Ramming Hammers for Supporting HDD Set Up
May 03, 2013
Trenchless installation of pipelines
U Mole not only offers a range of trenchless technology equipment for the direct installation of new pipe line in the form of its range of US-designed and manufactured HammerHead impact and ramming hammers, it also offers the ability to aid other trenchless systems achieve greater production rates through difficult ground conditions. One such technique is Horizontal Directional Drilling (commonly known as HDD).
HDD has been around as a technique for several decades now and has become established as a significant and widely used technique in the area of new installations of pipeline, particularly for crossing works under roads, rail tracks and other significant obstacles/buildings where open trench operations would be difficult if not impossible.
However, on many occasions one of the most difficult aspects of an HDD project is setting up the drilling machine in less than favourable ground conditions, such as sand, gravel and similar ground conditions where the ground may have the propensity to ‘run’ if not correctly controlled. As these ground conditions are often found near the start point of a bore it can make launching the pilot drill head and drill string correctly into the ground at the required angle of attack difficult. This can caused significant problems in trying to establish the required bore path early in the pilot bore and may even cause misalignment of the bore that would require potentially time consuming and expensive remedial work to correct once started.
One method that has been developed to help overcome this set of circumstances is the use of the Hammerhead pipe ramming hammers to install a washover pipe through the less competent ground near surface to enable the drill string to reach a solid ground horizon effectively.
Washover Pipe Installation
To achieve the washover pipe installation, depending on the length and depth to which the pipe needs to reach, a length of steel pipe is set up at the launch point of the HDD bore on the line of the bore and at the inclination required for the start of the HDD pilot run. A HammerHead ramming hammer is then used to push the steel pipe into the ground. If the length of the washover pipe is greater than that of the first length of steel pipe, additional lengths can be welded onto the lead pipe as required.
The lead end of the steel pipe may be fitted with a cutting shoe to help maintain the advance of during the ramming process but also help maintain the desired direction of the ram. It may also assist in engaging the lead end of the washover pipe into the competent ground that it is intended to reach, minimising ground loss at the washover pipe competent horizon interface.
A pre-project site investigation will have determined the length and depth the rammed washover pipe will needed to reach to ensure the pilot drill head cuts into more competent ground and so establish the correct start for the pilot bore.
Once the washover pipe has been installed, spoil inside it can be removed if required. The pilot drill head and drill string is then launched from the drilling rig directly into the competent ground without having to negotiate the potential interference of the loose ground through which the washover pipe has been rammed.
It is usual that the washover pipe would be of a dimension that would allow the final installed pipe being pulled in by the drilling rig to pass through it to surface so as not to interfere with the final pipe installation.
Depending on the project requirements, in some instances the washover pipe may be extracted once the final product pipe has been installed using the HDD rig. This may allow a sub-surface connection to another section of the product pipeline to be made. But this is not always the case and the washover pipe may be retained in position as an added protection or casing for the product pipe as it approaches the surface.
Frank Gowdy, Sale Director for U Mole said of the technique:
“We have provided some of our HammerHead ramming hammers to clients for just this type of operation because the units are easy ti handle, powerful and cost-effective in what is often a limited access area on many HDD projects. The advantages that installing a washover pipe can bring to the start of an HDD pilot bore more often than out weigh any additional costs that this initial set up work may add to the project given the potentially huge costs of rescuing a bore that has failed in unstable ground before it really begun.”
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
Groundforce
Otley Road
HG3 1UD Harrogate
United Kingdom
Phone:
+44 1423 852 295
Fax:
+44 1423 536731