Herrenknecht Vertical GmbH presents its first deep drilling rig
Aug 24, 2006
Herrenknecht AG in Schwanau, a market leader in mechanical tunneling systems, founded Herrenknecht GmbH in response to the worldwide increase in drilling activities and the low availability of drilling capacities on the German market. When designing this very innovative drilling rig, Herrenknecht Vertical GmbH's engineers mainly concentrated on drilling requirements for geothermal projects, because an increasing number of such projects are currently in the planning or implementation stage in Germany.
Considerable noise reduction
The great improvement in noise protection during machine operation is one of the most important innovations. Drilling near inhabited areas is often necessary during geothermal projects. Thus, Herrenknecht Vertical GmbH's engineers integrated comprehensive noise protection measures even during the construction phase of the now completed "HotRock 1" deep drilling rig, which will bore to depths of 3,500m to 5,000m in densely populated areas. The noise pressure level of the 3 slush pumps was significantly reduced by enclosing them in casings, while each of the 1,540kVA generators driving the rig was equipped with optimized exhaust silencers and air flow routing. For the two hydraulic cylinders of the lifting unit, noise reduction was achieved by means of pulsation damping. All these noise protection measures in combination mean the expected noise pressure level at a distance of approx. 150m from the rig is about the same as a domestic TV or radio at normal listening volume.
Maximum safety
The issue of work safety generally plays an important role in the drilling industry. Therefore, Herrenknecht Vertical GmbH also focused on this aspect during the development of the new deep drilling rig. New standards can be set by integrating extensive automation processes (hands off technology). Here, the completely new pipe handling system is unique. All handling of the drilling rods (max. length 19m, max. weight 4.5t) is carried out by means of a pipe handling system. This facility uses a scratch buffer when lifting the rods from their bearings onto the more than 9m high working platform. The horizontal positioning of the rod bearings next to the drilling rig, together with the pipe handling system which can be controlled from the control platform, allows the pipe to be transported safely throughout the entire process. No personnel need work in the hazard zone during this process.
The principle of hands off technology is also applied when tightening or loosening the bolts of the rods. The drilling rods are joined to or separated from the vertical bolting unit using partially automated processes. Since this process is also controlled from the control platform, no personnel need work in the hazard area.
More economic efficiency in drilling
Herrenknecht Vertical GmbH's engineers also investigated the potential for reducing drilling costs when developing the new concept for the deep drilling rig. In geothermal projects the cost of boring drilling holes down to a depth of 5,000m represents the largest portion of the budget and most of the project risk. In order to reduce drilling costs, the electricity for the Herrenknecht Vertical deep drilling rig will be taken from the public power grid. The rig can additionally be operated with commercially available generators. The comprehensive energy management system of the "HotRock 1" and the relevant components makes for considerable savings.
In addition, the overall drilling area can be kept very small in comparison with conventional equipment. The area required to assemble the complete deep drilling rig is no more than approx. 30 x 80m.
The Herrenknecht Vertical unit is optimally equipped for use in geothermal projects. After final testing by the owner, HotRock GmbH (Karlsruhe), the deep drilling rig will be employed in the commercial zone of the municipality of Bellheim (southern Germany). The geothermal power plant which is planned there will later produce 5-6 MW of electric power.
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …
Contact
Herrenknecht AG
77963 Schwanau
Phone:
+49 (0) 7824-302-0
Fax:
+49 (0) 7824-34-03