Tunneling for Kane‘ohe-Kailua gravity sewer project complete - boring machine completes three mile journey
Aug 08, 2016
Three miles of tunneling for the City and County of Honolulu’s largest sewer project, the Kane‘ohe-Kailua gravity sewer tunnel is complete. The route linking Kailua Regional Wastewater Treatment Plant (KWWTP) to the Kane‘ohe Wastewater Pre-treatment Facility (KWWPTF) took 13 months to bore through.
This milestone for the first phase of the Kane‘ohe-Kailua gravity sewer tunnel, called a “hole through,” represents the near-completion of the 13-foot diameter, roughly 16,000-foot long tunnel bored at depths of up to 400 feet. “Despite this being the largest sewer project in state history, this critical infrastructure project has had very little impact on our residents while ensuring our public and environmental health and safety for generations to come,” said Mayor Kirk Caldwell. “In addition to using gravity rather than energy, this project provides storage for wet-weather flows, preventing spills when wastewater flows exceed the system’s existing capacity.”
Southland Mole JV completed the 87-foot diameter shaft and sound retention wall at KRWWTP in January, 2015. The tunnel boring machine (TBM) was lowered approximately 77 feet below ground into the Kailua shaft and began boring a 13-foot diameter tunnel in April, 2015. The tunnel hit the halfway point from Kailua to Kane‘ohe in December 2015. Excavation from KWWPTF began August, 2015 in anticipation of the hole-through. The TBM will be dismantled and removed from the Kaneohe shaft, approximately 39 feet below ground level, at the end of June, 2016. The final activity of phase one will be to install and grout a pipeline 10-feet in diameter throughout the tunnel to transport wastewater flows. Pipe installation is expected to commence in August/September 2016.
Phase two of the project is installation of a tunnel influent pump station (TIPS) in the Kailua shaft. TIPS will receive and pump the tunnel flows up to the KWWPTF. The third and final phase of the project is construction of a tunnel influent facility (TIF) at the KWWPTF. Upon completion of all phases, the existing force main that transports wastewater from Kane‘ohe to Kailua will be decommissioned and the flows are expected to be redirected to the new gravity sewer tunnel in 2018.
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
Department of Customer Services
550 South King Street
96813 Honolulu
United States