Xylem delivers emergency bypass in record time following historic rainfall damage to major U.S. sewer main
May 26, 2017
Turnkey solution minimizes environmental impact and maintains service while ensuring regulatory compliance
Xylem a leading global water technology company dedicated to solving the world’s most challenging water issues, designed and built a major emergency sewer bypass in Memphis, Tennessee in just six days. Sixteen inches of rain fell on the city, half of which fell during a two-day deluge, during spring 2016. This unprecedented rainfall eroded the soil supporting a 96-inch sanitary sewer main that carried wastewater to one of the city’s central treatment plants.
City of Memphis officials immediately activated their Emergency Response Plan, bringing Xylem on board to design and develop a turnkey bypass solution to maintain sewer services, minimize the environmental impact and ensure regulatory compliance, while the main line was repaired. The project included the construction of a 2,400-foot-long, 40-foot-wide road through swamp land, so the site could be accessed.
A team of nearly 200 people composed of Xylem engineers, Memphis Public Works and contractor personnel worked in tandem to accelerate the project timeline, completing the entire turnkey bypass operation in record time. Typically this magnitude of bypass pumping would take between two to three weeks to be designed and constructed. However, the Xylem-led team completed the emergency task in just six days.
“At Xylem we pride ourselves on being a 24/7 company. We’re always available with a team of people who use their expertise and experience to solve complex customer challenges every day,” said Ken Albaugh, Regional Director for Xylem’s pump rental business. “This project is a great example of how we use our in-depth experience and resources to rectify an emergency situation, while minimizing environmental impact and ensuring adherence to all regulations.”
Click here to view a video on the project.
“Xylem provided us with the expertise and efficiency we needed in this emergency situation,” said Paul Patterson, Environmental Engineering Administrator for the City of Memphis. “This allowed us to focus our efforts entirely on design and construction and getting the pipe replaced. And that was key.”
The damaged 96-inch sanitary sewer main crossed South Cypress Creek and carried wastewater to the T.E. Maxson Wastewater Treatment Plant in Memphis. The bypass system needed to handle 160 million gallons per day (MGD) of peak flow and traverse 2,400 linear feet from the suction point to the discharge location.
Fourteen Godwin diesel-driven Dri-Prime CD400M rental pumps, two Godwin hydraulically driven CD300M pumps and nearly 30,000 linear feet of HDPE pipe were commissioned as part of the turnkey bypass, successfully pumping 60 to160 million gallons per day of raw sewage daily.
More News and Articles
Jun 05, 2023
Article
Hydrant-locating app launched for standpipe users
A free water hydrant-locating app for standpipe users has been launched by Aquam Water Services. The standpipe supplier developed the app to point permitted customers to the nearest hydrants approved for use by water companies, using information provided by individual …
Jun 02, 2023
News
Focus on pipe protection
Kwik-ZIP centraliser and spacer systems are solving challenges in trenchless pipe installations across Australia and worldwide. Late in 2022, Sydney Water and the West Region Delivery Team (WRDT) contracted Quickway for a water mains installation project. Quickway specialises in transport …
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
Contact
Xylem Inc.
1 International Drive
NY 10573 Rye Brook
United States
Phone:
+1 914 323 5700