NORDIPIPE as pull-in version for trenchless rehabilitation of drinking water pipes
Jul 08, 2014
Renovation » Lining with pipes
Pilot project with CIPP technology of SEKISUI SPR in Shumen, Bulgaria - The challenges often involved in drinking water rehabilitation projects are the available time window, residual flow capacity after the rehabilitation, diameter and length to be renewed. Other factors are the capacity to negotiate bends and local contruction site conditions.
In Shumen the Water Supply and Sewerage Company trusted the CIPP technology and instructed the rehabilitation of four sections in its water network. One section was a pilot project: For the rehabilitation of a 328 m long and 920 mm diameter large drinking water pipe the CIPP liner system NORDIPIPE™ was used as pull-in version for the first time.
Shumen is a city in northeastern Bulgaria whose drinking water supply is managed by the Shumen Water Supply and Sewerage Company. The region is supplied by 94 individual and independent water supply systems, covering 8 towns and 143 villages. There are 1,450 km of local distribution pipelines with 56,159 lateral connections. Water is supplied by pumping along 890 km of pipelines to the 72,209 households. Most of them are made of asbestos-cement and were constructed between 1950 and 1970. Others were made of steel that need to be rehabilitated because of leakages to guarantee an immaculate 24-hour drinking water supply for the next decades.
In autumn 2013 the Shumen Water Supply and Sewerage Company commissioned Stroitelna Mehanizatsia, a construction partner of SEKISUI SPR in Europe, with the rehabilitation of a deteriorated steel pipe with a length of around 3000 m and diameters of 544 - 920 mm. The project included four sections, three of them where rehabilitated by trenchless NORDIPIPE™ CIPP technologies of SEKISUI SPR. For the rehabilitation of a 328-metre long drinking water pipe section with diameter of 920 mm, the CIPP liner system NORDIPIPE™ as pull-in version was deemed to be the ideal technological solution.
Open construction would not have been possible due to the challenging construction site conditions. The 920 mm diameter steel pipe lies in an unstable ground with soft, loamy soil which meant limited accessibility, particularly during persistent rainfall. Therefore only a fast trenchless technology solution was considered for which excavation pits as start and end point and less equipment was sufficient. Further difficulties that the technology had to compete with were the high groundwater level, a strong gradient of 6-8%, a 15° bend and an operating pressure of 16 bar.
NORDIPIPE™ pull-in liner and its advantages
NORDIPIPE™ consists of a main hose and a calibration hose whose material combination has been approved in conjunction with NORDIPOX D resin for potable water under various approval schemes in several countries. The main hose is a fiberglass-reinforced needle-felt liner with a number of glass layers, selected according to internal pressure and diameter. Its durable PE outer coating protects the liner from external influences during installation and operation.
The calibration hose, a needle-felt liner with PE coating, raises the main hose into position within the old pipe and provides a smooth surface with increased hydraulic performance compared to the old host pipe.
Both hoses are impregnated with NORDIPOX D, a two-component epoxy resin, to receive a homogenous material combination as well as a consistent liner structure in the cured state. The pull-in version allows an accurate calculation of the resin material and a consistent resin distribution. Its particular material composition of glass-fiber, needle-felt, resin and PE coating makes it a fully structural liner. It can be thus called a "stand-alone pipe" for the purposes of DIN EN ISO 11298 Class A.
The installation process
Three construction pits provided access to the 328 m long pipe section at a depth of 3 m beneath a field alongside a main road. The installation length of 328 m would normally have been no problem. However, due to the poor bearing capacity of the loamy soil, for weight reasons the liner had to be divided into two lengths of 164 m. The impregnation process took place on a road near the construction site. Long distance was needed for laying out the liner while being impregnated by a mobile impregnation setup and directly wound onto a transport spool. The main and calibration hose were impregnated with the specially designed NORDIPOX D epoxy resin at about 4°C.
After pipe cleaning, the main hose was gradually drawn into one of the two 164 m long pipe sections by means of a 20 tonne capacity winch. Afterwards, the calibration hose was inverted with low pressure and a speed of 3–5 m/min by means of a pressure drum to position the main hose in the old pipe. The hoses were steam cured at a laminate temperature of 70°C and a new stand-alone pipe was created within a period of two hours. The insulating PE outer coating of the main hose allowed a reduced curing time despite the challenging construction site conditions and the high water level.
The rehabilitation process was concluded after sealing the four ends of the two 164 m long liner sections within two weeks. Following a pressure test, the pilot project for the NORDIPIPE™ pull-in liner for a 920 mm diameter pipe was successfully completed. The pipe was put back into 24-hour, seven-day operation to supply the city of Shumen safely with drinking water.
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
SEKISUI SPR Group
Lena Zemke
Julius-Müller-Str. 6
32816 Schieder-Schwalenberg
Germany
Phone:
+49 (0) 52 84/705-405
Fax:
+49 (0) 52 84/705-410