Robbins Double Shield completes Marathon Mileage
Feb 01, 2011
Hard-Working TBM breaks through at China’s Pinglu Tunnel
More than 500 people gathered at the breakthrough ceremony in a remote area of Shanxi Province to mark the occasion. “The key to this project’s success was the crew. We had the right mix of experienced people and young people hungry to learn,” said Paul Bargmann, Head of the Machinery Dept. for Alpine Bau GmbH. The Robbins machine successfully mined through difficult geology including coal seams and abrasive sandstone with up to 70% quartzite content. Advance rates topped out at 50 ring sets, or about 70 m (230 ft), per day.
The machine was previously used on a record-breaking 12 km (7 mi) long segment of the Yellow River Diversion in 2000. On that project, the TBM set two world records in its size class of 4 to 5 m (13 to 16 ft): best month (1,855 m/ 6,085 ft) and monthly average (1,352 m/ 4,435 ft). Both records still stand.
Though the TBM was already designed for similar geology and kept to its original specifications for the Pinglu Tunnel, the back-up was modified. “The back-up frame was extended from one stroke to two strokes. This was a key change, especially for such a long tunnel,” said Meik Mueller, Technical Director for Alpine’s Asia Division. The modification allowed the machine to maintain good advance rates despite transit times of up to 70 minutes for muck trains traveling from the machine to tunnel entrance.
Lining for the Pinglu Tunnel, consisting of unique hexagonal segments, was produced near the jobsite by Alpine. A crew of nearly 400 people worked at the remote site and segment factory to cast the specialized structures. During tunneling, the segments were placed in rings of four elements, in a honeycomb configuration staggered longitudinally. The design was created to allow for high-speed, continuous boring with no downtime while erecting segments.
The completed Pinglu Tunnel will go into operation in October 2011, connecting to the North Main Line of the Yellow River Project to transfer water to Pinglu, Shuozhou, and Datong areas. Over 100 km (62 mi) of the South Main Line were excavated by five TBMs, including four Robbins Double Shields, between 1999 and 2001. The entire scheme will transfer water from the Yellow River to dry regions of Shanxi Province, an area that receives just 400 mm (16 in) of rainfall per year on average.
The Robbins Company
29100 Hall Street
Solon, OH 44139
USA
Tel.: +1 440 248 3303
Fax: +1 440 248 1702
Email: sales@robbinstbm.com
Internet: http://www.robbinstbm.com/
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
The Robbins Company
44139 Solon, OH. USA
Phone:
+1 440 248 3303
Fax:
+1 440 248 1702