Primus Line® Breathes New Life into Historic Trunk Main in Brisbane
Aug 18, 2021
Urban Utilities relies on trenchless technology for 2.2 km section
One of Brisbane's oldest and most important drinking water pipes runs under Ann Street in the bustling business and nightlife district of Newstead and Fortitude Valley. Earlier this year, Urban Utilities completed a multi-million dollar rehabilitation project on this 130-year-old pipeline.
With the use of the trenchless technology Primus Line®, the project is expected to extend the life of the pipeline by at least 50 years providing an economical solution with minimal impacts to traffic and nearby businesses and residents.
The Ann Street pipeline is a cement-lined, cast iron pipe, and helps to supply water to the city centre and the inner-city suburbs. During the morning and evening peak consumption periods, about 500 litres of water per second flow through the pipe.
Thousands of vehicles a day roll along the four-lane road, which is one of the busiest roads in Brisbane’s central business district. Many car dealerships, restaurants, hotels, offices, residential buildings and several bus stops line the traffic route.
As with many water utilities, replacing water mains in heavily congested urban environments can be a costly and disruptive process. In this case, trenchless technology was the key to success.
Trenchless technologies allow utilities to rehabilitate water pipes that are nearing the end of their service life and "turn back the clock". In this way, security of supply can be ensured for future generations while minimising disruption to existing residents, businesses and traffic – and with significantly less investment than conventional methods.
Given the location of the pipe, flexible lining solution Primus Line® was chosen as it could pass through several bends in the pipe and be installed using a few small pits, to minimise the traffic impact.
Physical and economic evaluation in advance
As Primus Line® is a flexible stand-alone pipeline, which is installed with an annulus gap, it can withstand the operating pressures of the water main, but not the external loads from the traffic on the road above.
The large-scale project at Ann Street was preceded by a detailed condition assessment of the host pipe and economic evaluation, to ensure that the existing pipeline could withstand external loads in the future.
The results showed that the pipeline had sufficient load bearing capacity to allow the use of a semi-structural lining system such as Primus Line® for the desired service life of at least 50 years.
Primus Line® as selected method
Due to its unique three-layer structure, the Primus Liner combines flexibility with extremely high material strength. As a self-supporting pressure pipe liner independent of the old pipe, it absorbs the entire operating pressure, while the old pipe merely functions as a conduit. In accordance with ISO 11295, Primus Line® is an independent pressure pipe liner capable on its own of resisting without failure all internal loads throughout its design life. It has the ability to negotiate bends of up to 45 degrees, allows for seasonal movement of the pipeline and ensures the required operating pressure of up to 11.3 bar.
Despite the reduction in cross-section of the DN 600 pipe, flow calculations showed the client that the installation of a Primus Line® DN 500, with its low friction coefficient of only 0.028, would still provide the required flow.
Field trial
Before the start of the project for the complete renovation section of 2.2 km, a large-scale trial with a length of 350 m was carried out with the Primus Line® system – developed and produced in Germany.
In a single day shift, the pre-folded liner was pulled into the 350 m field trial section of the Ann Street trunk main, formed into its circular shape with compressed air and successfully connected to the pipeline network, demonstrating the speed and versatility of the system.
Start of the major project
The successful completion of the trial marked the start of the implementation of the "Ann Street" project. Detailed design and construction planning was performed in 2019 by Urban Utilities. The initial stages of the project also involved cleaning and prepping the existing pipe to make it suitable for installing the liner.
The installation phase due to its complexity and challenging site conditions, began in mid-2020 and was completed in early 2021. Most of the work took place at night and the small construction pits were closed during the day with large steel plates, to allow traffic to continue to flow.
The entire project was carried out by Urban Utilities’ own workforce. Urban Utilities previously installed Primus Line® on other rehabilitation projects in its service region. At the time, Urban Utilities engaged Primus Line® to provide training to its capital delivery team. Urban Utilities also keeps necessary tools and spare parts in stock to perform Primus Line® installations and to be able to do possible repairs and maintenance in-house. The Primus Line team provided engineering support and accompanied the beginning of the measure with a supervisor.
Four installation sections were necessary to rehabilitate the 2.2 km long pipeline section. The Primus Line® system DN 500 PN 16 was used to rehabilitate the DN 600 water pipeline made of cast iron with cement lining (CICL).
Special DN 500 connectors with a DN 600 flange on the pipeline side ensure the connection to the flange on the host pipe while keeping the pits as small as possible. After commissioning, the pipeline can be operated with an operating pressure of up to 11.3 bar.
Primus Line delivered the four liner sections pre-folded in a U-shape and wound onto drums. The liner insertion into the old pipe is done with a winch. In the process, it also passed through some additional smaller intermedia pits to reinstate valves and offtakes. The liner was pulled through these pits and cut afterwards to install the Primus Line® connectors and the necessary valves and t-pieces.
A pressure test concluded the successful installation before the main was disinfected and returned to operation.
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
Rädlinger primus line GmbH
Kammerdorfer Straße 16
93413 Cham
Germany
Phone:
+49 9971 8088 1505
Fax:
+49 9971 8088 9999