Gotthard Base Tunnel: Tunnelling works in the eastern tube of the Piora Basin finished
Dec 23, 2008
The Herrenknecht Gripper-TBM S-210 passed the Piora Basin – a critical zone of the Gotthard Massif - without problems. The tunnel boring machine S-211, driving the western tube, will also arrive in the Piora Basin at the beginning of 2009. North of the basin, both machines will have to tackle another seven kilometers of hard rock - at an overburden of 2,000 meters and with rock temperatures of up to 50 degrees centigrade.
Steel ribs (TH profiles) were installed directly behind the cutter head at one-meter intervals for rock support. The rock surface was sealed with a shotcrete layer and an inner lining was then applied in the form of a 30 centimeterer thick shotcrete segment ring. All this measures proved themselves in practice. “We could not measure any deformations,” explained Heinz Ehrbar, Senior Tunnel and Rail Line Manager of AlpTransit Gotthard AG. The tunnel boring machine driving the western tunnel has to excavate another 1,400 meters of tunnel until it reaches the Piora Basin, probably in the first three months of 2009.
Tunnelling north of the Piora Basin.
Once the Piora Basin is passed, another approx. 6.9 kilometers of tunnel have to be mechanically excavated until the Sedrun section is reached. This is the zone with overburdens of up to 2,000 meters and the highest rock temperatures of 50 degree centigrade encountered within the world’s longest railway tunnel.
Tunnelling progress in the Gotthard Base Tunnel.
In the north, two Herrenknecht Gripper TBMs – the S-421 and S-422 – already drove 3.2 and 1.9 kilometers of the two tunnel sections, each measuring 7.178 kilometers in length, along the Erstfeld-Amsteg section. According to the constructor the tunnelling works move forward as planned. Until October 1, 2008, the tunnellers excavated 118.4 kilometers of tunnel, shafts and adits, equalling 77 percent of the planned 153.5 kilometers.
Previous history: Piora – the tunnellers’ nightmare.
In the run-up to the construction of the Gotthard Base Tunnel, a major controversy broke out among geological experts. Some geologists even doubted the construction of the tunnel due to almost unmanageable fault zones. They expected a sugar-grained dolomite and high water pressures in the Piora Basin. Geological investigations were therefore carried out in the Piora Basin during 1993 and 1998. A 5.5 kilometer long exploratory adit was driven 350 meters above the planned base tunnel alignment from Faido using a small tunnel boring machine. During a core drilling on March 30, 1996, the Piora Basin and the sugar-grained dolomite, subjected to a water pressure of 150 bar, were reached for the first time. Within three hours, 1,400 cubic meters of soft rock mixed with water poured out of the drill hole which was only 10 centimeters in diameter. The TBM was disassembled and recovered and the adit was closed with an 8 meter thick concrete plug.
After that, 19 inclined probe drillings were carried out from the exploratory adit toward the planned base tunnel alignment. Laboratory analyses of the drill cores revealed carbonate-sulfate trias, i.e. a rock with relatively good rock mechanical properties. Probe drillings, carried out at the tunnel face this September, confirmed the results from the laboratory analyses: The dolomite rock of the Piora Basin is hard, non-aquiferous and therefore suited for mechanized tunnelling.
Contact:
HEADQUARTERS OF THE HERRENKNECHT AG.
Schlehenweg 2
77963 Schwanau
PH.: +49 (0) 7824-302-0
FAX: +49 (0) 7824-34-03
E-Mail: info@herrenknecht.com
Internet: www.herrenknecht.com
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
Herrenknecht AG
Schlehenweg 2
D-77963 Schwanau
Phone:
(+49) 78 24 30 20
Fax:
(+49) 78 24 34 03