Luxemburg farmers place their faith in the E+S Site Road - Optimum load distribution
Sep 15, 2005
The Beckerich-Huttange-Nordange main collecting system in Luxemburg, which Weiland Bau S.à.r.l. is constructing on behalf of the Syndicat Intercommunal de Dépollution des Eaux Résiduaires de l’Ouest (SIDERO), is about 3,300 m long. In addition to the new collecting system – a corrugated sheath measuring DN/OD 315 to 400 mm – a district heating pipeline and a duct for an optical fibre cable are also being laid in the trench in a single work process. To protect the ground of what is mainly grazing land, the contracted company is using about 500 running metres of Site Road from Emunds+Staudinger. This satisfies the client’s brief as well as the needs of the affected farmers, for it eliminates extensive soil extraction and removal, as required for the construction of a conventional site road of crushed rock. The temporary Site Road is quickly and easily laid. Owing to their optimum load distribution, the 2.4 m long and 3.8 m wide elements protect the ground effectively from destruction and compaction by construction vehicles.
Since the 2.5 m wide and up to 3.5 m deep trench passes almost exclusively through valuable pasture, the concerns of the affected farmers were initially considerable. It was essential that the construction vehicles should do as little damage as possible to the topsoil. It was also important not to destroy the drainage system in the clayey soils typical of the region that tend to become waterlogged. For this reason, the client opted for a temporary site road – a procedure that, in the opinion of everyone concerned, has paid off. The production and removal of a conventional site road of crushed rock is generally extremely laborious. "The tasks involve bulldozing or excavating the topsoil and storing it temporarily, laying a geotextile and a course of crushed rock with subsequent compaction, excavating and removing the crushed rock, and replacing the topsoil," explains Project Manager Edgar Krings, Weiland Bau S.à.r.l. With the new E+S Site Road, all these tasks are omitted. No special vehicles are needed for moving materials to and from the site. The individual Site Road elements can be laid directly, without any large-scale preliminary earth moving. At the same time, they also withstand extreme loading. Owing to their good load distribution – point loads are spread over an area of about 9 m2 – the Site Road elements provide the necessary stability even on soft ground.
What’s more, thanks to simple design and special connectors, assembly is relatively quick. "The Site Road is composed of rugged angle elements laid lengthwise and special transverse profiles," explains Frank Abeling, Site Road Product Manager, Emunds+Staudinger GmbH, describing the elements that have already been successfully used in building construction and civil engineering assignments at home and abroad. "Assembly of the 2.4 m long and 3.8 m wide elements on site couldn't be simpler," Abeling continues. An excavator lifts the elements one after another from a reversing truck, and then they are joined together with a kind of chain joint. For the project in Luxemburg, however, it was possible to omit this step, as the panels pressed themselves immovably into the clayey ground.
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
Emunds + Staudinger GmbH
41836 Hückelhoven - Baal
Phone:
+49 (0) 2433 / 453-0
Fax:
+49 (0) 2433 / 453-100