Records tumble at the Cabrera Tunnel: Never before has a TBM tunnelled so fast
Jan 02, 2009
The two tunnel tubes of the Cabrera Railway Tunnel near Valencia are completed: The Herrenknecht Double Shield tunnel boring machine (TBM) S-373 achieved breakthrough after the second tunnel on September 25, 2008 – 5 months ahead of schedule. This means that the planned overall construction time was cut by a quarter. Tunnelling performances of up to 106 meters per day were achieved during the completion of the shell of the two approx. 6,000 meter long tubes, so that the tunnel was ready to "accommodate" the railway technology in only 14 months.
First record as early as November 2007
Construction work for the first tunnel tube started already three and a half months after the factory acceptance of the TBM in Schwanau on April 12, 2007. Top daily performances of up to 83.2 meters showed that the S-373 tunnel boring machine was optimally designed for the geology. In November 2007 alone, a total of 1,600 meters of tunnel were excavated. The tunnelling of the first tube was completed only six months after the beginning of the construction work. At that time, the Herrenknecht branch manger Juan Arroyo forecast the following for the completion of the second tube: "If everything continuous to runs smoothly, we can finish work in December 2008". His estimate was not completely accurate. Because tunnelling work was completed already at the end of September 2008. For the construction of the second tube, the site was logistically equipped in such a way that the tunnelling performances outmatched those achieved in the first tube. The lining segments were produced around the clock, and the production of the mortar to fill the space between the lining segments was extended correspondingly, so that the double amount of material was available all the time. After the beginning of the tunnelling work on the 2nd tube on May 5, 2008, the team achieved weekly performances of more than 400 meters on several occasions; on average, the machine excavated 284 meters of tunnel per week and laid 178 lining segments.
Double Shield TBM allows non-stop tunnelling
The Herrenknecht Double Shield TBM with a diameter of 9.69 meters drilled continuously through the rock. The TBM held fast to the rock using gripper plates, creating the necessary contact pressures for the tunnelling work. At the same time the lining segments were installed with the help of the lining segment erector. Concrete segments weighing up to 8.8 tonnes and one keystone create a ring with a width of 1.6 meters thus forming the frame of the tunnel.
The Spanish Herrenknecht branch managers Francisco Avila Aranda and Juan Arroyo mentioned several factors to explain the speedy progress in the tunnelling activities: the experienced construction site team of FCC Construcción S.A. and Construcciones Sanchez Dominguez-Sando S.A., the logistics system which was planned in detail and the tunnel boring machine which was precisely adapted to the geology consisting of hard limestone. Consultant and tunnelling expert, such as Dr. Ingeniero de Caminos, Canales y Puertos Don Felipe Mendaña are impressed at the speed achieved by the machine and the construction site team: "The right machine type was chosen for the geology: a double shield. This made it possible to carry out almost 100% of the tunnelling work in the "double shield mode", allowing the simultaneous installation of the tunnel lining and the excavation work. Furthermore, the construction site team, excellently trained and coordinated by the construction company and the perfect logistics system contributed to this extraordinary performance."
The La Cabrera Railway Tunnel
The La Cabrera Tunnel crosses beneath the Sierra de La Cabrera and overcomes a difference in height of around 170 meters with a gradient of up to almost 3 percent between the western and eastern portal. As part of the extension of the high speed railway network between Madrid and Valencia, the tunnel forms the core part of the 11.2 kilometer long section "Siete Aguas-Buñol". The plan is to put the tunnel into operation at the end of 2010, after the installation of the necessary railway technology.
Tunnelling performances in figures
1st tube
Beginning of the construction work: July 27, 2007
Completion: January 25, 2008
Tunnel length: 5,974.4m
Top daily performance: 83.2m / 52 lining segment rings (December 1, 2007)
Top weekly performance: 430.4m / 269 lining segment rings (week 47/2007)
Top monthly performance: 1,600m / 1,000 lining segment rings (November 2007)
2nd tube
Beginning of the construction work: May 5, 2008
Completion: September 25, 2008
Tunnel length: 5,966.4m
Top daily performance: 105.6 m / 66 lining segment rings (July 19, 2008)
Top weekly performance: 435 m / 290 lining segment weeks (wekk 30/2008)
Top monthly performance: 1,688m / 1,055 lining segment rings (July 2008)
Contact:
HERRENKNECHT AG.
Achim Kühn
Schlehenweg 2
77963 Schwanau
PH.: +49 (0) 7824-302-0
FAX: +49 (0) 7824-34-03
E-Mail: pr@herrenknecht.de
Internet: www.herrenknecht.de
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
Herrenknecht AG
77963 Schwanau
Phone:
+49 (0) 7824-302-0
Fax:
+49 (0) 7824-34-03