Water pipeline from Turkey to Cyprus - 1,600 mm diameter PE 100 pipeline and its flange-technology solution
Jul 24, 2014
Planning, dimensioning and construction » Pipe installation
The use of polyethylene pressure pipelines is gaining ever greater international regard and becoming ever more sophisticated.The reasons are diverse, and include this material‘s excellent resistance to corrosion, the flexibility of PE 100 pipes, and the resultant installation and cost benefits.
The construction of the 80 km long drinking-water pipeline through the Mediterranean sets new standards in water supply. Urgently needed by the Turkish Republic of Northern Cyprus (TRNC), it runs from the Turkish mainland (Mersin province) to the Turkish part of the island of Cyprus. Single lengths of 500 m PE pipe are being produced for the TRNC project, and installed tethered to float around 250 m below the surface of the Mediterranean. The otherwise customary seabed installation was not the first-choice solution for this project. One of the reasons was the depth exceeding 1,400 m, interspersed with numerous underwater ridges and trenches, encountered along the installation route.
Figure 1: Elevation of the trans-Mediterranean pipeline route between Turkey and Cyprus. [Source: Reinert-Ritz GmbH]
The plans for this project go back more than fifteen years. The Alaköprü dam at the Turkish side was planned as early as 1998; the installation of the PE 100 pressure pipeline is now merely the conclusion of a long chain of events. Construction of the dam began in the mountains of the province, to the north-east of the Mediterranean town of Anamur, in 2011. The dam is also to be used for the generation of hydroelectric power, as well as storing the water required for the pipeline. From here, the water is transported by pipeline to the Anamur pumping station, and then enters the pressure PE line leading into the Mediterranean. After travelling around 80 km through the sea, the PE pressure pipeline reaches the coast of the Turkish Republic of Northern Cyprus, where the water is pumped into the reservoir of the Geçitköy dam, some 3 km way.
Figure 2: Left: completed stub end at Reinert-Ritz right: stub end, complete with steel encapsulation, pipe extension and bracing. [Source: Reinert-Ritz GmbH]
The specially made flange connectors are welded on to the long PE pipes on site and bolted to the steel pipe yokes by means of a steel flange provided specifically for this purpose. This yoke is then anchored to the seabed by means of steel cables to the securing and anchoring point. The challenge for Reinert-Ritz was that of providing a product to join the PE pipes and steel yokes durably and securely such order that even the most adverse conditions encountered underwater in the Mediterranean could not impair the connection. At a depth of around 250 m, this design involves the following technical challenges: buoyancy forces exerted by the PE 100 pipeline; powerful and dynamic sea currents, high shipping (and submarine) traffic frequency, potential of earthquakes, and the 7 bar operating pressure.
Decision for high quality and safety
The Nordhorn company is the specialist for semi-finished products and full pressure rated fittings conforming to the specified pressure classification for large dimensions up to an outside diameter of d 2000 mm; hence the right address for solutions to demanding problems. With over forty years of experience in plastics and the company’s pronounced quality awareness, the definitive arguments are established for initiating the co-operation between the project planner and Reinert-Ritz. From the high-quality granulate, used for production of the semi-finished products, through to the machining of the finished stub ends, the company was able, with its all- encompassing Quality Assurance system, to guarantee the high production standards vital for the performance and completion of this demanding project. This high quality consciousness has been shaped, in particular, by work for the gas industry in Germany, one of the first customers for PE, which makes use of this material and its high flexural strength in areas subject to mining subsidence. Only then did the safety and cost benefits result - within just fifty years - in PE‘s leadership on the supply-systems market.
It is therefore not surprising that ever more positive experience is being accumulated, with the application of PE pressure-pipe systems in large-scale industrial fire-extinguishing installations and power-generation plants, including the nuclear-energy industry.
There are two production routes for these full pressure- rated fittings: injection moulding and machining. The hollow bars and solid rods made by Reinert-Ritz are used in the latter process. This method assures a product free of voids and incorporating more than forty years of design and processing experience.
Solution of the complex flange concept
Figure 4: A 500 m pipe section in Turkey connecting bolts, on both ends of the steel yoke. The yoke is then anchored to the seabed, to enable the pressure pipeline to "float" at an average depth of 250 m. [Source: Reinert-Ritz GmbH]
Conclusion
The precondition for the success of this project was the successful evolution for the ultra-demanding innovative flange design of a PE 100 fitting which would durably join steel and PE 100. The extreme dynamic loads to which the flanged connection is exposed in underwater service were, above all, taken into account in development. Excellent communications and co-operation between Reinert-Ritz and the project planners achieved successful in-company installation and have generated an extremely high level of confidence for the longterm tightness and safety of the flanged connection.
(Authors: Dragisa Dubocanin, Paul Hutchings and Michael Ritz, Reinert-Ritz GmbH)
More News and Articles
Jun 05, 2023
Article
Hydrant-locating app launched for standpipe users
A free water hydrant-locating app for standpipe users has been launched by Aquam Water Services. The standpipe supplier developed the app to point permitted customers to the nearest hydrants approved for use by water companies, using information provided by individual …
Jun 02, 2023
News
Focus on pipe protection
Kwik-ZIP centraliser and spacer systems are solving challenges in trenchless pipe installations across Australia and worldwide. Late in 2022, Sydney Water and the West Region Delivery Team (WRDT) contracted Quickway for a water mains installation project. Quickway specialises in transport …
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
Contact
Reinert-Ritz GmbH
Dragisa Dubocanin
Ernst-Heinkel-Straße 2
48531 Nordhorn
Germany
Phone:
+49 (0) 5921 8347-0
Fax:
+49 (0) 5921 8347-25