Leaving Stones Unturned - CIPP Leaves Stones Unturned
May 18, 2015
Cured-in-place-pipe technique renews wastewater lateral while sparing landmark bridge
The motherhouse of the Dominican Sisters of Peace was becoming a frequent stop for The Waterworks, a residential and industrial plumbing firm based in Columbus, Ohio. At about 100 years old, the wastewater lateral from the motherhouse to the street was well past its life expectancy. Continued treatments for backups due to root intrusion in the lateral’s widening joints were becoming too much for the antiquated pipe to bear.
Scott Steiner, project coordinator for The Waterworks, said crews used a jet vac and tractor cam to get a clear video of the problem area. Upon seeing it, he said, “We recommended it was time to look into a long-term solution to this problem. They agreed.”
The Waterworks proposed rehabilitating the lateral with cured-in-place-pipe (CIPP) technique, which would create a durable, impervious pipe with improved flow. They could make the repair in a single shift at a fraction of the cost of open cut replacement.
They consulted Mike Moore of Source One Environmental. Headquartered in Davison, Michigan, Source One is HammerHead Trenchless Equipment’s authorized distributor of HydraLiner CIPP tools and consumables.
No trenching
Open cut replacement had been ruled out for a number of reasons, including the need to preserve a historic deck-arch bridge. Most of the 135-foot long manhole-to-manhole run of original line was 8-inch-diameter vitrified clay pipe. But one section was a 50-foot length of 8-inch cast iron that ran through the foundations of the bridge’s century-old stonework at each side of the creek. To cross the creek at continuous grade, the iron pipe had been suspended from brackets attached to the bridge’s underside.
Trenching would not only damage the lawns and gardens of the motherhouse’s property, but it would require partial demolition of the bridge, irreparably degrading its status as a perfectly preserved artifact of the institution’s past. The bridge’s deck supports the only two-way access to the motherhouse. That meant demolition would also reroute all traffic to a one-way drive past the Dominican’s retirement center, the site’s only other access.
"Early estimates to repair the damaged area by closing and trenching the road, partially dismantle the bridge, replace the damaged pipe and then put everything back together were well into six figures,” Steiner said. “And the work would have taken several months. The project was a great candidate for pipe lining through cured-in-place-pipe technique."
Equipment & consumables
HammerHead provided a Super Hydra Inversion Drum, electric wet out table and lining trailer for the installation, as well as a water boiler. Both the drum and boiler were mounted in pickup truck beds, providing ease of transport and good on-site mobility. Jim Mathews, The Waterworks vice president of operations, said, “The setup of that large inversion machine is spot on – easy to move around, user friendly, and holds up to 330 feet of 8-inch felt for mainline work. For this job it was just perfect.”
The CIPP consumables consisted of HammerHead HH felt liner, extended cure resin and extended cure hardener.
HammerHead CIPP specialist Cory Steckmann explained the product choices. “Every job and every jobsite can be different, so liner and resin combinations offer different choices. This job provided good access at both ends, running from one manhole to another, so they chose HH Liner, which can withstand pressure even while unsupported outside the pipe. That way they didn’t need a calibration tube.”
Calibration tubes are flexible sleeves cut to length and closed off at one end before inverting them inside an installed liner. The calibration tube is then inflated to mate the liner to the existing pipe and is maintained at a specified pressure while it cures. Cure times vary. When the CIPP has fully set, the calibration tube is deflated and removed, leaving the new pipe ready for use.
In this application, however, the liner itself was simply tied off at one end after it was installed. Pressure during the cure was maintained with the force of hot water instead of a calibration tube. Thermal-setting resins have a shorter cure time, which was activated in this application by the water’s heat.
Site prep
Mathews said success in this application depended on thorough preparation. “We really did our homework prior to the job, making sure we knew what that system involved. We didn’t rush it, even though it could be seen as an urgent project, since there’s a stream right there we wanted to protect.”
Installers arrived on the site at 8 a.m. Wastewater from the lateral was bypassed to a pumper truck at the run’s upstream manhole. The motherhouse adjusted workflow of its on-site laundry and food service to minimize effluence during the installation. Service continued throughout the installation, however, with minimal disruption to the facility’s normal routines.
The line was cleaned with high pressure jetting before sending the tractor cam in to inspect it for any changes that would pose a problem and to document the condition of the existing pipe immediately prior to rehabilitation.
Wet out
To begin the wet out process, the crew laid the lining out onto the ground and cut it to length. They mixed the epoxy resin’s components to the manufacturer’s specified ratio for this job. Then the crew carefully impregnated the liner with the resin, working it from one end to the other with the electric press on the wet out table, ensuring consistently optimum saturation of each felt fiber.
Use of an extended resin formula gave the crew up to four hours of open working time, since the run was so long. Should an unexpected difficulty arise that required a longer installation window, the delay would not impact the quality of the installation.
Inversion
The impregnated lining was sent inside the existing pipe in a CIPP “inversion process.” The crew first wound the liner, fresh from wet out, onto the Hydra Drum spool. They sealed the drum, fastening the free end of the felt to the inversion collar through the drum nozzle.
When the drum was pressurized with air from a trailer-mounted compressor, it forced the resin-impregnated felt to push out through the nozzle, turning itself resin-side out as it entered the lateral, inverting itself outward until it reached the opposite opening. Inversion began just before 11 a.m., taking only 30 minutes to complete.
Thermally activated curing
The far end of the liner was tied off. The crew now filled the liner with water heated to 176 degrees. Hydraulic pressure inside the pipe forced the lining firmly against the sides of the pipe, holding it there throughout the cure. The HH liner held its shape even under pressure to bridge past fractures and joints, eliminating deformities. To monitor pressure, the installation crew set the inversion drum regulator and opened the air intake. Pressure from the combination of water and compressed air could be read directly from the inversion drum’s gauges.
The resin being used for this project requires thermal assistance to properly cure. Minimum temperature for activation is 130 degrees. Maintaining water temperature at 176 degrees throughout the curing process shortened the cure time. Once activated, the resin’s cure time as calculated for this project’s combination of products and jobsite conditions was just two-and-a-half hours.
Once cured, the closed end of the liner was cut off and water was drained from the pipe. The tractor cam was used again to inspect the installation, providing video documentation of the rehabilitated pipe.
The liner had been installed directly into the existing lateral without and cuts or excavation. Service was restored simply by removing the bypass pump truck and an inflatable 8-inch plug from the line. No restoration work was required.
The new 8-inch CIPP rehabilitation has added at least 50 years to the lateral’s service life and ended any need to deal with root intrusion and backups until at least 2064.
CIPP
Lining the pipe through CIPP literally creates a new composite pipe from the existing pipe and a resin-saturated felt liner. The liner binds to the original pipe’s interior, creating a new pipe with superior durability and improved flow.
Once the liner has been placed in the existing pipe through CIPP’s unique inversion process, it is formed to the pipe under pressure from air, steam or hot water. The type of pressure used matches the components that are chosen for the job and the job’s specifications. Since the impregnated liner will adhere to almost any material, it can be used in pipes made of clay, cast iron, concrete and even PVC.
Lining a wastewater main or lateral generally puts an end to root intrusion, which is the underlying cause of most sewer-related problems. It also prevents wastewater from leaking along the pipe and infiltration by rain or runoff when the ground is saturated.
The liners are flexible enough for bends of up to 90 degrees, improving flow at offsets and joints due to its smoother surface at these transitions. The cured pipe is strong enough to span joint gaps in the existing pipe and can rehabilitate sections where wall fragments are missing.
A properly performed CIPP rehabilitation with quality components adds a minimum of 50 years to the expected service life of the main or lateral.
Cory Steckmann, sales and support specialist for HammerHead lateral products, said about half of his CIPP clients are plumbers or lateral cleaning specialists trained in CIPP technique and no longer subbing it out. Others come to investigate CIPP as a way to expand the plumbing solutions they can offer their customers.
“It’s not hard to learn,” Steckmann said. “But this particular application was done by The Waterworks, who are very experienced in CIPP rehabilitation, offering it through both their residential and industrial divisions.”
Steckmann said this job was an exemplary demonstration of both CIPP and what The Waterworks can do with it. “First, it was quite a long run. Second, they shot the liner under a paved road and through a stone bridge without disturbing them. It would have been impossible to do this with any method other than CIPP.”
More News and Articles
Dec 04, 2023
News
Water loss reduction initiative expands to Mexico
In an effort to combat water loss, a global collaboration involving organizations from the UK, US, and Mexico is launching a long-term project in Querétaro, Mexico. Utilizing actionable AI, the initiative aims to manage and conserve water resources across 350km …
Dec 01, 2023
News
TBM on site for Melbourne CBD sewer upgrades
A microtunnel boring machine (TBM) has arrived on Elizabeth Street to help deliver one of the biggest upgrades to Melbourne CBD’s sewer network in more than a century.
Nov 29, 2023
News
Shedding light on evaporation
Researchers at MIT (Massachusetts Institute of Technology) have made a groundbreaking discovery that could change our understanding of evaporation, a ubiquitous process in our environment. They found that under certain conditions, light can directly cause evaporation without the need for …
Nov 27, 2023
News
NEW UNITRACC Construction Site Documentation: "Rehabilitation of a DN 400 Concrete Gravity Sewer with a SAERTEX-LINER® MULTI over a Length of 69 m" (CIPP)
New construction site documentation in the renovation section of the e-learning platform: Rehabilitation of a DN 400 concrete gravity sewer with CIPP lining using SAERTEX-LINER® MULTI, type S+ Standard. The objective of this rehabilitation measure was to enhance the structural …
Nov 24, 2023
News
Tracto grundoram supports sewer replacement at coastal town
Budleigh Salterton is a popular and picturesque seaside town situated within the East Devon Area of Outstanding Natural Beauty. Located at the start of the stunning Jurassic Coast; a UNESCO World Heritage Site recognised for its outstanding rocks, fossils and …
Nov 22, 2023
News
Interflow’s sustainability strategy
Having been in business for 86 years, Interflow has proven it knows a thing or two about longevity. Right now, that requires an all-encompassing sustainability strategy, as Richard McCarthy, Interflow’s executive general manager southern region, explained.
Nov 20, 2023
News
Mastering public sector challenges together
An interview with Managing Director Robert Ristow
Nov 17, 2023
News
Tractebel and Aurecon forge strategic partnership to revolutionize dam projects in Queensland, Australia
Tractebel and Aurecon form a strategic alliance to revolutionize dam projects in Queensland, Australia, combining their global expertise and local knowledge to meet the rising demand for dam upgrades.
Nov 15, 2023
News
HDD to help Monarto pipeline project
SA Water will use horizontal directional drilling (HDD) to assist in installing a section of pipe underneath the Melbourne to Adelaide rail corridor.
Nov 13, 2023
News
Neom’s sustainable water solutions with renewable desalination
Saudi Arabia’s visionary city, Neom, is leading the way in sustainable water solutions with the construction of a desalination plant powered entirely by renewable energy.
Nov 10, 2023
News
Adept delivers on Geelong infrastructure project
Adept Civil Group has successfully delivered on a sewer reticulation extension project at the Charlemont Rise estate.
Contact
HammerHead Trenchless Equipment
Jason T. Haas
500 South C. P. Avenue
53551 Lake Mills
United States
Phone:
+1 920-648-4848
Fax:
+1 920-648-1781