Robbins TBM overcomes high overburden at Olmos
Sep 09, 2008
A 5.3 m (17.4 ft) Robbins TBM is standing up to the pressure in Peru. The Main Beam machine is boring a 13.9 km (8.6 mi) long tunnel through the Andes Mountains, beneath up to 2,000 m (6,500 ft) of hard, potentially squeezing rock.
The TBM was launched in March 2007 for sub-contractor Odebrecht Peru Ingenieria y Construccion, S.A.C (OPIC). General contractor Concesionaria Trasvace Olmos, S.A. won a 20-year build-operate concession from the Peruvian National Government and Lambayeque Regional Government in July 2004.
The machine is boring in complex geology consisting of quartz porphyry, andesite, and tuff from 60 to 225 MPa (8,700 to 32,600 psi) UCS. Over 400 fault lines are present along the entire tunnel, including two major fault lines approximately 50 m (160 ft) wide. The overburden has created another problem — high in-tunnel temperature, predicted to exceed 54 degrees Celsius (130 degrees Fahrenheit). To cope with the high temperature Robbins has designed the machine with a unique ventilation and air cooling system. Two interacting systems are being used to cool the tunnel to 32 degrees Celsius (90 degrees Fahrenheit) or below. The high jobsite elevation (1,080 m / 3,500 ft) results in less dense air and less heat transfer capacity per cubic meter of air, so the two systems will make it possible to blow more air into the tunnel for a maximum cooling effect.
The Robbins machine has overcome not only tough geological conditions but also unpredictable weather. A flood in April 2008 covered the jobsite in a thick layer of mud and debris and washed out the only access road leading to the construction area. Despite the three-week delay the machine is still on schedule for a projected finish in March 2009. The machine is now averaging 3.2 m (10.5 ft) per hour, with production rates of up to 38.3 m (126 ft) per day. As of August 2008 the TBM had advanced 6,000 m (20,000 ft).
By March 2010, the first phase of the tunnel project will be operational and will supply more than 2 billion cubic meters (500 billion gallons) of water annually for irrigation of 560 km2 (130,000 acres) of farmland. The second phase will involve construction of at least two more drill and blast tunnels and two stations for hydroelectric power. The facilities will be capable of generating 600 MW each.
Contact:
The Robbins Company (Headquarters)
29100 Hall Street
Suite 100
Solon, OH 44139
USA
Brianna Home, Marketing Director
Desiree Willis, Technical Writer
Email: marketing@robbinstbm.com
Phone: +1 253 872 0500
Fax: +1 440 248 1702
Web: www.robbinstmb.com
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.