HOBAS ® Goes XXL: Pipes OD 3000 Jacked for Poland's Largest Wastewater Treatment Plant
Feb 17, 2010
3 meters are a little more than the average ceiling height of a flat, yet one can hardly be speaking of something "average" when talking about a 3 m pipe diameter – and yet this has become routine for HOBAS.
Due to this project's size, it was broken down into three sections. The first is approximately 5.7 km long and realized with HOBAS Jacking Pipes OD 3000 (DN 2800) which were installed along the right side of the Vistula, whereas 1.4 km OD 3000 are laid on the left river bank. The pipelines meet in the third section where two lines DN 1600 are inserted in a 4.5 m diameter concrete tunnel crossing beneath the Vistula.
Up to now the consortium of contractors Hydrobudowa 9, PRG Metro and KWG (all belonging to the PBG Group) has completed 1600 m of the first pipeline section utilizing two microtunneling Herrenknecht machines AVN 2000 as well as 2400 and separators HSP 500. One of the challenges that had to be faced is the high ground water level that lies around 1 to 2 m below the surface and therefore reaches 4 to 8 m or 3 floors above the pipe top. Piles by Larsen were set up around the thrust pits and jet-grouting was added to prevent too much water from pouring in.
Only this way was it possible to reduce the volume of 200-300 m3/h (= up to 2000 bathtubs of water) to 20-30 m3 which are constantly pumped out. Due to the grouted screens it was furthermore safer lifting the drilling heads in and out of the pits.
Worthwhile mentioning is the 840 m long part of the first section where the pipes were supposed to be jacked from both ends meeting in the middle. However, installations with HOBAS Pipes can be conducted so precisely that the section could be jacked with one single drive and from one side only. The smooth and even outer surface and high stiffness (SN 50000 und 64000) of the relatively light-walled HOBAS Pipes were significant for this success.
The tunneling progressed at an average of 3 m per hour, the separator processing 84 tons of soil per hour (=42 m3/h) and a 3 m long pipe takes roughly 0.5 h to be jacked. An interesting fact is that the preparation (disassembly and reassembly of electric cables, slurry pipes and hydraulic hoses) takes 40 to 60 minutes. Considering this and including the breaks for the workers one can say that an average of 10 pipes could be put into the ground per day.
At this speed it was possible to accomplish the first sections weeks ahead of schedule. The contractors’ expectations were certainly exceeded, especially, because new sections could now be commenced, given the limited resources of the subcontractors establishing the pits.
Currently, pipes are continued to be jacked beneath the main road of the district Białołęka. An open trench would not have been possible here since the construction works would have impaired the traffic on this important 6-lane road (3 lanes in each direction). The pipeline route runs beneath the middle, the green line, of the road and a single drive over 910 m will break the record of longest single drives in the project. 2 curved stretches with 450 and 900 m radii are part of the section and are realized with 1 m pipes - the angular deflection being well held within the couplings. The 450 m radius is implemented over a stretch of 100 m and a laser to measure the inclination of the pipeline can only be utilized on straight sections, in curves this is done with the help of a gyroscope and water level.
To go XXL with OD 3000 pipes for Czajka, HOBAS Technicians developed a centrifugal facility which rotates at 75 km/h. The mold together with the heaviest pipe available result in an impressive rotating 45 ton mass, which by the way equates to 2 fully laden 18-wheelers. HOBAS once again lives up to the motto: HOBAS®. Make things happen.
Overview | |
---|---|
Year of Construction | 2009 - 2010 |
Construction Time | 21 months |
Total Length of Pipe | 5.7 km |
Diameter | DE 3000 |
Pressure Class | PN 1 |
Stiffness Class | SN 40000 – 64000 |
Installation Method | Jacking |
Application | SewerLine® |
Client | Waterworks Warsaw |
Constructors | PBG Group: Hydrobudowa 9, PRG Metro and KWG |
Advantages | tailor made solutions, high corrosion resistance, comparably thin pipe walls, easy installation |
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
HOBAS France
92270 Bois Colombes | France
Phone:
+33.6.84 04 53 23
Fax:
+43.463.48 21 21