Perfect Pipeline Premiere: Herrenknecht Direct Pipe for the first time in Canada
Dec 12, 2013
A smooth success right from the beginning: For the first time, a Canadian construction company has installed a pipeline using the Direct Pipe® technology from Herrenknecht. Crossing beneath the Beaver River in the province of Alberta with a 42 inch pipeline (1,067mm) was successfully completed in two weeks.
Wes Lingerfelt got up to speed on the jobsite: "We were at the machine seven days a week to get the project finished quickly and efficiently." Wes Lingerfelt operated the Direct Pipe® system, which Canadian tunnelling company Michels Canada ordered from Herrenknecht for the Beaver River pipeline crossing in the province of Alberta. A pipeline with a diameter of 42 inches (1,067mm, double FBE coating) had to be built over a length of 340 meters under the river.
The drill was carried out with an entry angle of four degrees and an exit angle of eight degrees with an overburden of around five meters below the river bed. The target pit was reached after 13 days of drilling between the start on August 24 and breakthrough on September 8, 2013. Wes Lingerfelt is impressed by the performance capacity of the technology: "We reached an impressive 68 meters on our best day."
Direct Pipe® was first used in Canada to cross beneath the Beaver River, a premiere achieved with bravura. Patrick O'Donoghue, Trenchless Crossing Manager at Michels Canada: "Direct Pipe is gaining more and more attention among trenchless tunnelling specialists in North America. We look forward to completing more high-quality projects."
The crossing beneath the Beaver River is part of a section of the 'Cold Lake Pipeline' extension between La Corey and Hardisty over a total length of 240 kilometers. The client Inter Pipeline Limited is expanding its capacities for the transport of the bitumen gained from oil sands in Cold Lake.
The Direct Pipe® Technology developed by Herrenknecht combines the advantages of Microtunnelling and Horizontal Drilling Technology (HDD). In only one work step, a prefabricated pipeline is installed in the trenchless mode and the required borehole produced simultaneously. This provides for the speedy and highly cost-efficient installation of pipelines with lengths of up to more than 1,500 meters. To date, 35 projects have been completed successfully using Direct Pipe in Germany, Great Britain, Italy, Canada, the Netherlands, Thailand and the USA.
Beaver River Crossing
Ort | Bonnyville, Kanada | Herrenknecht Direct Pipe® | |
Anwendung | Sand, Ton, Steine, Findlingen, Muscheln, Holz | AVN800X | Drehmoment: 90 kNm |
Geologie | Öl | Pipe Thruster HK750PT | Schubkraft: 750 t |
Auftraggeber | Inter Pipeline Limited | Kunde | Michels Canada Co. |
Pipeline |
Durchmesser: 42“ (1.067 mm) Länge: 340 m |
More News and Articles
Nov 29, 2023
News
Shedding light on evaporation
Researchers at MIT (Massachusetts Institute of Technology) have made a groundbreaking discovery that could change our understanding of evaporation, a ubiquitous process in our environment. They found that under certain conditions, light can directly cause evaporation without the need for …
Nov 27, 2023
News
NEW UNITRACC Construction Site Documentation: "Rehabilitation of a DN 400 Concrete Gravity Sewer with a SAERTEX-LINER® MULTI over a Length of 69 m" (CIPP)
New construction site documentation in the renovation section of the e-learning platform: Rehabilitation of a DN 400 concrete gravity sewer with CIPP lining using SAERTEX-LINER® MULTI, type S+ Standard. The objective of this rehabilitation measure was to enhance the structural …
Nov 24, 2023
News
Tracto grundoram supports sewer replacement at coastal town
Budleigh Salterton is a popular and picturesque seaside town situated within the East Devon Area of Outstanding Natural Beauty. Located at the start of the stunning Jurassic Coast; a UNESCO World Heritage Site recognised for its outstanding rocks, fossils and …
Nov 22, 2023
News
Interflow’s sustainability strategy
Having been in business for 86 years, Interflow has proven it knows a thing or two about longevity. Right now, that requires an all-encompassing sustainability strategy, as Richard McCarthy, Interflow’s executive general manager southern region, explained.
Nov 20, 2023
News
Mastering public sector challenges together
An interview with Managing Director Robert Ristow
Nov 17, 2023
News
Tractebel and Aurecon forge strategic partnership to revolutionize dam projects in Queensland, Australia
Tractebel and Aurecon form a strategic alliance to revolutionize dam projects in Queensland, Australia, combining their global expertise and local knowledge to meet the rising demand for dam upgrades.
Nov 15, 2023
News
HDD to help Monarto pipeline project
SA Water will use horizontal directional drilling (HDD) to assist in installing a section of pipe underneath the Melbourne to Adelaide rail corridor.
Nov 13, 2023
News
Neom’s sustainable water solutions with renewable desalination
Saudi Arabia’s visionary city, Neom, is leading the way in sustainable water solutions with the construction of a desalination plant powered entirely by renewable energy.
Nov 10, 2023
News
Adept delivers on Geelong infrastructure project
Adept Civil Group has successfully delivered on a sewer reticulation extension project at the Charlemont Rise estate.
Nov 09, 2023
News
NEW LAUNCH: UNITRACC Module "Details on the Installation of Lining with UV Cured-in-Place Pipes" (Renovation: CIPP)
Introducing the new e-learning module for the course "Renovation: Lining with Cured-In-Place Pipes"! This module focuses on the installation of UV CIPP using the high-quality SAERTEX-LINER® specifically designed for gravity pipes and sewers - with contributions by renowned manufacturer SAERTEX …
Nov 08, 2023
Article
Future perspectives - Give water somewhere else to go
Extreme rainfall, flooded streets, destroyed houses and infrastructure, people fighting for their lives amidst the floods. 2021 was also marked by such tragic events. It´s time to ask how flood disasters happen, and what can be done about them.
Contact
Herrenknecht AG
Achim Kühn
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 (0)7824 302-5400
Fax:
+49 (0)7824 302-4730