Gotthard Base Tunnel: Tunnelling works in the eastern tube of the Piora Basin finished
Dec 23, 2008
The Herrenknecht Gripper-TBM S-210 passed the Piora Basin – a critical zone of the Gotthard Massif - without problems. The tunnel boring machine S-211, driving the western tube, will also arrive in the Piora Basin at the beginning of 2009. North of the basin, both machines will have to tackle another seven kilometers of hard rock - at an overburden of 2,000 meters and with rock temperatures of up to 50 degrees centigrade.
Steel ribs (TH profiles) were installed directly behind the cutter head at one-meter intervals for rock support. The rock surface was sealed with a shotcrete layer and an inner lining was then applied in the form of a 30 centimeterer thick shotcrete segment ring. All this measures proved themselves in practice. “We could not measure any deformations,” explained Heinz Ehrbar, Senior Tunnel and Rail Line Manager of AlpTransit Gotthard AG. The tunnel boring machine driving the western tunnel has to excavate another 1,400 meters of tunnel until it reaches the Piora Basin, probably in the first three months of 2009.
Tunnelling north of the Piora Basin.
Once the Piora Basin is passed, another approx. 6.9 kilometers of tunnel have to be mechanically excavated until the Sedrun section is reached. This is the zone with overburdens of up to 2,000 meters and the highest rock temperatures of 50 degree centigrade encountered within the world’s longest railway tunnel.
Tunnelling progress in the Gotthard Base Tunnel.
In the north, two Herrenknecht Gripper TBMs – the S-421 and S-422 – already drove 3.2 and 1.9 kilometers of the two tunnel sections, each measuring 7.178 kilometers in length, along the Erstfeld-Amsteg section. According to the constructor the tunnelling works move forward as planned. Until October 1, 2008, the tunnellers excavated 118.4 kilometers of tunnel, shafts and adits, equalling 77 percent of the planned 153.5 kilometers.
Previous history: Piora – the tunnellers’ nightmare.
In the run-up to the construction of the Gotthard Base Tunnel, a major controversy broke out among geological experts. Some geologists even doubted the construction of the tunnel due to almost unmanageable fault zones. They expected a sugar-grained dolomite and high water pressures in the Piora Basin. Geological investigations were therefore carried out in the Piora Basin during 1993 and 1998. A 5.5 kilometer long exploratory adit was driven 350 meters above the planned base tunnel alignment from Faido using a small tunnel boring machine. During a core drilling on March 30, 1996, the Piora Basin and the sugar-grained dolomite, subjected to a water pressure of 150 bar, were reached for the first time. Within three hours, 1,400 cubic meters of soft rock mixed with water poured out of the drill hole which was only 10 centimeters in diameter. The TBM was disassembled and recovered and the adit was closed with an 8 meter thick concrete plug.
After that, 19 inclined probe drillings were carried out from the exploratory adit toward the planned base tunnel alignment. Laboratory analyses of the drill cores revealed carbonate-sulfate trias, i.e. a rock with relatively good rock mechanical properties. Probe drillings, carried out at the tunnel face this September, confirmed the results from the laboratory analyses: The dolomite rock of the Piora Basin is hard, non-aquiferous and therefore suited for mechanized tunnelling.
Contact:
HEADQUARTERS OF THE HERRENKNECHT AG.
Schlehenweg 2
77963 Schwanau
PH.: +49 (0) 7824-302-0
FAX: +49 (0) 7824-34-03
E-Mail: info@herrenknecht.com
Internet: www.herrenknecht.com
More News and Articles
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Mar 18, 2024
News
Global Student Innovation Challenge Calls on Next-Generation Leaders to Tackle Water Security
High School and University Students Worldwide Invited to Expand Water Access and Community Resilience
Mar 15, 2024
News
New water treatment wins Prestigious Award
Introducing a advancement in water treatment, developed by Cardiff University researchers in collaboration with Origin Aqua, the FreeOxTM technology has garnered acclaim by winning a prestigious challenge award at the World Water Tech Innovation Summit. This single-step process not only …
Mar 13, 2024
News
Satellite-based river monitoring technique could provide early warning of flooding
A satellite-based method for monitoring the flow of rivers from orbit could provide a valuable early warning system for flood risk, University of Glasgow researchers have claimed.
Mar 11, 2024
News
Revitalising infrastructure with HDD
Through the use of horizontal directional drilling, TasWater is delivering a new sewer pipeline to improve sewer and stormwater transfer capacity in Launceston, Tasmania.
Mar 06, 2024
News
Picking up the pace on climate action: Building momentum from COP28
At the halfway point of the Paris Agreement, the legally binding international treaty on climate action, average global temperatures are already hitting 1.8°C above pre-industrial levels and future projections are stark. At COP28 in December, we could not escape the reality …
Mar 01, 2024
News
Luminescent sensor detects ‘forever chemical’ pollution in water
Researchers in the UK and Germany have developed a new approach for detecting pollution from ‘forever chemicals’ in water through luminescence.
Feb 28, 2024
Article
BETT installation demonstrating GHG emissions reduction of wastewater treatment
This study presents BioElectrochemical Treatment Technology (BETT) as a new wastewater management solution toward the Net-Zero future. The results reported herein were collected from a BETT pilot system installed at a large brewery in Los Angeles, CA, United States processing …
Contact
Herrenknecht AG
Schlehenweg 2
D-77963 Schwanau
Phone:
(+49) 78 24 30 20
Fax:
(+49) 78 24 34 03