Short construction period and high level of safety
Nov 30, 2009
The large-scale sewage treatment plant Czajka, situated to the north-east of Warsaw, is scheduled to be finished in December 2010 – and this after only a two-year construction period. With a cleaning capacity of almost 450,000 cubic metres per day, designed for the equivalent of two million inhabitants, it will be the largest waste-water facility in Poland. Together with the Warbud construction company, PERI´s Polish engineers developed a cost-effective and comprehensive formwork and scaffolding concept which fulfilled all requirements regarding the best-possible concrete surfaces, short construction period and a high level of on-site safety.
System combination for high walls
For forming the eight to eleven metre high reinforced concrete walls, with wall thicknesses between 20 and 75 centimeters, PERI wall formwork systems TRIO, VARIO and RUNDFLEX have been combined. Equipped with appropriate platform systems, these customised complete solutions offer maximum safety for the construction site team as well as fast shuttering times due to the formwork being moved as large-area complete lifting units from cycle to cycle. PERI UP reinforcement scaffold provide here an ideal addition for safe working conditions, and PERI UP stair towers guarantee optimal access to areas of operations.
Increase safety – reduce costs
For the straight wall sections, the TRIO Platform from PERI with regulationapproved working platforms and access ways on all required levels, have proved to be particularly advantageous. For this purpose, TRIO panel formwork with all stipulated working platforms, ladder access and guardrails was mounted to form complete liftable units. As pre-assembly takes place only once, construction site personnel save on any subsequent additional time and effort for modification work.
In addition, the contractor has been using PERI VARIO GT 24 girder wall formwork – likewise complete with a pre-assembled platform system. Here, too, all anchor positions and element connections can be reached without any risk and safe working areas are available for the concreting work. Similarly as with the TRIO Platform, the one-time only assembly at the beginning and the dismantling at the end also ensures enormous time savings with the VARIO formwork system. This means that the usual time-consuming handling of individual brackets and planking every time is no longer necessary.
A well-rounded solution
Construction of sewage treatment plants involves the forming of reinforced concrete walls with a range of different tank diameters. The PERI RUNDFLEX formwork elements used can be adjusted quickly and easily on site in order to match the required radius. The self-cleaning hexagonal thread of the spindles provides continuous fast adjustment. Through the extension splice, panels remain securely connected to each other even at heights of eight metres. Horizontal connections take place using the proven BFD alignment coupler from the TRIO product range. The BFD bridges infill areas of up to ten centimetres thick with only one connection part so that the number of individual components is reduced. This means that a time-consuming search for appropriate fixing devices is no longer necessary. The fact is that particularly with circular formwork systems, such internal and external longitudinal compensations are inevitable and this now results in considerable time savings for the construction crew.
Formwork and scaffolding from one source
PERI plans and supplies formwork and scaffolding from one single source. As a result, all systems can be optimally matched to each other and adapted to the construction progress. For this project, the contractor has been using PERI UP reinforcement scaffold. These scaffold units are extremely stable without requiring anchors and ballast and can therefore be moved without any additional assembly work. The use of lightweight aluminium staircase units extends the areas of application of the PERI UP Rosett modular scaffolding. In those places where walls already concreted prevent direct access to the working areas, PERI UP stair towers provide safe and convenient access for site personnel. In addition, the metric grid system of the PERI UP allows the installation of landing crossings with system decking and standard ledgers – thus avoiding the need of any time-consuming adjustments of tubes and couplers.
Environmental protection – a sector with a future
In Poland, more than 1,000 waste-water treatment plants must be built or modernised in order to fulfill European standards which take effect in 2015. With a price tag of over 500 million euros, Czajka is not only the largest sewage facility in the country, but it is also considered one of the most important environmental protection measures in Europe. The clients are the municipal water and sewage works of Warsaw, whilst project realization is the responsibility of an international consortium – Veolia Water System, Poland; Veolia subsidiary Krüger, Denmark; OTV, France; WTE Wassertechnik, Germany – under the supervision of the Warsaw building contractors, Warbud. As project completion has been carried out in two phases, this has ensured that daily operations have also continued during construction work.
Contact:
PERI GmbH: Schalung Gerüst Engineering
Postfach 12 64
89259 Weissenhorn
PH.: +49 (0)7309.950-0
FAX: +49 (0)7309.951-0
E-Mail: redaktion@peri.de
Internet: www.peri.de
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.