Soil removal techniques:

Jacking pipes are jacked either dynamically or statically from a starting shaft to a target shaft. During this process, the soil or rock material loosened by the jacking is transported away, either continuously, in intervals or after the boring is completed [Stein05a].

(Image: Soil displacement techniques)

Soil displacement techniques:
These techniques involve the static or dynamic jacking

(Image: Overview of the methods of trenchless installation of cables and pipelines by jacking or drilling)
(Image: Pros and cons)

Advantages of Trenchless Construction:

  • Groundwater lowering is not necessary
  • Relatively small volume of excavated soil
  • Only road breaking is necessary at the starting and target pits
  • Low impact on traffic, resulting in fewer traffic jams and less strain on residents due to exhaust fumes
  • Less damage to neighboring structures
(Image: Pros and cons)

Disadvantage of Trenchless Technology:

  • Potentially higher costs due to

Jul 31, 2008

Modules

This presentation is part of the series of presentations "Utility Tunnelling" and intends to give an extensive introduction to the topic of trenchless technologies.

Jun 22, 2023

Dokumentationen

Rehabilitation of a DN 400 concrete sewer section with “Lining with Cured-In-Place Pipes” (product name: SAERTEX-LINER® MULTI, type S+ Standard). The aim of the rehabilitation measure was the static strengthening and the restoration of the tightness of the old sewer.

(Image: Presentation of a pipe jacking with an intermediate jacking station)

In this method, jacking pipes are jacked by pressing-in through the subsoil from a starting shaft to a target shaft with the aid of a jacking station as well as intermediate jacking stations.
Jacking in a straight or curved line path is made possible by means of a steerable shield machine positioned at the head of the first pipe. The spoil excavated at the working face is conveyed to the surface through the jacked pipe string.

(Image: View into …
(Image: Attention!)

With reference to the variant used to support the workface or to convey the excavated soil the technical components vary in pipe jacking.

(Image: Schematic presentation of a pipe jacking)

Advantages of trenchless technology compared to the open cut method:

  • Preventing break-up and replacement of road surface
  • Prevention of soil excavation masses
  • Minimizing groundwater retention measures
  • Little impairment to traffic flow especially in inner urban areas
  • Only short-term noise and emission pollution while excavating the starting and target shafts
(Image: Disadvantages of the open cut method for installing drains and sewers (Part 1) [GSTT])

The duties of the shield machine in pipe jacking are as follows [Scher77a] :

  • To protect the personnel,
  • To create the necessary cavity so that the following pipe string can be pressed in with a minimum degree of soil deformation and with the lowest possible skin friction,
  • To protect the cavity until the jacking pipes can finally carry all the loads and forces,
  • To secure the working face against collapsing soil and rock as well as groundwater, and
(Image: Overview of shield machine types)

In jacking processes, extensive and irreparable damages are frequently observed, which is due to irregularities of the subsoil.

Although extensive subsoil investigations can reduce the subsoil risk, failures and damages cannot completely be excluded.

(Image: Attention!)

These are the consequences of damages during pipe jacking:

  • Insufficient quality of the construction execution
  • Delay
  • High costs
  • Environmental impacts
(Image: Distribution of damages in pipe jacking in Germany (source: IFB, Hanover 1993))

Mar 07, 2014

Course

This course includes tutorial services and a final examination. The installation of supply and disposal lines is still mostly performed using the open cut method consisting of digging a trench, laying the pipe under the protection of shoring, and subsequently backfilling the trench. Given the many disadvantages associated with this method along with the growing environmental awareness of the population, it is imperative that trenchless technologies be taken more strongly into account in the planning and construction of pipelines and utility networks. The learning module "Utility tunnelling" is divided into seven lessons, each focusing on a specific topic. The contents of the individual lessons are complemented with a link to more detailed literature. This literature is not relevant to the exam, but serves as a reference for a more in depth look. The module "Utility Tunnelling" ends with a final examination, which references all of the modules content. In order to complete the course successfully, and stress-free within four weeks, we recommend following the following agenda which distributes the different modules evenly over the entire period: 1st week: Module: Introduction, Fundamentals and geotechnical investigations, Pipe jacking (Part 1) 2nd week: Module: Pipe jacking (Part 2), Microtunnelling 3rd week: Module: Jacking pipes, Jacking steering 4th week: Module: Starting and target shafts, Final exam This schedule is only a recommendation, as it is of course up to you when and how you work through the curriculum.

(Image: Microtunnel construction - View of the start shaft with main jacking station and reinforced concrete jacking pipe [FI-FBS])

Hydraulic pipe jacking (see ATV-A 125E or DVGW-W 304 [ATVA125:1996]) [Stein85a] [Conra84b] [Hornu89] [Scher77b] [Stein85e] has been available since the turn of the 20th Century as an alternative to the gallery techniques (heading) and the shield tunnelling with segment lining. This method for the case under consideration …

Today, supply and discharge lines are still predominantly installed by using the open-cut method: a trench is dug, the lines are installed. Under the protection of an embankment or sheeting and the trench is filled afterwards.

In the face of the numerous disadvantages as well as the citizens' growing environmental consciousness in the future it is urgently necessary to take trenchless technology into account much stronger than until today as an alternative …

(Image: Simple hand shield - working face with natural support)

Hand shields are non-mechanised open shield machines in which the soil at the working face is loosened by hand using auxiliary tools (pickaxe, spades, shovels or pneumatic hammer). The removal of the spoil is carried out with the aid of conveyor belts, transport carts or tracked conveying buckets (dump trucks).

Examples:

(Image: Hand shield (external diameter 4672) with working …

(Table: Classification of hand shields according to the type of working face support)

(Image: Attention!)With partial support, the surface of the working face is divided into sections and is either supported by means of natural partial support on bench plates (bench (plate) or platform shields) and/or by means of mechanical partial support using breast plates.

(Image: Hand shield with breast plates - working face with mechanical partial support) (Image: Hand shield with benches (Bench shield) - working face with natural partial support) (…

(Image: Attention!)

Shield machines with partial excavation by hand are predominantly used for:

  • short jacking distances under 50 m
  • crossings of traffic ways
  • jacking of an extraordinary cross-section
  • groundwater-free soil or rock

SM-T1 - areas of application:

  • stable, cohesive soil, i.e. firm-stiff and very stiff cohesive soil (soil class LBM 2 and 3 and/or LBO 2 and 3 according to DIN 18319) with a compressive strength of approx. 1.0 N/mm2
  • Rock with uniaxial compressive strength ≥ 5 N/mm2 (classes FD 2 to 4 and/or FZ 2 to 4)

SM-T2 - areas of application:

  • loose to densely compacted non-cohesive soil (classes LNE 1 to 3 and/or LNW 1 to 3) with a particle size concentration < …