Building a pop-up sewage treatment plant
Apr 13, 2022
When a pipe was struck during routine maintenance near a popular beach, Northumbrian Water’s teams swiftly mobilised to construct a mini treatment works in 48 hours to protect the beach and public from sewage. Treatment works manager Frank Errington talked Utility Week through the engineering feats required for the rapid repairs.
Picture the scene: Saltburn is a popular Yorkshire beach with an adjacent car park next to a miniature golf course accessed via a narrow road. Several meters beneath this tourist hotspot run wastewater pipes to an nearby pumping station. During planned extension to the car park, a third party council worker was driving steel piles down and struck what was initially believed was a network gravity main. When Northumbrian’s team arrived on site, they quickly realised it was a far more complex than first thought and called Errington in.
“It was clear when I got to site it was pumped sewage so I could see it was the rising main that had been compromised,” he explained. “The number one priority was to protect customers and the environment as much as we could so we cordoned the beach off on the first day.” After this the company enacted its standard emergency response for burst rising mains that meant putting in calls to contractors across the northeast to mobilise a small army of experts and engineers.
The damaged pipe runs from a pumping station under Skillet Beck, which flows between the busy beach carpark and a miniature golf course. Therefore the repair had to be made in the stream bed. “There’s no way of diverting the main: it’s a highly pressured 600mm diameter GRP (glass reinforced plastic) wired rising main, which is fairly special because it has wires to over each joint to keep the bolts in place,” Errington said. He noted that the pressure is generally 4.8 to 5 bar, which could pump liquid up to 49 metres into the air.
Engineers had to divert a section of the stream to make the damaged pipe accessible. Tankers, hay bales and hundreds of tonnes of sand and whinstone stone were brought in to stem the flow and act as a rudimentary filtration to catch debris released by the waste pipe.
“We had to empty the main while continuing to pump properly otherwise it would have flooded across Saltburn beach. The flow meant we couldn’t just set up a new pumping station on the site so we utilised the existing one by disconnecting two of the four pumps, connecting temporary overland pipework to existing pumps,” Errington said.
This alone, he explained, was a significant achievement in itself because the pumps were “looking for” signals back from the pipework. “As I was leaving the site on the second night, I realised we needed to really think outside the box, I called a partner company United Rentals first thing on Friday and asked if they could build me a very large primary tank that could get the solids out as the first point of treatment.” A team arrived and got to work straight away on a treatment solution. Six articulated vehicles, three 72,000 litre tanks, two sludge and one of only two rotary drum screens in the country arrived on site on the Saturday morning that gave the capability to treat 150,000 litres of wastewater each hour.
The sewage had to be removed from the broken point. Errington explained the health and safety challenges: “We couldn’t go down and dig at that kind of pressure and flow, so we modified the pipework to direct the flow towards the treatment process we put on the site. It’s processing up to 150,000 litres an hour, depending on the flow.” “It’s fair to say that to build a treatment plant in 48 hours is no mean feat,” he said. “This was a third party incident that caused a non-planned outage – whatever it costs we have to fix it for our customers and the environment.” The Environment Agency has been supportive of the company and its partners’ work to minimise impact from the damaged pipe. Having put in place a stopgap solution, the teams needed a permanent fix. “We’re excavating in two locations to find the line of the main and where the bends are. We have teams of engineers looking at the best options, which may be mass pouring concrete. Our teams are ready to finish the final repair but we need to get the design nailed. As we explore sections of pipe we will get a clearer understanding of what needs doing.”
A week on and although the pop-up treatment works has eased the initial pressure, the break in the main is proving more complicated to repair than first thought because of the pipe’s location, depth, and the specialist fittings needed. The team are digging almost five metres into the ground to expose the pipe and assess what fittings are required. These will then have to be manufactured specially. Given the recent storms, Errington said weather was never far from the teams’ minds. “In the background we had network teams involved to understand what storage capacity there is available in the network. There are effectively three gravity mains feeding into the sewage pumping station. When it was designed someone had foresight to put huge attenuation tanks in place,” he explained. On the Saltburn side there is potential to hold up to six hours worth at normal flow rate and the station has an emergency overflow system. “We have a backup plan but we have a real focus on weather,” he concluded.
More News and Articles
Apr 26, 2024
News
Bothar’s cutting head innovation
The trenchless industry in Australia continues to grow and the need to provide customised solutions becomes vital for a leading subsurface contractor.
Recognising the need for advanced solutions to meet the growing …
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, …