Quality proves its worth
Jan 07, 2015
Sewer rehabilitation with SPR™ technology in Budapest, Hungary
With the consistent application of Spiral-Wound technology along several kilometers and for several years, Budapest has developed into a model city for Spiral-Wound pipe rehabilitation in Europe. The individual versions of the technology are suitable for different rehabilitation requirements with various diameters and shapes of sewer networks. Since 2010, approx. 18,861 m lengths of round as well as custom shaped profiles have been rehabilitated in Hungary and thereof 5,869 m beneath the Budapest city centre.
With the latest large profile rehabilitation project in the north-east of Budapest, the technology demonstrated again its wide range of capabilities. SEKISUI SPR rehabilitated together with its construction partner Agriapipe 565 metres of the strong corroded cement pipe with dimensions of 1400 x 2100 mm underneath the Pozsonyi Street. From the end of June to the beginning of October 2014, the pipe rehabilitation team repaired the egg-shaped sewer while maintaining a controlled live flow using the SPR™ Spiral-Wound pipe method.
The Spiral-Wound technology from SEKISUI SPR is already a familiar rehabilitation solution for the city of Budapest. The city has, since 2010, been impressed by the low costs, brief construction times as well as the longevity of the trenchless rehabilitation technology. After approx. 18,861 metres of successfully rehabilitated sewer pipes in Hungary and 5,869 m underneath the city life of Budapest, the Spiral-Wound method has proven its worth. Most recently, the Spiral-Wound pipe system showed its potential in the trenchless rehabilitation of 54 m of the egg-shaped sewer underneath Pozsonyi Street in 2013, and of an additional 565 metres in the summer of 2014.
"Since the sewer network of Budapest features various diameters and shapes, the Spiral-Wound technology with its different method versions is the ideal solution for the operators. This provides a rehabilitation process for all standard diameters in circular form, but in particular, with SPR™, also for the most diverse custom shapes, such as box or mouth-shaped, or even egg-shaped profiles, up to 5500 mm," commented Mr. Zoltán Varga, the Managing Director of Agriapipe Ltd, the construction partner. A central aspect in the selection of the Spiral-Wound method several years ago was also the requirement for the necessary structural integrity of the old structures to be re-established. Additionally it is an advantage that work can be carried out exclusively through existing manholes so that there are hardly any hindrances for the local residents as well as the street traffic of this megacity during the rehabilitation.
Year |
Location |
Spiral-Wound Technology |
Diameter (mm) |
Length(m) |
2010 | Budapest, Hungary | SPRTM RO | 800 | 273 |
2010 | Budapest, Hungary | SPRTM | 1350 | 31 |
2010 | Budapest, Hungary | SPRTM EX | 300 | 700 |
2011 | Budapest, Hungary | SPRTM | 1200,1800 | 156 |
2011 | Budapest, Hungary | SPRTM EX | 300 | 668 |
2012 | Budapest, Hungary | SPRTM EX | 500,400,300 | 917 |
2013 | Budapest, Hungary | SPRTM EX | 200,300,400 | 2505 |
2013 | Budapest, Hungary | SPRTM | 1400/2100 | 54 |
2014 | Budapest, Hungary | SPRTM | 1400/2100 | 565 |
Variants of Spiral-Wound technology
The Spiral-Wound pipe method is based on the principle of the mechanical in-situ production of a liner made of extruded plastic profile strips. The process produces liners for nominal widths of 200 to 5500 mm by a winding machine that pushes the Spiral-Wound profile in the host pipe or – depending on the process version – leads the Spiral-Wound liner through the structure. By standard, PVC-U profile strips are installed with the Spiral-Wound pipe technologies with differently structured locking systems, depending on the procedure.
One exception is the SPR™ PE method in which an HDPE profile strip is used and the mechanical lock is replaced by a PE welding connection. The three Spiral-Wound pipe methods SPR™, SPR™ EX and SPR™ RO, which have been used in Budapest for years as a model for future-oriented sewer rehabilitation, differ in particular according to two important features: On the one hand with regard to the static stability, on the other hand, the positioning of the winding machine in the winding process.
The well-established Spiral-Wound pipe methods SPR™ EX and SPR™ RO wind the liner without annular space into the host pipe. In the end a close-fit liner with minimal cross-section reduction is created that allows an increased flow rate due to the low roughness of the material. If an annular space is created during the winding process, the necessary grouting with high-strength grout serves as a structural component on the SPR™ liner or with sealing material as insulation for the SPR™ PE method.
SPRTM |
SPRTM PE |
SPRTM EX |
SPRTM RO |
|
Diameter |
800 – 5500 mm
|
900 – 3000 mm
|
200 – 750 mm
|
800 – 1500 mm
|
Material |
PVC-U
|
HDPE
|
PVC-U
|
PVC-U
|
Shape |
Circular, egg, mouth and any other
|
Circular
|
Circular
|
Circular
|
Annular space |
Annular space
|
Annular space
|
Close-fit
|
Close-fit
|
Winding machine |
running ahead
|
firmly stationed
|
firmly stationed
|
running ahead
|
Host pipe condition class type II
Budapest Sewage Works Pte Ltd. operates the complete 5400 km long sewer system of the metropolis. Underneath there is also a 730 m long cement pipe with a diameter of 1400 x 2100 mm that drains collected rain and wastewater of the district 13, in the north-east of Budapest into the wastewater treatment plant. The combined wastewater sewer, which has been in operation since 1907, exhibits material fatigue due to non-stop operation over the years as well as cracks and damage due to corrosion. Bacteria and caustic sulphuric acid inside the pipes have attacked the cement even though the concentration is low due to the common draining of wastewater and rainwater. The damage also decreased the structural stability of the concrete sewer.
The egg-shaped sewer in need of rehabilitation is located under the very busy main road, Pozsonyi Street, in the 13th district of downtown Budapest. In addition, buses come through every 5 minutes in the bus lane between the two lanes in each direction. For rehabilitation through standard manholes, only a few meters around the access needed to be blocked off for the equipment and the rehabilitation vehicle. There was hardly any hindrance for traffic above ground even though the rehabilitation project underground was rather large and many metres in length.
Winding process during controlled live flow
The 565 metre long ailing sewer section was rehabilitated with the SPR™ Spiral-Wound method by winding a steel-reinforced profile strip of PVC-U into a new highly resistant plastics inner layer directly within the host pipe. For that, the guide frame of the Spiral-Wound machine was lowered through a standard manhole into the rehabilitation section, installed into the host pipe directly and adjusted to the egg-shaped profile of the sewer while taking the statically required annular space into account. The 52 Spiral-Wound pipe spools stationed one after another above ground supplied the winding machine continuously with profile strips via the standard manhole. The winding machine moved forward with every rotation by one profile width and locked the profile with a tongue-and-groove mechanism to create a watertight liner. Once one of the 52 Spiral-Wound pipe spools was used up, the new profile strip was joined in a portable butt welding unit.
The winding process was carried out during controlled live flow in the old sewer. A masonry wall was built at the upstream point so that the pump could transfer the combined wastewater into the following sewer section. After about 250 metres of rehabilitated sewer section, the stone wall was moved from the upstream point into the middle of the rehabilitation section to control the live flow for the remaining metres to be rehabilitated. The goal was to maintain a water level of maximum 15 cm. Heavy rainfall posed a challenge occasionally as the water level rose to 1 metre and the winding process had to be interrupted briefly. Since the winding machine always remained stationed in the old sewer, winding could resume promptly after the water level had dropped and the pipe was cleaned.
Grouting
The winding process aimed to generate a defined annular space between the Spiral-Wound liner and the host pipe, which was filled with a high-strength grout in a subsequent work step. The thickness of the annular space is determined according to the following principle: as little annular space as possible, but as much annular space as necessary for the required static properties. In this case, the thickness was between 50 mm and 80 mm.
After the Spiral-Wound liner was completed, a bracing system was installed so that the annular space could be filled. The bracing frames positioned the Spiral-Wound pipe liner according to the static requirements and thus prevented buoyancy, a positional deviation and deformation during the subsequent grouting. The annular space was sealed after each 80-metre section of installation length and filled up in layers with special grout to re-establish the static features of each section.
Durable corrosion protection of the concrete structure
In the long term, the new rehabilitated pipe offers an important operational advantage: Since the steel-reinforced plastic Spiral-Wound pipe liner is not a temporary aid for installation, but rather remains a fixed design component of the rehabilitation solution, it permanently protects the host pipe and the filled-in annular space grout against mechanical abrasion and attack by the combined wastewater. In the end, the SPR™ Spiral-Wound pipe liner therefore serves as formwork for a new mineral grouting of the old sewer and as a reliable protective coating over many years that separates the concrete structure from the combined wastewater. The smooth and abrasion-resistant surface of the SPR™ liner will improve the hydraulic capacity minimum for the next 50 years of continuous operation and compensates for the minimal cross-section reduction of the host pipe.
A fine conclusion
As the final step, the reconnection of the grouting sections and laterals were done as usual. During this year's rehabilitation project, the SPR™ technology not only proved to be durable and economic, but also a rehabilitation method that can be accomplished comparatively quickly. After the city ordered the works, successful completion of the rehabilitation of the sewer section was planned for just 15 weeks later on the construction schedule.
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
SEKISUI SPR Group
Lena Tiedeken
Julius-Müller-Str. 6
32816 Schieder-Schwalenberg
Germany
Phone:
+49 (0) 162/ 105 07 86