Microtunneling to Exacting Standards in Holland
Jul 07, 2005
Not only were ground conditions difficult and the water table high, but also tunneling under an excavated canal with banks higher than the surrounding land required exceptional safety measures.
The WRK I and II pipelines between Utrecht and Abcoude run parallel with the A2 Freeway. During the next few years, Rijkswaterstaat (Directorate-General for Public Works and Water Management) is going to expand the A2 Freeway between Amsterdam and Utrecht from three to four lanes. For this reason, the pipeline to the east of the freeway must be moved some 60 m eastward over a distance of about 5 km.
Amsterdam Water carried out the preparatory survey work itself and had been able to decide the course the pipes needed to follow. After a pre-selection process, a building consortium, Visser & Smit Hanab, Papendrecht, Netherlands/Dura Vermeer Infra, Hoofddorp, Netherlands, was chosen as the most suitable partners. Good cooperation between Amsterdam Water and the chosen partners meant that a quick match between the owner's theoretical approach and the contractor's practical approach was possible and this saved time to produced a good, final, detailed plan.
In the soft peat soil, the boring machines could not be offset against the sheet piling as they would normally. The clay/water mixture does not exert much counter-pressure, so the piling would simply be pushed away unless additional measures were taken. For this reason, large profiles were filled in the middle of the concrete floor with frames behind it to offset the drilling frame and transfer the thrust to the surroundings through the concrete floor.
After the new pipeline had been laid and connected to the existing one, the section to be replaced was removed. This meant removing around 1,500 concrete pipe sections. Because the system could not be shut down completely and water transfer had to be maintained throughout, the pipelines were connected one at a time.
The new part of the freeway is being built on an enormous sand bank whose weight compresses the peat soil layer. Everything else under the freeway can also be compressed and moved, including a pipeline. So, after examining the various options, Amsterdam Water chose to relocate the new pipeline as deep as economically possible. The traditional method of construction by excavating a trench was also discounted because it would have been very expensive and complex since the peat extends from the surface to a depth of 6 to 8 m. Instead Amsterdam Water chose to place the pipeline in the Pleistocene sand layer under the peat since the new freeway does not affect a pipeline at that depth. For the construction of a pipeline of this size (outside diameter of 1,200 mm), both concrete and steel can be used. The consortium chose steel for economic reasons.
During the preparation, it became apparent that the permit authority, Hoogheemraadschap Amstel Gooi en Vecht, would set exacting standards where the pipeline passed under the Geuzensloot. The Geuzensloot is an excavated canal at NAP level (Normal Amsterdam Water level). Because the banks of the canal are regarded as primary water-retaining structures, the Hoogheemraadschap standards are set for exceptional levels of construction stability and safety. For the crossings the new pipelines pass under the Geuzensloot in additional casing pipes with a diameter of 1,500 mm. This alteration to the plans meant more work and more time to get it done.
The entire project was carried out with minimal removal of groundwater. The removal of groundwater and its discharge are sensitive topics in the Netherlands — especially in view of the fact that the pipeline is being built at great depth through boring and a great deal of drainage would normally be required in peat soil to keep the pits dry. This meant that an alternative solution was required. The method chosen was more expensive than pumping out excess water, but did not have the discharge problem. The pits were designed to be waterproof and the pipe jacking was carried out without allowing water in flow. The pipes were jacked through a special rubber seal designed to withstand both the hydro-static pressure and the pipe movement to prevent ground water from entering the pit.
Amsterdam Water and the contractor’s consortium approached this project as a joint team from an early stage. The fruits are evident in the quality of the detailed plan, while short communication lines and quick responses for decisions saved time. The Visser & Smit Hanab/Dura Vermeer consortium was able to carry out the project in the most economical way and delivered the result that the customer wanted — an optimal win-win situation.
Where a technically complex project is concerned, a year passes by in no time, even if the twin pipeline to be built is only 5 km long. The pipeline was constructed entirely by micro-tunneling in Pleistocene sand at a depth of 10 m. Peat is located above this layer of sand, which is not the favorite kind of soil for pipeline owners or contractors. The performance of Visser & Smit Hanab/Dura Vermeer building consortium was unique in delivering this complex project on time, safely and to a very high quality.
Ton Timmermans is unit manager of trenchless technology at Dura Vermeer Ondergrondse Infra BV, Hoofddorp, Netherlands. Gerard Jonkergouw is manager of special projects at Visser & Smit Hanab BV, Papendrecht, Netherland.The article was first published in the Trenchless Technology International, May 2005.
More News and Articles
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Feb 22, 2023
News
IWA-Grundfos UN Water Conference youth delegates announced
The International Water Association and Grundfos are proud to announce that 14 bright and promising international young water professionals (YWPs) have been selected to be part of a delegation to the upcoming UN 2023 Water Conference, on 22-24 March 2023 …
Feb 20, 2023
News
Smart Lock makes short work: Hong Kong sewer drain repair
When the Hong Kong Drainage Services Department identified a badly damaged pipe, it was Smart Lock’s sleeve solution that empowered contractors to successfully rehabilitate the damaged section.
Feb 17, 2023
News
iMPREG celebrates UV Liner installation success in the UK
iMPREG has helped complete the task of installing an ultraviolet liner in the United Kingdom.