World Record. Main Breakthrough on the Epoch-Making Gotthard Project.
Oct 28, 2010
The breakthrough at the Gotthard Base Tunnel on October 15, 2010 in the Eastern tunnel marks the most significant milestone on the way to completing the longest railway tunnel in the world. With the 2 times 57 kilometer long epoch-making project, Switzerland is connecting northern and southern Europe by rail through the Alps. After completion of the project, Herrenknecht Gripper tunnel boring machines have excavated and secured more than 85km of the main tubes.
In 2017, the first high-speed trains will travel along, or rather through, the New Alpine Transversal (NEAT) at speeds of 200 to 250 kilometers per hour. This will cut the journey time from Zurich to Milan by one hour to 2 hours and 40 minutes. Swiss Railways are expecting, in particular, to cut freight transport times - yet another important improvement in traffic logistics between Germany and Italy. A new era in trans-Alpine rail travel is dawning. Setting off from Bahnhofstrasse in Zurich for a morning's leisurely shopping in the stylish Galleria Vittorio Emanuele II in Milan and returning the same afternoon with your shopping bags full of the best Italian designer wear. Only a dream? In 2017, this vision could be reality.
This quick jaunt between the two commercial centers will be made possible by a unique, epoch-making project - the construction of the new Gotthard Base Tunnel along with the Ceneri and Zimmerberg Base Tunnels. With a length of 57 kilometers and a maximum altitude of 550 meters above sea level, i.e. truly at the foot of the St. Gotthard mountain, two single-lane tunnel tubes will cross the Alpine range from valley floor to valley floor, as it were, on an almost level course. This will put an end to travel that was so slow, passengers could almost pick the flowers along the line, and the need for double locomotives to drive freight trains up steep gradients will be a thing of the past.
"This will be a high-speed rail corridor for Europe straight through the Alps, to transport goods in an environmentally friendly way from Rotterdam to Genoa," says Moritz Leuenberger, Swiss Federal Councillor, in describing the 'longest wonder of the world'. "We are working together with our partners on developing Europe's infrastructure, even though we are not members of the EU," he continues. This truly great feat is part of Switzerland's plan to transfer as much freight transport from road to rail as possible, as a way of protecting the environment.
The Alpine country is nearing this goal in leaps and bounds. The 'shell' of the world's longest railway tunnel is almost complete - the final and crucial breakthrough at the halfway point, the border between the Faido and Sedrun construction lots, took place on October 15, 2010. This will mark the completion of one of the most important stages in this spectacular undertaking, which has seen such impressive feats throughout its history. It is the result of almost half a century of intensive planning and has evolved continuously along with technology and geological science. It has also required courageous and farsighted political decisions to be made. The idea of a Gotthard Base Tunnel was first voiced in 1947 - but construction work on the tunnel did not begin until 2001.
More than 85km of the main tubes have been excavated and secured with Herrenknecht tunnel boring machines. These high-tech steel giants from Schwanau, with a length of more than 400 meters and cutterheads measuring 9.5 meters, tunnelled their way through the tremendously hard rock, while the crowds of skiers enjoying the snow some 2,000 meters above in the Lukmanier Pass remain oblivious to the ear-splitting noise and the machine's brute force. Since beginning their mountain-munching journey in 2003, the cutting wheels of the four Herrenknecht machines have 'swallowed' around 10.5 million cubic meters of rock. This is about four times the volume of the Pyramid of Cheops in Giza. Around 75 % of the tunnel's main route have been or are being excavated by these 'mega-moles', as the tunnel boring machines (TBMs) are sometimes known. However, with the sum total of 114 kilometers of parallel tunnels, the project is far from being complete.
A total of 152km if tunnels, shafts and galleries
A total of 152 kilometers of tunnels and shafts need to be created for the Gotthard Base Tunnel project. The planners have divided the two main tunnels and the almost 180 cross passages into five construction phases. The overall construction time could be considerably reduced, because work on the five sections could be carried out simultaneously. However, extensive logistics provisions were also necessary. Access and supply tunnels had to be built, and enormous underground caverns had to be excavated to serve as bases for the tunnelling activities or drill & blast operations.
Between high-precision planning and geological imponderables
Surprises can always occur when boring tunnels the size of the Gotthard project. It is not for nothing that tunnel constructors have great respect for their task. Their work is a tightrope walk between the highly planned and the unforeseeable. In spite of the many preparatory investigations, unexpected difficulties can always occur. For example, at the very beginning of tunnelling from the southern side of the Gotthard in February 2003 - after only 200 meters - work was interrupted by unconsolidated rock. The two TBMs that set off from Bodio - affectionately known to the tunnelling teams as 'Sissi' (S-210) in the eastern tube and 'Heidi' (S-211) in the western tube - encountered geological disturbance zones known as kakirite zones. Such geological conditions are too soft for Gripper TBMs, which are designed for very hard rock, and make rapid tunnelling progress almost impossible. Every meter of excavated tunnel must be secured in a complex process. The machines could not leave these disturbance zones behind them until August 2003, after around 400 meters of tunnelling.
But a construction log can also include unexpected positive reports. For example, there was good news from the northern side in spring 2004. In the construction plan the geologists had predicted a tunnelling interruption of up to four months to deal with the Intschi zone. Luckily, however, this zone was around 50 % shorter than expected, and the teams operating the machines with the innocent-sounding names 'Gabi 1' and 'Gabi 2' were able to pass through the zone, albeit with reduced tunnelling speed. That said, however, the ups and downs in the mountain seemed endless. Good monthly tunnelling performances of 560 m and penetration rates of up to 12 mm per revolution were followed by difficult stretches, some with a penetration rate of only 3 mm per revolution and an advance of only 140 m per month.
The machines also had to deal with changeable geological conditions in the south on the stretch from Bodio to Faido, which impaired tunnelling performances. Noticeable improvements were attained by adapting the two TBMs to the unforeseen circumstances. In December 2005, 'Sissi' achieved the best daily performance in the Gotthard Tunnel so far, with 38 meters in the east tube.
In June and October 2006 the construction teams in the north celebrated the end of tunnelling in the Amsteg - Sedrun section with a spectacular performance. The machines sped towards the end of the construction lot six and nine months ahead of schedule, respectively. But it all ended with an anticlimax. Just before the end of the lot they met with a geological obstacle - kakirite. This is why the TBMs were dismantled in advance in the solid rock zone. The workers then transported the machine components out of the tunnel with the tunnel train.
In the fall of 2006, breakthrough was finally made in the south, too, with the required precision at the Faido multifunctional station. The TBMs with diameters of more than eight meters reached their targets after 13.5 and 14 km respectively, with vertical and horizontal deviations of only a few centimeters. This degree of accuracy is comparable to a marksman hitting a 1 euro coin at a distance of two kilometers. After a total overhaul and a refit with new, larger cutterheads with diameters in excess of nine meters, Sissi and Heidi set off again in July and October 2007, tunnelling northwards from Faido towards Sedrun.
Tunnelling safely through the "ordeal" of the Piora Basin
A further difficult zone awaited the tunnel builders on this stretch - the Piora Basin - a funnel-shaped formation filled with sugargrained dolomite and water, which reaches deep into the rock of the mountain range. Its existence was long known, and hardly any other part of the Gotthard had been investigated as intensely prior to the construction work. Since no one knew how far into the mountain the funnel reached, a decision was taken to make exploratory drills. A horizontal tunnel with a length of around 5.5 kilometers was driven from the cantonal road to the disturbance zone. In 1996, this zone was penetrated. The loose grains of rock turned out to be exposed to the enormous pressure of around 150 bar. A thick jet of water mixed with dolomite shot out of the mountain and flooded the road. The media called it 'D-Day at Piora Beach'.
19 inclined drills were made from the exploratory tunnel to the vicinity of the future base tunnel, finally giving the engineers the all clear. They hit on hard rock with no water pressure. Examining drill cores, temperatures and seismic results brought the geologists to the conclusion that the bottom of the Piora Basin was sealed with gypsiferous cap-rock. And so, on October 12, 2008, Sissi reported: 'Piora Basin successfully crossed', and its sister machine soon followed suit.
Tunnelling using conventional drill & blast methods between the Faido and Sedrun intermediate headings was also an extreme technical challenge. Here, the tunnellers blasted huge underground stations out of the rock. They will serve as special stopping bays for trains in emergencies. The branching tunnel will also allow trains to change from one tube to another during operation. A sophisticated system of transverse and connecting tunnels guarantees that smoke can escape and fresh air can enter the tunnel. The two 'multifunctional stations' are huge construction sites in themselves. Here, the rock presented tunnellers with a particular drill & blast challenge.
The mountain pressure in some sections was so high that the usual method of increasing the target dimensions of the excavating cross section was of no use. Normally, this gives the mountain the opportunity to 'let off steam' - the more it deforms, the more mountain pressure is released. But in the critical zones of the Gotthard Base Tunnel, stability could not be achieved by just permitting deformation. A counterforce was needed against the mountain to stop the cavity from reclosing completely. The solution was to use telescopically slidable rings. In this method, two telescopically slidable steel half-rings are connected to form full rings inside the tunnel cross section, excavated with an overcut of about 70 centimeters. The ring segments slide slowly together under the mountain pressure until their ends meet and they stabilize each other.
56 meters in just 24 hours
After a major overhaul, the two Herrenknecht Gripper TBMs, Gabi 1 and 2, completed the northern Erstfeld-Amsteg section with a length of just over 7 kilometers in 2009. The geological conditions there were almost ideal. This meant a Gotthard tunnelling record could be set in late summer 2009. In the space of only 24 hours, Gabi 2 chomped its way through no less than 56 meters of mountain - a world record for a tunnel boring machine of such dimensions. On June 16 and September 16, 2009, the construction site teams in the north reached their destinations in Amsteg after only 18 months, that is, six months ahead of schedule. This breakthrough was a prime example of the tunnel builders' and the machines' precision. Both TBMs had deviated from the ideal line, horizontally by 4 millimeters and vertically by 8 millimeters - millimeter precision in the truest sense.
At this time, Sissi and Heidi were still working in the mountain in the south. Although Heidi had some problems with a rock collapse in the western tube between Faido and Sedrun in March 2010, the subsequent stabilization measures only interrupted tunnelling until July 2010. Luckily enough, this event had almost no impact whatsoever on the project schedule. Work continues, including that of the two (vault) lining units supplied by the Herrenknecht branch company Maschinen- und Stahlbau Dresden, which follow the two tunnelling 'ladies' at a respectful distance. These 600-meter-long 'worms' lay drainage pipes, install sealing systems and concrete the vaults in twelve-meter stages. In a nutshell, they prepare the tunnel tubes, with top monthly performances of 600 meters, for the installation of the railway technology.
At Herrenknecht headquarters in Schwanau and at the company's Swiss branch we are proud to have supplied the essential technology for the excavation of the Gotthard Base Tunnel, in the form of four TBMs.
On Friday, October 15, 2010, breakthrough was achieved in the eastern tube and an "unhindered view of the Mediterranean" has become a reality. Breakthrough in the western tube is expected to take place in spring 2011. A few years of finishing work will then follow, to turn the tunnel into a functioning high-speed rail route with massive security precautions, for example the two emergency stations where trains can stop in case of danger. Here, passengers will be able to move quickly from one tunnel to the other - each of the two tubes serves as an escape route for its twin. This is a clever solution, which came after lengthy consideration of all the alternatives by all those involved in Switzerland. The work of the tunnel builders and the machines is now approaching its end. And the results are very satisfying. All risks were dealt with, all setbacks were overcome, all emotional rollercoaster rides were survived. And schedules were adhered to, despite the almost unimaginable complexity of the project. Time lost in one place was made up for elsewhere. On the occasion of the last stage goal, the Erstfeld - Amsteg breakthrough - Moritz Leuenberger, Member of the Swiss Federal Council, spoke of a "triumphant victory over the doubters and moaners". His motto was "no matter how high the mountain and no matter how hard the rock, where there's a will there's a way. We can do it, because we want it."
Four Herrenknecht Gripper Tunnel Boring Machines (TBM) bore and secure more than 85 kilometers of the two 57-km long main tubes of the Gotthard Base Tunnel. Gripper TBMs are specialists for hard rock.
Herrenknecht Gripper TBMs “Sissi“ and “Heidi“ in the south: | |
TBM diameter Bodio-Faido: | 8.83m |
TBM diameter Faido-Sedrun: | 9.43m |
Joint Venture - southern section:
TAT Consortium (Tunnel AlpTransit – Ticino): Implenia Industrial Construction, Alpine Bau GmbH, CSC Impresa Costruzioni SA, Hochtief AG, Impregilo SpA
Herrenknecht Gripper TBMs “Gabi I“ and „Gabi II“ in the north: | |
TBM diameter Amsteg-Sedrun: | 9.58m |
TBM diameter Erstfeld-Amsteg: | 9.58m |
Joint Venture - northern section:
AGN Consortium, Gotthard Base Tunnel North: STRABAG AG Tunnelbau Schweiz (CH) / STRABAG AG (A)
1707 | The master builder Morettini from Ticino chipped and blasted a 64m long tunnel through the Chilchberg mountain – it is known as the ‘Urner Loch’ |
1872 | Construction of the first rail tunnel through the Gotthard begins, under the direction of the Swiss engineer Louis Favre. |
1880 | Breakthrough is achieved on February 29, with impressive precision for that time. |
1882 | The longest railway tunnel in the world at the time, with a length of 15 kilometers, goes into operation. |
1969 | Construction of the first road tunnel through the Gotthard begins. |
1980 | The first road tunnel is opened to traffic and connects Göschenen with Airolo. |
1993 | Exploratory drills begin at the Piora Basin |
1996 | The first preparatory and exploratory work for the Gotthard Base Tunnel begins in Sedrun. |
1998 | The Swiss government approves financing for the New Alpine Transversal (NEAT). |
1999 | Excavating activities begin in Sedrun with the first blasting works. |
2001 | The first machine orders are awarded to Herrenknecht. |
2003 | Tunneling work with the four Herrenknecht Gripper TBMs begins. |
2006 | The Herrenknecht TBMs on the northern and southern sections of the Base Tunnel reach their first target –up to nine months ahead of schedule. |
2008 | The dreaded Piora Basin is successfully crossed by the S-210. |
2009 | Mechanized tunnelling is successfully completed in the north. |
October 15, 2010 | Main breakthrough of the Gotthard Base Tunnel in the Eastern tunnel between Sedrun and Faido. |
2017 | The Gotthard Base Tunnel – the centerpiece of the new Alpine transversals – is scheduled to go into operation. |
More News and Articles
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) …
Contact
Herrenknecht AG
77963 Schwanau
Phone:
+49 (0) 7824-302-0
Fax:
+49 (0) 7824-34-03