HDD long distance record in Scandinavia
Mar 28, 2014
Trenchless installation of pipelines
Top performance at minus 27 degrees Celsius
Last winter, a team of the Swedish tunnelling company BAB Rörtryckning AB was struggling through centimeter-thick ice about 70 kilometers north of Stockholm. The mission was to install two sewage and drinking water pipelines under the Länna Kyrksjö lake. They are being used to supply the nearby community of Norrtälje whose pipeline system is also to be supplied in future with water from Mälaren lake to the west, because the town has grown so fast in recent years. The drilling tool used by BAB Rörtryckning was a Horizontal Directional Drilling Rig (HDD Rig) type HK150C made by Herrenknecht with a pulling force of 150 tonnes.
The first hole for the drinking water pipeline led from the shore to the bottom of the lake. There, the pipeline had to be connected to a conventionally laid pipeline, thus creating a link to the opposite shore. After only 2 days of drilling, the 700 meter long pilot was completed at the bottom of the lake. Then the weather changed dramatically. The temperature fell by more than 25 degrees and the general contractor SVEAB was suddenly faced with a frozen lake with a decimeter thick ice layer. "We fought against the ice for a total of two weeks, 24 hours a day. Day and night up to four boats were working on the lake as ice-breakers" recalls Magnus Tingstrand from BAB Rörtryckning AB. The boats had to break through the ice to be able to lift the pilot head, change it for a reamer and to connect the pipe which also was frozen into the ice. The effort was worth it – the 28-inch pipeline was installed safely in time for Christmas.
After a well-deserved Christmas break, BAB started installing the sewage ducts in January 2013. The plan was to install this in the form of a single "Double Pack" pipeline consisting of two Polyethylene tubes (2x355 mm). This runs parallel to the previously created drinking water pipeline, which in turn, was to be produced in one step from shore to shore deep under the seabed. The weather was constantly icy. "We first had to clear the jobsite of ice and snow, which took us one full day with temperatures of 27 degrees Celsius below zero," said Magnus Tingstrand. Nevertheless, the drill team was able to achieve record-breaking performances with the HDD Rig. The pilot drill of the 1,385 meter long crossing under the lake was mastered with a record of 457 meters per day within an absolutely short period of time. No HDD project with a comparable length had ever been realized successfully before in Scandinavia. The pipeline installation itself took just under 48 hours.
A result which is pretty impressive. The core part of the new supply and disposal lines for the Norrtälje community was completed after only three months. The completion of the entire project is scheduled for 2015.
HDD - Horizontal Directional Drilling
The HDD method (Horizontal Directional Drilling) is a worldwide tried-and-tested technology for the underground installation of pipelines. In a first step, a pilot drill is driven from the launch to the target point. In a second step, the pilot hole is widened in the opposite direction by a so-called reamer. The reaming is often repeated several times depending on diameter and geological ground conditions. In a last step, the pipeline is inserted into the reamed bore hole. HDD rigs from Herrenknecht are used worldwide to install oil and gas pipelines as well as water and wastewater pipelines with diameters of up to around two meters (80 inches) - rapidly, cost-efficiently and causing low impact on the environment.Project data | Machine data | ||
---|---|---|---|
Location | Norrtälje, Sweden | HK150C Crawler Rig | |
Application | Wastewater; drinking water | Pipeline diameter |
Wastewater: 2x 355mm (2x14 inches "Double Pack") Drinking water: 710mm (28 inches) |
Pipeline length |
Wastewater: 1,385m Drinking water: 700m |
Pulling force | 1,500kN, 150t |
Geology | Soft clay | Torque | 70kNm |
Client | SVEAB | Contractor | BAB Rörtryckning AB |
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
Herrenknecht AG
Achim Kühn
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 (0)7824 302-5400
Fax:
+49 (0)7824 302-4730