Power plant pipeline for the Bristen power plant in the canton of Uri
Aug 16, 2022
DN 1000 power plant pipeline
Figure 1: Transporting the DN 1000 ductile iron pipes in the Maderaner valley [Source: Werner Volkart]
1 Planning and approval phase
In 2008 the planning phase commenced for the Bristen power plant in the Swiss canton of Uri. The planning and official negotiations dragged on for eight years. Eight years during which a detailed utilisation and implementation plan was drawn up for a hydropower plant.
After all these efforts, the Bristen hydropower plant in the Maderaner valley is one of the most environmentally friendly ones in the whole of Europe. In March 2015, the time finally came: the positive report from the Swiss Nature and Homeland Security Commission (ENHK) was submitted in which it is unequivocally stated that the project at the Chärstelenbach meets the requirements for maximum possible environmental protection [1].
2 Choice of pipe material
Three months later the district of Silenen issued the construction permit. To be considered as the largest structural challenge, in addition to the completion of the water catchment, is the installation of the pressure pipeline in the upper section of the route as far as the catchment area, a difficult task in both topographical and geological terms. In total, the route of the pipeline extends over 1,800 m, for the main part through impassable terrain. For the pipe material, the operator opted for DN 1000 ductile iron pipes in the thrust and tractive restraint design. These were supplied by the Swiss pipe specialist TMH Hagenbucher AG from Zürich.
Ductile iron pipes are perfectly suited to these conditions. This is not merely to do with the high degree of resistance and the long working life of the pipes, but also their simplicity of installation: the trench is excavated and the pipe is aligned on the bottom of the trench. With the help of the restrained push-in joint, the next pipe is assembled and the trench is ready for backfilling again. This means that the construction site remains very manageable. A further advantage of ductile iron pipes lies in the fact that they can be laid in rocky ground without any special bedding material [2].
3 Logistics
Because of the topography and the roughness of the terrain, the Epp construction company from Bristen (Switzerland), the Arnold AG installation company from Schattdorf (Switzerland), the pipe manufacturer Duktus (Wetzlar) GmbH & Co. KG from Wetzlar (Germany) and the pipe supplier TMH Hagenbucher AG from Zürich (Switzerland) were facing a challenging logistical task. This was further aggravated by the fact that a total of 50 special adapter pipes had to be made to measure at short notice so as to be able to adjust the pipeline to its route. At this point the experience of the pipe supplier and their technical equipment for working with the ductile iron pipes were of the highest value.
4 Construction of the pipeline
The construction of the pipeline began in April 2016. In the initial phase the DN 1000 ductile iron pipes had to be transported from their storage location at Amsteg im Reuss valley along 3 km of mountain road in the Maderaner valley to Bristen. A tractor with trailer was used for this which, loaded with up to three pipes, was manoeuvred along the narrow, winding road (Figure 1).
From this interim storage area onwards, a crawler excavator then carried each pipe individually to the pipe trench. The power plant pipeline was built uphill, against the direction of flow, so that the pipes and fittings had to be assembled “upside-down” (Figure 2).
In the normal case, to do this the pipe trench was excavated over a length of around 6 m, the pipe aligned and the trench backfilled directly afterwards. An excavator with a screening bucket was used for this, so that the excavated material could be broken up and put back straightaway. Thanks to the efficient chain of transport, the reliable BLS® restrained push-in joint, which can be safely and rapidly assembled even under these difficult installation conditions, and the robust exterior protection of the pipes with cement mortar coating, the experienced assembly engineers from Arnold AG (Rohreinbau) were able to work at a rate of up to 60 m a day.
The special pipes, such as the adapter pieces before changes of direction (Figure 3), were made to measure at the Hagenbucher centre of competence in Eglisau, about 120 km away, within 2 to 3 working days (Figure 4), ready to be transported to the construction site for installation. This work was able to be done at the centre of competence regardless of weather conditions. In detail, the pipes were cut to length, the cement mortar coating was removed to the appropriate length, the pipe ends were chamfered and a welding bead was applied around the circumference by means of an automatic welder (Figure 5). Finally, a corrosion protection coating was applied to the pipe ends, consisting of a zinc coating and a bitumen finishing layer.
While this was being done, the construction company was backfilling those areas of the pipeline which were still open (Figure 6), meaning that at no point was the construction work delayed on account of the preparation of the special pipes.
5 Power plant building and power plant pipeline
In order for the power plant – consisting of the water catchment in the “Lägni”, the 1,800 m long power plant pipeline and the power plant building at the valley station of the Bristen-Golzern cableway – to blend harmoniously into the landscape, the water catchment has been concealed behind a rock, the power plant building has been designed as a showpiece power plant with a gable roof and the power plant pipeline has been installed underground. Only in one section did the pipeline have to be run above ground, suspended beneath a pipe bridge over the Chärstelen stream. With the deflection capability of the BLS® restrained push-in joints, the pipeline is able to follow the curved shape of the bridge without the use of additional fittings (Figure 7).
After completion of the construction work, the pipe bridge will be upgraded into a footbridge and the pressurised water pipeline beneath it will not be visible from above (Figure 8). The entire power plant pipeline was completed within just seven months. In the 1,800 m long pipeline there are 40 fittings (double socket bends MMK 11 to MMK 45), three fittings with manholes (Figure 9) and 50 special pipes installed.
As the main building with the turbines is located directly next to the valley station of the Golzern cableway so popular with hikers and mountain bikers, the Bristen power plant will also act as a showpiece power plant. In this way, as well as the actual production of energy, it can contribute added value for tourism in the Maderaner valley.
6 Data on the project
Client: | KW Bristen AG |
Catchment: | Lägni, 1,007 m above sea level |
Power plant: | Schattigmatt, 827 m above sea level |
Gross head: | 180 m |
Pressure pipeline: | 1,800 m ductile iron pipes with BLS® restrained push-in joints and cement mortar coating |
Fittings: | 40 socket bends, DN 1000, in ductile cast iron - MMK 11° to MK 45° with BLS® restained push-in joints |
Bibliography
Author
More News and Articles
Mar 29, 2023
News
Water management: Spain invests nearly 23 billion euros
The Spanish government improves its water management and will invest nearly 23 billion euros to comply with European Water Directives.
Mar 27, 2023
News
UN World Water Day 2023: How municipalities can accelerate the water transformation
The United Nations is proclaiming the motto “Accelerating Change” for World Water Day on 22 March. The message: because the pressure on drinking water reserves is increasing worldwide, the change towards sustainable water use must be accelerated.
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 15, 2023
News
Versatile electric pipe-cutter makes UK debut
The first all-electric battery-operated lateral pipe-cutter to enter the UK market has secured sole distribution with pipeline equipment specialist Ant Hire Solutions.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Contact
European Association for Ductile Iron Pipe Systems · EADIPS®/ Fachgemeinschaft Guss-Rohrsysteme (FGR®) e.V.
Dipl.-Ing. Christoph Bennerscheidt
General Manager
Doncaster-Platz 5
45699 Herten
Germany
Phone:
+49 2366 9943905
Fax:
+49 2366 9943906