Stopper Specialists hold back the tide at Medmerry
Jan 22, 2014
Groundforce’s pipe-testing and flow control division, Stopper Specialists, has supplied two of its large diameter Trelleborg Mega Plug inflatable pipe stoppers to contractors working on a major new sea defence project near Selsey on the Sussex coast.
The £28m Medmerry Managed Realignment Scheme has created new sea defences inland from the coast to allow a new intertidal area to form on the seaward side. The project has been undertaken by Team Van Oord, a joint venture between Van Oord, Kier, and local contractor Mackley Construction.
Rather than try to hold back the sea the Environment Agency, as client, chose a ‘managed retreat’ which allows a designated area of marsh to flood at high tides while being exposed during low tides. 7km of earth embankment has been built inland to act as new flood defence, along with a perimeter drainage ditch and sluices in the banks to let freshwater from inland drain out to sea.
To complete the scheme a 110m wide breach in the shingle bank to had to be excavated to allow inundation of the site. Part of this process was to remove an existing outfall structure whilst maintaining the existing flood defence and so the outfall pipes needed to be closed to prevent seawater entering the site. The contractor called in Stopper Specialists to close the pipes using two of its 700 – 1600mm Trelleborg Mega Plugs. These are large cylindrical inflatable plugs some 2.5m long and up to 1.6m in diameter when inflated.
"They are simply lifted into the pipes and inflated to a pressure of 1bar which is enough to seal them in place and withstand the water pressure in the pipe", says Stopper Specialist Technical Sales Representative, Matt Maidment. The plugs are made from tough aramid and Kevlar reinforced rubber with a heavy duty steel core and are designed to create a secure seal quickly and safely.
"These are actually not the largest in the range", says Matt. "We also offer models capable of stopping pipes of up to 2.4m in diameter." Team Van Oord project manager Tony Battrick said that without the Mega Plugs, progress on this element of the job could have been much slower. "We had two solutions: the conventional one of blocking the pipes with masonry or this one, which of course was much quicker.", he says.
The Mega Plugs were lifted into place with a tractor-mounted loading crane and then inflated with a compressor before closing the isolating valves to keep them at the correct pressure. "Once in place, they require no maintenance beyond a daily visual inspection", says Matt. The plugs remained in place for one week, during which time they kept seawater out of the site whilst the excavation of the breach took place.
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
Groundforce
Beckwith Knowle, Otley Road
HG3 1UD Harrogate, North Yorkshire
United Kingdom