No run of the mill mission on the Florida coast near Miami
Oct 12, 2016
In February 2016 construction company Bessac completed work on a protection tunnel in extremely difficult geology in South Florida. In just ten months and using a customized machine designed especially for the mission, a "Herrenknecht Combined Shield" (HCS, diameter 3.13 m), 1,613 meters were tunnelled adhering to the highest safety standards. A new sewer line was installed in the finished tunnel – after half a century in use the old pipe was simply worn out.
The ground conditions and project circumstances of the mission at Norris Cut were anything but standard. Not only did the karstified, permeable geology pose the risk of flooding the machine. The complex Fort Thompson Formation to be tunnelled through was also full of sand-filled cavities. The tunnel face was therefore prone to instability.
For this reason the construction of the protection tunnel for a new sewer line between Virginia Key and Fisher Island required a special and highly flexible machine with exceptional safety features. A Herrenknecht Combined Shield offered the necessary adaptability: available in slurry mode as well as in EPB mode depending on the requirements, the HCS machine is optimally prepared for changeable ground conditions.
Additionally, the front area of the machine had to be accessible at all times during the challenge off Miami to allow for tool changes, for instance. For maximum safety a bulkhead with a dive pit was developed especially for the project. Thanks to the bulkhead between the front two machine parts and the overpressure thus enabled, muck and water cannot penetrate into the machine at the tunnel face. Should high water pressures nevertheless lead to flooding, the dive pit allows safe locking into the flooded area.
In the end the safety reserves were not needed. Neither the sophisticated lock system nor the EPB mode of the HCS machine were used. The ground was highly permeable as expected, however the proper design of the cutterhead and the appropriate disc cutters enabled the customer to perform only one maintenance stop, performed under compressed air after a novative ground treatment from the TBM.
"Dorsey" began the drive near the treatment plant on Virginia Key in April 2015. Right from the very first meter the project was characterized by its special requirements: to save space, with a diameter of twelve meters the launch shaft was rather small. At the beginning there was no room for the HSC machine's back-ups and they were only able to be used one by one after 70 meters of tunnelling. For the first section the TBM was therefore pushed forward in pipe jacking mode using a jacking frame adapter developed by the customer, the rest of the tunnel was then lined with concrete segments.
At a depth of up to 21 meters below sea level, the 3.13 meter diameter "Dorsey" dug its way forward in the months that followed. After 227 working days came the breakthrough on Fisher Island on February 16, 2016 – top performances of up to 24 meters per day and about 300 meters per month confirmed the optimum configuration of the TBM. By the end of the year the new 60" discharge pipeline is due to be installed in the finished protection tunnel and put into operation.
The successful drive on the Norris Cut project has pushed the boundaries of what is possible in Florida's tunnelling industry and contributed to its further development: "The project has set standards for work in Florida's underground and showed solutions for deep sewer lines in the porous Fort Thompson Formation," confirms Bernard Theron, President of Bessac.
With the construction of the Port Miami Tunnel already, machine technology from Herrenknecht had demonstrated that even the most complex ground conditions such as the Fort Thompson Formation can be safely mastered with optimally adapted technology. Despite its huge diameter of nearly 13 meters, in 2013 the EPB Shield S-600 reached its target reliably thanks to an additionally installed slurry circuit. According to internationally renowned accounting and consulting firm KPMG, in 2012 the Miami Port Tunnel was one of the ten most innovative transport projects in the world.
More News and Articles
Sep 22, 2023
News
Courtesy of Mcelroy- Mobile App goes live for PPXXI
PPXXI Conference and Exhibition welcomes McElroy Manufacturing, Inc. as the mobile app sponsor. Their sponsorship enhances networking opportunities for the delegates. Scheduled over September 25 -27, 2023, in Lake Buena Vista, Florida, PPXXI is the key technical and business event …
Sep 20, 2023
News
What’s on at Aquatech Amsterdam 2023
Aquatech is the leading water technology show in the world, with over 800 exhibitors and expecting over 22,000 visitors from over 140+ countries.
Sep 18, 2023
News
Cleveland's $3B Project Clean Lake Features Large-Scale Storage Tunnels
Designed to reduce pollution in Lake Erie by four billion gallons per year, Project Clean Lake is a 25-year plan being overseen by Cleveland's Northeast Ohio Regional Sewer District (NEORSD). When construction crews complete the $3 billion undertaking in 2036, …
Sep 13, 2023
News
Mullane rehabilitates heavily deteriorated stormwater pipelines
Mullane once again proved why the company is an industry leader in pipeline solutions with a relining project on the mid north coast of New South Wales.
Sep 11, 2023
News
Pezzimenti Trenchless boasts microtunnelling capabilities
Pezzimenti Trenchless continues to showcase its position as a leading trenchless specialist by completing works on two Victorian projects.
Sep 08, 2023
News
Silvertown Tunnel under Thames - Newham to Greenwich near O2 Arena: See two massive boreholes in east London
The second of two boreholes beneath the Thames – which will together form London’s new Silvertown Tunnel – is now complete.
Sep 04, 2023
News
American Water Issues Sustainability Report
Report highlights American Water’s sustainable impact on communities across the U.S.
Aug 31, 2023
News
Anaergia Selected to Design, Build and Operate Organic Waste-to-Renewable Energy Project in San Diego County
System to provide renewable power, reduce wastewater utility costs, and cut greenhouse gas emissions for East County Advanced Water Purification facility.
Aug 28, 2023
News
Interflow’s spiral wound lining for sustainable pipe maintenance
Spiral wound lining is a sustainable method of pipe maintenance, allowing water authorities and councils to renew their critical infrastructure. Interflow is an expert in this field and has been pioneering new techniques for decades.
Aug 25, 2023
News
The unique challenges of maintaining coastal sewer infrastructure
Loader tells Trenchless Australasia that it can be hard to identify minor issues, meaning that sometimes faults are only seen when there is a system failure. “There’s a range of things that will contribute to damaging the sewer network,” says …
Aug 23, 2023
News
Aqua Metro partners with Yarra Valley Water
Aqua Metro has been awarded a position on the Yarra Valley Water Pipes and Facilities Program of works.
Aug 21, 2023
News
European Commission Regulation restricting lead in PVC supports circular aims of PVC pipe manufacturers
TEPPFA welcomes the new European Commission regulation restricting lead usage in PVC products, setting a new standard in environmental responsibility and public health protection. This regulation supports the ongoing efforts of PVC pipe manufacturers to create a more sustainable circular …
Contact
Herrenknecht AG
Achim Kühn
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 (0) 7824 302-5400
Fax:
+49 (0) 7824 302-4730