Tunnelling marathon three quarters complete following whitechapel breakthrough
May 06, 2014
Thousand tonne boring machine Victoria breaks through into Whitechapel station as train tunnels reach 75% complete mark.Over 19 miles (32 kilometres) of tunnelling completed and more than 2.5 million tonnes of earth removed.The Crossrail is being delivered on time and on budget.
Crossrail’s train tunnels are three quarters complete following the breakthrough of Victoria, one of the project’s huge boring machines, into Whitechapel station.
The 150 metre long machine is named after Queen Victoria and began her journey at Limmo Peninsula in east London at the end of 2012. She broke into the huge underground space at Whitechapel where work is taking place 35 metres below the surface to create over a kilometre of new platform and passenger tunnels for the new Crossrail station.During the second half of 2014, whilst tunnelling will continue, the project’s focus will begin to shift to the substantial job of fitting out the stations and tunnels.
The Mayor of London, Boris Johnson, said:
"With three quarters of tunnelling complete, we're tantalisingly close to finishing what is without doubt a monumental feat of engineering. It's quite remarkable what the Crossrail team has achieved so far and we now look forward to the next exciting stage of the project - the fitting out of the Crossrail stations of the future."
Rail Minister Stephen Hammond said:
"Crossrail is set to transform rail travel across the South East when it opens in 2018, improving journeys for thousands of passengers and securing long-term economic benefits across the region and beyond. This is a major milestone in the Crossrail project, and I am delighted with the progress that is being made."
Crossrail Chief Executive Andrew Wolstenholme said:
"Our tunnelling marathon deep beneath the streets of the capital is continuing apace with the construction of the new rail tunnels now three quarters complete. Over the past two years, our huge machines have built more than 19 miles of tunnels and removed more than two million tonnes of earth."
Three of Crossrail’s boring machines have already retired, with a further five still in use.
- In the west, the tunnels between the Royal Oak Portal and Farringdon are complete.
- In the east, Victoria and Elizabeth have reached Whitechapel; Ellie is heading towards Stepney Green and Jessica is being prepared to complete Crossrail’s shortest tunnel drive between Limmo Peninsula and Victoria Dock.
- On the south east section of the route, Sophia has finished her drive and Mary is heading under the Thames.
When Crossrail opens in 2018, it will increase London's rail-based transport network capacity by 10 per cent and dramatically cut journey times across the city, bringing an extra 1.5 million people to within 45 minutes of central London.
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …
Contact
Crossrail Press Office
United Kingdom
Phone:
020 3229 9552