Bendigo Groundwater Project works on schedule
Jun 16, 2017
Work on the three components of the Coliban Water-managed interim solution for addressing Bendigo's rising groundwater is on schedule to be completed by mid-2017.
The Bendigo Groundwater Project involves the construction of a 5.4 kilometre pipeline connecting a new groundwater treatment plant at the New Moon Mine in Eaglehawk to a new brine storage lagoon at Coliban Water’s Bendigo Water Reclamation Plant in Epsom.
The Victorian Government has provided $29.77 million in funding to manage rising groundwater in mine voids beneath Bendigo. Coliban Water is delivering the project.
Bendigo Groundwater Project Director David Sheehan said work on the pipeline started in April within the plant and is progressing along Simpsons Road towards Lake Neangar.
“The pipeline construction works have been designed to limit inconvenience to residents. The Simpsons Road section is being built using directional boring, a trenchless technique that minimises excavation and prevents damage to trees and root systems.
“There will be some short-term disturbances for residents, such as traffic management and noise. We have notified residents and will communicate directly with any residents affected as the works progress along Simpsons Road,” said Mr. Sheehan.
Construction work on the groundwater treatment plant and brine lagoon has also been progressing well.
“Around 60 per cent of the plant has been built offsite by our contractor in Adelaide. Onsite construction at the New Moon Mine is scheduled to begin next week.
“Despite the heavy rainfall in April, earthworks for the new brine lagoon are 80 per cent finished. Once the earthworks are completed the lagoon will be lined with polyethylene to make it waterproof.
“The brine lagoon will be capable of holding 270 megalitres, the equivalent volume of 108 Olympic-sized swimming pools,” said Mr Sheehan.
Ward Bros from Rochester are the contractors for the brine storage lagoon, Lendlease are building the groundwater treatment plant and Veolia Water Network are constructing the pipeline.
The pipeline, treatment plant and storage lagoon will deliver a four-year solution to manage the rising groundwater in the Central Deborah Gold Mine and mine voids beneath Bendigo. It is scheduled to be fully operational by mid-2017.
The Department of Environment, Land, Water and Planning is working with community, stakeholders and local agencies to identify a long-term solution for managing Bendigo's groundwater.
For further information and the latest updates see our Bendigo Groundwater Project and Planned works and interruptions pages.
More News and Articles
Apr 26, 2024
News
Bothar’s cutting head innovation
The trenchless industry in Australia continues to grow and the need to provide customised solutions becomes vital for a leading subsurface contractor.
Recognising the need for advanced solutions to meet the growing …
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, …
Contact
Coliban Water
37-45 Bridge Street
VIC 3550 Bendigo
Australia