HERRENKNECHT »Käthchen« Achieves Breakthrough
Aug 17, 2018
The site crew working with tunnel boring machine »Käthchen« (»Katie«) has completed the second tube of the Bossler tunnel. The breakthrough near Mühlhausen im Tale in Baden-Württemberg is another milestone in the construction of the Stuttgart-Wendlingen-Ulm railway line. The Bossler Tunnel is part of the Stuttgart-Ulm railway project and is expected to go into operation in 2022.
When »Käthchen« (Ø 11,340 mm) broke through the target wall, the Earth Pressure Balance Shield (EPB) had completed around 18,000 meters of tunnelling in the sandstone, limestone and claystone rock.
The Herrenknecht tunnel boring machine (TBM) finished the second tube of the Bossler Tunnel in early June. Now the shell construction of the tubes in this section is completed.
The railway tunnel is of great importance for the new Wendlingen-Ulm line and is expected to go into operation in 2022. Travel time on the Stuttgart-Ulm route will be almost halved. Ten million passengers a year will benefit from the project.
The second tube of the Bosslertunnel runs parallel to the first, which the team from ARGE ATA Tunnel Albaufstieg (Porr Deutschland GmbH, G. Hinteregger & Söhne Baugesellschaft m.b.H., Östu-Stettin Hoch-und Tiefbau GmbH, Swietelsky Baugesellschaft mbH) had already completed in November 2016.
The TBM »Käthchen« was then disassembled into its individual parts, transported back to the starting point and prepared for the launch of the second drive. From April 2017, the machine again worked its way continuously through the rock.
Construction of the two tubes was carried out differently than originally planned. After the preliminary geological analysis, the construction team had only intended to use »Käthchen« over a distance of about 2.8 kilometers. In the course of further exploration, however, the soil conditions turned out to be more favorable than expected.
The TBM from Herrenknecht was thus able to excavate nearly 7.8 kilometers in the first tube and even 8.8 kilometers in the second tube – which is almost the entire tunnel distance. The work progressed extremely quickly.
From the beginning, »Käthchen« achieved top performances. In June 2015 already, two months after the start of the drive in the first tube, she reached the thousand meter mark. She was able to cover up to 38 meters per day and after advancing for six months had already excavated three kilometers – a strong performance on the part of the site crew.
A total of 60,000 segments were installed in the Bossler Tunnel. They were manufactured in the purpose-built factory close to the Aichelberg tunnel portal.
The Albvorland Tunnel is part of the new construction of the Wendlingen-Ulm railway line. The Herrenknecht tunnel boring machines »WANDA« and »Sibylle« (Ø 10,820 mm) are in operation there – so far having excavated almost four kilometers of tunnel. As part of the Stuttgart 21 project, Herrenknecht is also working on the Filder Tunnel.
The Multi-mode TBM »SUSE« (Ø 10,820 mm) has already excavated over 10 kilometers of the tunnel route planned to connect the main station with the airport.
Project data »Käthchen« achieves breakthrough
MACHINE/PROJECT DATA S-833
Machine type: EPB Shield
- Shield diameter: 11,340 mm
- Drive power: 4,550 kW
- Tunnel length: 2x 8.806 m, tunnelling distance: 17,612 m
- Geology: brown (claystone, sandstone layers) and white Jurassic (marl, marl limestone, limestone)
- Customer: ARGE ATA Tunnel Albaufstieg (Porr Deutschland GmbH, G. Hinteregger & Söhne Baugesellschaft m.b.H., Östu-Stettin Hoch-und Tiefbau GmbH, Swietelsky Baugesellschaft m.b.H.)
- Client: Deutsche Bahn AG
More News and Articles
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Mar 18, 2024
News
Global Student Innovation Challenge Calls on Next-Generation Leaders to Tackle Water Security
High School and University Students Worldwide Invited to Expand Water Access and Community Resilience
Mar 15, 2024
News
New water treatment wins Prestigious Award
Introducing a advancement in water treatment, developed by Cardiff University researchers in collaboration with Origin Aqua, the FreeOxTM technology has garnered acclaim by winning a prestigious challenge award at the World Water Tech Innovation Summit. This single-step process not only …
Mar 13, 2024
News
Satellite-based river monitoring technique could provide early warning of flooding
A satellite-based method for monitoring the flow of rivers from orbit could provide a valuable early warning system for flood risk, University of Glasgow researchers have claimed.
Mar 11, 2024
News
Revitalising infrastructure with HDD
Through the use of horizontal directional drilling, TasWater is delivering a new sewer pipeline to improve sewer and stormwater transfer capacity in Launceston, Tasmania.
Mar 06, 2024
News
Picking up the pace on climate action: Building momentum from COP28
At the halfway point of the Paris Agreement, the legally binding international treaty on climate action, average global temperatures are already hitting 1.8°C above pre-industrial levels and future projections are stark. At COP28 in December, we could not escape the reality …
Mar 01, 2024
News
Luminescent sensor detects ‘forever chemical’ pollution in water
Researchers in the UK and Germany have developed a new approach for detecting pollution from ‘forever chemicals’ in water through luminescence.
Feb 28, 2024
Article
BETT installation demonstrating GHG emissions reduction of wastewater treatment
This study presents BioElectrochemical Treatment Technology (BETT) as a new wastewater management solution toward the Net-Zero future. The results reported herein were collected from a BETT pilot system installed at a large brewery in Los Angeles, CA, United States processing …
Contact
Herrenknecht AG
Achim Kühn
Head of Group Marketing and Corporate Communications
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 7824-302-5400
Fax:
+49 7824-302-4730