Final Work, Acceptance, Renovation Defects
Quality Control by Documentation of the Rehabilitation Measure
The documents listed below should be submitted to the client:
- Protocols of the CCTV-inspections including the records
- Proof of the preparatory work
- Proof of the reconnection of laterals
- Delivery note of the lining tube
- Recording of the tensile forces determined during winched in place installation
- Documentation of continuously measured pressure, temperature and/or UV light parameters
- Construction diary (site journal)
- Leak tightness test reports.