No run of the mill mission on the Florida coast near Miami
Oct 12, 2016
In February 2016 construction company Bessac completed work on a protection tunnel in extremely difficult geology in South Florida. In just ten months and using a customized machine designed especially for the mission, a "Herrenknecht Combined Shield" (HCS, diameter 3.13 m), 1,613 meters were tunnelled adhering to the highest safety standards. A new sewer line was installed in the finished tunnel – after half a century in use the old pipe was simply worn out.
The ground conditions and project circumstances of the mission at Norris Cut were anything but standard. Not only did the karstified, permeable geology pose the risk of flooding the machine. The complex Fort Thompson Formation to be tunnelled through was also full of sand-filled cavities. The tunnel face was therefore prone to instability.
For this reason the construction of the protection tunnel for a new sewer line between Virginia Key and Fisher Island required a special and highly flexible machine with exceptional safety features. A Herrenknecht Combined Shield offered the necessary adaptability: available in slurry mode as well as in EPB mode depending on the requirements, the HCS machine is optimally prepared for changeable ground conditions.
Additionally, the front area of the machine had to be accessible at all times during the challenge off Miami to allow for tool changes, for instance. For maximum safety a bulkhead with a dive pit was developed especially for the project. Thanks to the bulkhead between the front two machine parts and the overpressure thus enabled, muck and water cannot penetrate into the machine at the tunnel face. Should high water pressures nevertheless lead to flooding, the dive pit allows safe locking into the flooded area.
In the end the safety reserves were not needed. Neither the sophisticated lock system nor the EPB mode of the HCS machine were used. The ground was highly permeable as expected, however the proper design of the cutterhead and the appropriate disc cutters enabled the customer to perform only one maintenance stop, performed under compressed air after a novative ground treatment from the TBM.
"Dorsey" began the drive near the treatment plant on Virginia Key in April 2015. Right from the very first meter the project was characterized by its special requirements: to save space, with a diameter of twelve meters the launch shaft was rather small. At the beginning there was no room for the HSC machine's back-ups and they were only able to be used one by one after 70 meters of tunnelling. For the first section the TBM was therefore pushed forward in pipe jacking mode using a jacking frame adapter developed by the customer, the rest of the tunnel was then lined with concrete segments.
At a depth of up to 21 meters below sea level, the 3.13 meter diameter "Dorsey" dug its way forward in the months that followed. After 227 working days came the breakthrough on Fisher Island on February 16, 2016 – top performances of up to 24 meters per day and about 300 meters per month confirmed the optimum configuration of the TBM. By the end of the year the new 60" discharge pipeline is due to be installed in the finished protection tunnel and put into operation.
The successful drive on the Norris Cut project has pushed the boundaries of what is possible in Florida's tunnelling industry and contributed to its further development: "The project has set standards for work in Florida's underground and showed solutions for deep sewer lines in the porous Fort Thompson Formation," confirms Bernard Theron, President of Bessac.
With the construction of the Port Miami Tunnel already, machine technology from Herrenknecht had demonstrated that even the most complex ground conditions such as the Fort Thompson Formation can be safely mastered with optimally adapted technology. Despite its huge diameter of nearly 13 meters, in 2013 the EPB Shield S-600 reached its target reliably thanks to an additionally installed slurry circuit. According to internationally renowned accounting and consulting firm KPMG, in 2012 the Miami Port Tunnel was one of the ten most innovative transport projects in the world.
More News and Articles
Dec 06, 2023
News
LeakNavigator saves millions of litres of water
The UK’s largest water and wastewater company, Thames Water, has selected Ovarro’s end-to-end service LeakNavigator to deliver a three-year leakage reduction contract, writes Tony Gwynne, global leakage solutions director at Ovarro.
Dec 04, 2023
News
Water loss reduction initiative expands to Mexico
In an effort to combat water loss, a global collaboration involving organizations from the UK, US, and Mexico is launching a long-term project in Querétaro, Mexico. Utilizing actionable AI, the initiative aims to manage and conserve water resources across 350km …
Dec 01, 2023
News
TBM on site for Melbourne CBD sewer upgrades
A microtunnel boring machine (TBM) has arrived on Elizabeth Street to help deliver one of the biggest upgrades to Melbourne CBD’s sewer network in more than a century.
Nov 29, 2023
News
Shedding light on evaporation
Researchers at MIT (Massachusetts Institute of Technology) have made a groundbreaking discovery that could change our understanding of evaporation, a ubiquitous process in our environment. They found that under certain conditions, light can directly cause evaporation without the need for …
Nov 27, 2023
News
NEW UNITRACC Construction Site Documentation: "Rehabilitation of a DN 400 Concrete Gravity Sewer with a SAERTEX-LINER® MULTI over a Length of 69 m" (CIPP)
New construction site documentation in the renovation section of the e-learning platform: Rehabilitation of a DN 400 concrete gravity sewer with CIPP lining using SAERTEX-LINER® MULTI, type S+ Standard. The objective of this rehabilitation measure was to enhance the structural …
Nov 24, 2023
News
Tracto grundoram supports sewer replacement at coastal town
Budleigh Salterton is a popular and picturesque seaside town situated within the East Devon Area of Outstanding Natural Beauty. Located at the start of the stunning Jurassic Coast; a UNESCO World Heritage Site recognised for its outstanding rocks, fossils and …
Nov 22, 2023
News
Interflow’s sustainability strategy
Having been in business for 86 years, Interflow has proven it knows a thing or two about longevity. Right now, that requires an all-encompassing sustainability strategy, as Richard McCarthy, Interflow’s executive general manager southern region, explained.
Nov 20, 2023
News
Mastering public sector challenges together
An interview with Managing Director Robert Ristow
Nov 17, 2023
News
Tractebel and Aurecon forge strategic partnership to revolutionize dam projects in Queensland, Australia
Tractebel and Aurecon form a strategic alliance to revolutionize dam projects in Queensland, Australia, combining their global expertise and local knowledge to meet the rising demand for dam upgrades.
Nov 15, 2023
News
HDD to help Monarto pipeline project
SA Water will use horizontal directional drilling (HDD) to assist in installing a section of pipe underneath the Melbourne to Adelaide rail corridor.
Nov 13, 2023
News
Neom’s sustainable water solutions with renewable desalination
Saudi Arabia’s visionary city, Neom, is leading the way in sustainable water solutions with the construction of a desalination plant powered entirely by renewable energy.
Contact
Herrenknecht AG
Achim Kühn
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 (0) 7824 302-5400
Fax:
+49 (0) 7824 302-4730