New Nitrogen Pipeline for the University Hospital Bern
Jan 12, 2016
Founded in 1534, the “Inselspital” hospital in the city of Bern today is one of the most prominent University Hospitals in Switzerland and an internationally renowned centre for high-tech medical science. The premises in the western part of the city include several buildings accommodating numerous highly specialised clinics where round about 40.000 inpatients and 520.000 outpatients are treated per year.
It is not hard to imagine that the infrastructure for operating such a high-technology complex is very expansive and has to be continuously adapted to the requirements. In order to extend the pipeline network a new nitrogen pipeline had to be installed from a fuel depot into a building housing the intensive care, casualty and surgery units (INO).
Liquid nitrogen, as a medical application, is used for freezing tissue and cells at temperatures as low as -196 °C, the so-called "cryopreservation". For the new pipeline a vacuum-insulated pipe with an outer diameter of 63 mm, which could bear up against these sub-zero temperatures, was to be installed inside a protection pipe PE NW 280 S8.
The 70 m long bore path on the clinic premises, densely covered with buildings, took its course past the hospital chapel and into a ventilation room in the basement of the INO building. Due the very confined space in the launch area, a 2.50 m high earth dam between the building and the fuel depot was chosen as the starting place for the drill rig by the parties involved. In order to avoid damage to the existing pipelines inside the building the bore into the 3 m deep storage room had to maintain a target precision of +/- 20 cm horizontally as well as vertically. All in all, this was just the right job for the experienced drilling crew of the pipe laying experts Zemp.
The construction works started in May 2015. An excavator was lifted to the launch area with the help of a truck crane to dig out the start pit for the pilot bore and another pit for collecting the drilling mud. Then the GRUNDODRILL 18ACS, weighing the whole of approximately 15.2 tons, was placed onto the banked-up starting place by means of a 100 t truck-mounted crane.
The pilot bore, reaching a depth of up to 6.50 m, caused no problems. On arrival at the target a core hole of 450 mm in diameter was drilled through the wall of the building into the ventilation room to allow pulling the backreamer of Ø 400 mm in. One single reaming operation was sufficient to pull the new pressure pipeline through the bore path. As the basement offered very little space the single pipe segments were no longer than 2.50 m and had to be welded together in situ to form 12.50 m long pipe strings. During the process of pulling in such a previously prepared pipe string was welded on every 12.50 m.
The drilling mud was collected in a 500 l basin at the target point in the basement, from where it was pumped into a pit in the access area of the casualty department via a 60 m long line. The high share of gravel did nothing to make pumping any easier, but was not really a great drawback for the pipe pulling operation.
The final works like primary cleaning of the buildings, new installation of an inspection chamber and disassembly of the machine with the truck-mounted crane having been completed, the new line was turned over to the satisfied customer after only 10 working days. "Once more, the merits of trenchless installation in general were proved by this project, especially in connection with the TT technology. Thanks to the reliability and flexibility of our GRUNDODRILL 18ACS, this measure was happily resolved, drawing to a profitable close", was the satisfied conclusion of the company owner, Markus Zemp.
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
TRACTO-TECHNIK GmbH & Co. KG
Günter Naujoks
Paul-Schmidt-Straße 2
57368 Lennestadt
Germany
Phone:
+49 (0)2723 / 808-130
Fax:
+49 (0)2723 / 808-180