The Krakow DTW is built to last
Sep 09, 2009
Economic Microtunneling with HOBAS® Jacking Pipe Systems - Establishing the main collector of the Lower Bench of Vistula River (DTW - Dolnej Terasy Wisły) is very important for Krakow, the second largest city in Poland. The city’s growth as well as EU requirements spurred on the extension and modernization of the existing water and sewage system. A large part of the projects is funded by the EU and also the DTW collector is a so-called ISPA project.
Construction works for the collector are conducted in three stages and in two parts regarding contractors.
DTW Collector Part I
The installation of the first part of the Vistula Lower Route collector in Krakow was initiated in March 2008, the line going into service within the next months. This part of the project is realized by a consortium consisting of Hydrobudowa 9 & PRG Metro. Microtunneling was chosen for mainly economic reasons. Since the planned pipeline route runs in 6 m depth nearby the Vistula River where water collects in layers of sand and gravel, the costs for dewatering and excavation works would have been considerably higher than for tunneling.
The pipes used for the project are HOBAS CC-GRP Jacking Pipes with outer diameters of 1,099 and 1,229 mm. Two independent microtunneling machines were utilized and the right amount of lubricant was applied to maximize the progress. The smooth and non-absorbent surface of the pipes doubled the effect of bentonite lubricant so that the installation ran smoothly over the 200 m long drives and without the help of intermediate stations. The latter would only have been activated if allowed jacking forces had been exceeded. Since their help was not needed, the installation speed was doubled.
The achieved jacking rate of up to 25 m per 24 h was the result of the contractors’ experience, the pipes’ properties and good planning. The thrust and reception pits are made of steel piles. This solution has proved its worth in the past and is now an accepted technique in Poland. Pits of any required shape can be made this way, adapted to local conditions and the optimal pipe length, which in this case is 3 m. The piles are extracted once the pipe installation has been completed. Concrete sunk shafts are utilized where intermediate stations are taken out after the pipe has been installed, to make way for a HOBAS CC-GRP Shaft. Due to the high precision of microtunneling it is possible to drill through the provided and temporarily sealed sparings in the reinforced concrete walls. Once the pipeline is laid, the intermediate jacking stations are lifted out and CC-GRP Shafts are placed in the 3 m diameter sunk shafts. Thanks to their comparatively small dimension and low weight, this is done with ease.
It was important for the contractor that all parts of the new collector, such as also manholes and fittings, were prefabricated and from one source, which together with microtunneling guarantee a complete high-quality leak tight system. It was furthermore of great importance to be able to continue installation works during the winter months. Taking the high durability of the pipeline system into account, a pressure line of the system will also be established with CC-GRP utilizing DN 500 Pipes PN 6.
DTW Collector Part II
The remaining 3.4 km line is realized under the direction of INKOP, another contractor specialized in microtunneling. Its construction was commenced in September 2008 and is expected to be completed by the end of 2009.
The works were conducted under similar soil and groundwater conditions as for Part I. Outstanding progress was achieved with installation rates up to 24 m / 12 h. The intermediate stations once again stood still during all drives, even lengths up to 208 m were easily tackled without help. Optimal technological parameters, the smooth surface of HOBAS Pipes and sufficient lubrication applied every 21 m make an efficient and economic realization of the project possible.
Overview | |
Year of Construction | 2008 - 2009 |
Total Length of Pipe | 6500 m |
Pressure Class | PN 1, PN 6 |
Diameter | DE 530, 1099, 1229 |
Installation | Microtunneling, Open trench |
Application | Sewer®, ShaftLine® |
Client | Krakow Waterworks |
Contractor | Hydrobudowa 9, PRG Metro, INKOP. |
Advantages | Ideal for microtunneling, low friction, durability |
Contact:
HOBAS System PolskaSp. z. o. o.
Koksownicza Str. 11
41-300 Dabrowa Górnicza
Poland
PH.: +48.32 639 04 50
Fax: +48.32 639 04 51
E-Mail: hobas.poland@hobas.com
Internet: www.hobas.pl
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.