Preparatory Work

Calibration of Connections

Before installing the lining tube, connections must be calibrated and documented according to station and position to ensure that the connections can be found and opened without errors.

After installation of the lining tube, the connections to be opened must be calibrated with the same measuring technique. If possible, the opening should be carried out by the employees who have carried out the calibration first hand.

 