Niagara Tunnel Receives Premier Project Award at Platts Global Energy Awards
Jan 27, 2014
In December 2013, Hatch Mott MacDonald and its Canadian parent company Hatch received one of two Premier Project Awards at the Platts Global Energy Awards, for their work on the Niagara Tunnel project. The award was presented at the Waldorf Astoria in New York City.
According to Platts, "The winner of the Premier Project Award in the Engineering category is ambitious not only in its dazzling scale, but also in its contribution towards achieving a larger goal."
As Platts reported, "The Niagara Tunnel was safely completed in March 2013, nine months ahead of schedule and $100M under its $1.6B budget. The tunnel will provide the province with a reliable, maintenance free source of clean energy for the next 100 years. It is also a key element of what judges called Ontario Power's 'ambitious but attainable' long-term energy plan including closure of the remaining three coal-fired generating stations."
Platts noted the "many logistical hurdles" on the project:
All underground work had to be accessed from a single entrance at the outlet end of the tunnel, so all tunnel operational equipment had to be designed to allow traffic to pass to and from the TBM. Concrete was at times pumped 1.4 km, requiring very precise mix design and quality control. And because the excavation proceeded from the outlet end of the water conveyance to the intake end, which is located immediately below the International Niagara Control Structure in the upper Niagara River, about 2 km upstream of the Horseshoe Falls, preventative measures had to be taken to prevent potentially serious groundwater inflow during TBM excavation.
In November 2013, the Niagara Tunnel Project was named Canadian Tunnelling Project of the Year at the Awards Gala of the Tunnelling Association of Canada.
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
Hatch Mott MacDonald, Inc.
150 South Independence Mall West
Philadelphia, PA
United States