Building a pop-up sewage treatment plant
Apr 13, 2022
When a pipe was struck during routine maintenance near a popular beach, Northumbrian Water’s teams swiftly mobilised to construct a mini treatment works in 48 hours to protect the beach and public from sewage. Treatment works manager Frank Errington talked Utility Week through the engineering feats required for the rapid repairs.
Picture the scene: Saltburn is a popular Yorkshire beach with an adjacent car park next to a miniature golf course accessed via a narrow road. Several meters beneath this tourist hotspot run wastewater pipes to an nearby pumping station. During planned extension to the car park, a third party council worker was driving steel piles down and struck what was initially believed was a network gravity main. When Northumbrian’s team arrived on site, they quickly realised it was a far more complex than first thought and called Errington in.
“It was clear when I got to site it was pumped sewage so I could see it was the rising main that had been compromised,” he explained. “The number one priority was to protect customers and the environment as much as we could so we cordoned the beach off on the first day.” After this the company enacted its standard emergency response for burst rising mains that meant putting in calls to contractors across the northeast to mobilise a small army of experts and engineers.
The damaged pipe runs from a pumping station under Skillet Beck, which flows between the busy beach carpark and a miniature golf course. Therefore the repair had to be made in the stream bed. “There’s no way of diverting the main: it’s a highly pressured 600mm diameter GRP (glass reinforced plastic) wired rising main, which is fairly special because it has wires to over each joint to keep the bolts in place,” Errington said. He noted that the pressure is generally 4.8 to 5 bar, which could pump liquid up to 49 metres into the air.
Engineers had to divert a section of the stream to make the damaged pipe accessible. Tankers, hay bales and hundreds of tonnes of sand and whinstone stone were brought in to stem the flow and act as a rudimentary filtration to catch debris released by the waste pipe.
“We had to empty the main while continuing to pump properly otherwise it would have flooded across Saltburn beach. The flow meant we couldn’t just set up a new pumping station on the site so we utilised the existing one by disconnecting two of the four pumps, connecting temporary overland pipework to existing pumps,” Errington said.
This alone, he explained, was a significant achievement in itself because the pumps were “looking for” signals back from the pipework. “As I was leaving the site on the second night, I realised we needed to really think outside the box, I called a partner company United Rentals first thing on Friday and asked if they could build me a very large primary tank that could get the solids out as the first point of treatment.” A team arrived and got to work straight away on a treatment solution. Six articulated vehicles, three 72,000 litre tanks, two sludge and one of only two rotary drum screens in the country arrived on site on the Saturday morning that gave the capability to treat 150,000 litres of wastewater each hour.
The sewage had to be removed from the broken point. Errington explained the health and safety challenges: “We couldn’t go down and dig at that kind of pressure and flow, so we modified the pipework to direct the flow towards the treatment process we put on the site. It’s processing up to 150,000 litres an hour, depending on the flow.” “It’s fair to say that to build a treatment plant in 48 hours is no mean feat,” he said. “This was a third party incident that caused a non-planned outage – whatever it costs we have to fix it for our customers and the environment.” The Environment Agency has been supportive of the company and its partners’ work to minimise impact from the damaged pipe. Having put in place a stopgap solution, the teams needed a permanent fix. “We’re excavating in two locations to find the line of the main and where the bends are. We have teams of engineers looking at the best options, which may be mass pouring concrete. Our teams are ready to finish the final repair but we need to get the design nailed. As we explore sections of pipe we will get a clearer understanding of what needs doing.”
A week on and although the pop-up treatment works has eased the initial pressure, the break in the main is proving more complicated to repair than first thought because of the pipe’s location, depth, and the specialist fittings needed. The team are digging almost five metres into the ground to expose the pipe and assess what fittings are required. These will then have to be manufactured specially. Given the recent storms, Errington said weather was never far from the teams’ minds. “In the background we had network teams involved to understand what storage capacity there is available in the network. There are effectively three gravity mains feeding into the sewage pumping station. When it was designed someone had foresight to put huge attenuation tanks in place,” he explained. On the Saltburn side there is potential to hold up to six hours worth at normal flow rate and the station has an emergency overflow system. “We have a backup plan but we have a real focus on weather,” he concluded.
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …