Large Up Size Pipe Replacement Beneath The West Highland Railway
Feb 26, 2013
Pipe bursting, in general
A HammerHead® HB125 static pipe-bursting system, provided by U Mole was recently utilised by rail contractor Carillion to undertake an interesting and challenging project to replace a 450mm i.d. clayware sectional culvert running beneath the main railway line between Crianlarich and Oban.
Running at around 5m depth, the 450mm existing culvert needed to be not only replaced but also up-sized to 630mm with the replacement pipe being HDPE. Whilst the project at first appeared to be a straight replacement job, with the need to utilise a 730mm diameter expander behind the bursting head, an equivalent up-size of over 250mm diameter, the installation of the new pipe was not going to be easy.
Although the contractor had used the Hammerhead® HB125 on an earlier section of works on the West Highland rail route, given the massive up-size required for the new installation, operator training of Carillion personnel was completed by U Mole engineers prior to the works on site at project site at Taynuilt.
Other parts of the challenge on the Taynuilt site over and above the up-size required, was access and site preparation. To achieve the replacement installation site works were undertaken for 14 days before the bursting work could commence. This was because ground conditions at the site proved to be soft which meant the footings for the pipe bursting system had to be correctly constructed. The site also required the removal of a line of trees in the rail embankment. These site preparations of the launch and burst site had to be completed with imported stone etc. Also required was the environmental protection of local waterways in case of any hydraulic leaks etc.
Once the site prep was completed the job could be started. Carillion’s workforce was ultimately delighted at the ease of operation of the bursting system once set up. The bursting works, including machine set up were completed over the course of just two days. The actual simultaneous burst run and new pipe installation were actually completed in less than half a working with day no disturbance to the railway line on the embankment above. Looking ahead to a series of future bursts beneath the railway line members of the crew commented that they were looking forward to once again using the HB125 system.
In terms of the site set-up, another complication which was faced by the contractor was ensuring that launch pit face was able to resist the pulling forces of the bursting rig. Carillion’s Section Engineer for the works, Glen Henderson, had to develop a temporary jacking face system which was capable of distributing the pulling force of the rig against the relatively soft railway embankment. Glen said: “Due to the added resistance caused by the expansion process when bursting the existing pipe, the pit face had to be very robust. The set-up ultimately consisted of driven sheet piles with 13 mm (½ in) thick steel road plates.”
Works were carried under the normal working times of the trains. RETB tokens of the OBN2 line between Dalmally station and Connel station were taken and pipe pulling operations to install the new pipe took place between trains. The contractor also continuously monitored the cant and level of the track so that the works could be stopped at the first sign of any movement. The depth of the fill between the pipe installation and the track allowed sufficient consolidation through the embankment such that during the operation no track movements occurred.
Glen went on to say: “Due to the depth of this culvert below the track level, the traditional deep excavation and replacement would not have been feasible. With guidance and training from U Mole we were able to exploit the benefits of trenchless technology. We were able to cut down on our material usage in terms of not requiring substantial amounts of backfill and we minimised our wastage by having no excavated material to dispose of. Any opportunity where we are able to keep the railway open to traffic whilst undertaking this type of work puts us ahead of our competition and allows us to achieve a more economical and sustainable end result for both Carillion and ultimately Network Rail and the service’s customers.”
More News and Articles
Mar 29, 2023
News
Water management: Spain invests nearly 23 billion euros
The Spanish government improves its water management and will invest nearly 23 billion euros to comply with European Water Directives.
Mar 27, 2023
News
UN World Water Day 2023: How municipalities can accelerate the water transformation
The United Nations is proclaiming the motto “Accelerating Change” for World Water Day on 22 March. The message: because the pressure on drinking water reserves is increasing worldwide, the change towards sustainable water use must be accelerated.
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 15, 2023
News
Versatile electric pipe-cutter makes UK debut
The first all-electric battery-operated lateral pipe-cutter to enter the UK market has secured sole distribution with pipeline equipment specialist Ant Hire Solutions.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Contact
Groundforce
Otley Road
HG3 1UD Harrogate
United Kingdom
Phone:
+44 1423 852 295
Fax:
+44 1423 536731