centre of Wigan, into which the fibre optic cables of the traffic management system would be installed.
However, for the M56 crossing project the contractor chose the PBA85V unit because the one very specific difference between the standard PBA85 rig and the PBA85V system is that, on the ‘V’ version, a gearbox normally used in the Perforator® PBA150 rig is fitted. This allows the ‘V’ unit to boast double the torque capacity of the basic unit. This would enable the bore to be completed efficiently in the harder ground conditions of the crossing site under the M56.
To complete the crossing first the rig is established in the start shaft on the line and level required for the crossing. As the pilot bore progresses the use of the Optic Electronic Navigation System (OEN), which is a laser based system, enables the pilot bore to be driven along the required route of the bore towards the target point.
With the bore at the correct size the pipe installation can then be completed by jacking the necessary pipe into place behind the auger chain whilst removing the displaced auger units at the reception shaft.
The PBA85V can also be utilised as an HDD rig where circumstances warrant and allow with a directional drilling system which can be fitted to the system which utilises the twin wall pilot rods of the standard PBA 85 system which are designed to accept high pressure HDD fluids, to create the initial bore. Subsequently, the high pressure drilling fluids are delivered to special rotary reamers using a purpose built pump, tank and mixer unit with a 2,000 litre capacity. Towing attachments and swivels have been specially designed to work within the PBA85V’s 65 tonnes of pullback capacity to enable the pull-in of the product pipe.
Installations on the M56 project as a whole, including the HDD works, started in January 2010 and were completed by March 2010. The HDD installations took an average of two restricted-hours night shifts each to complete. These were carried out in this manner because of traffic management constraints, restricted working space, and a requirement to dig the HDD rigs in at each site as each set-up was working adjacent to or under the live and open M56 motorway. Works on the auger crossing installation took 5 day shifts subsequent to shaft construction and site preparation.
According to Graham Smedley, managing director of Perforator® Ltd: "Using Perforator’s PBA guided boring systems on this auger crossing enabled the completion of what might otherwise have been a difficult installation to complete given the restrictions on the site in terms of both working close to an operational motorway and in the limited space available. We were very pleased to be able to provide a solution that proved so effective for the contractor. The PBA85V, and other members of the PBA family of pilot auger systems, enables the installation of pipes in straight-lines to grade in a wide variety of situations. Because of the system’s accuracy, installation of other utility pipe networks such as gas mains, water mains and drainage pipelines can also be achieved in areas surrounded by other services and known obstacles."
Commenting on the project for A E Yates site manager Sven Till said: "A difficult challenge was successfully undertaken by AEY Trenchless Solutions, in providing a solution to a problem for the Highways Agency by the use of the Perforator machine. A job well done"
More News and Articles
Apr 29, 2024
News
Minimising cultural impacts with trenchless
Through the benefits of trenchless technology, Yarra Valley Water is minimising impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe in Epping, …
Apr 26, 2024
News
Bothar’s cutting head innovation
The trenchless industry in Australia continues to grow and the need to provide customised solutions becomes vital for a leading subsurface contractor.
Recognising the need for advanced solutions to meet the growing …
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Contact
Perforator Limited
S13 9NP Sheffield
Phone:
+44 (0)1142 693258
Fax:
+44 (0)1142 889380