First mechanically-excavated tunnel beneath the Bosporus
May 18, 2009
Completed safely and on schedule with Herrenknecht technology: In mid-April 2009, the Herrenknecht S-391 tunnel boring machine (Ø 6.11m) reached its target shaft in Istanbul. The new "Melen 7" tunnel crosses beneath the Bosporus, which is the sea strait between the Asian and the European parts of the Turkish metropolis. When the interior construction is completed, the tunnel will supply the European part of the city with water from the Asian part. At its deepest point, the tunnel route runs 135 meters below the sea strait’s water level. The construction team and the tunnelling machine excavated this challenging section safely. The first mechanically-excavated tunnel beneath the Bosporus was built in 13.5 months only.
The "Melen 7" tunnel is the key element of a large-scale project to secure an improved long-term water supply for the huge city of Istanbul, which today is home to more than 10 million inhabitants. This water is not only required on the European side of Istanbul for the inhabitants' drinking water supply, but is also urgently needed for agriculture and regional industries. For this purpose, the river Melen has been dammed on the Asian side, 170 kilometers outside the gates of the city. From this high-rainfall area, the water will be channeled to Istanbul in several stages. To lead the water to the European part of the city too, the tunnel must cross beneath the Bosporus.
The biggest challenge within the project was to excavate the tunnel tube at the enormous depth of up to 135 meters beneath the water level. Therefore, the machine had to be sealed to withstand water pressures of up to 13.5bar.The initial tunnel tube built by the tunnel boring machine was constructed with lining segments (prefabricated components made of reinforced concrete) which are equipped with special seals designed to withstand a water pressure of up to 20bar. The moulds for production of the lining segments were supplied by Herrenknecht Formwork GmbH to Turkey. The final finishing work for water conveyance will be made of steel tubes and is expected to be completed in spring 2010.
The launch shaft for the machine was situated in the city quarter of Sariyer on the European side. The first approx. 2.3 kilometers were constructed with a gradient of 7.45%. The overburden to the seabed was only 35 meters in some parts, with a water column which was twice as high, at 70 meters. The rest of the route (1.1 kilometers) ran almost horizontally. In mid-April 2009 – 13.5 months after the start on the European side – the Herrenknecht tunnelling shield appeared on schedule in the 140 meter deep target shaft in the Asian city quarter of Beykoz. In order to be able to recover the machine from the small target shaft, which had a diameter of only 8 meters, the Herrenknecht engineers designed the machine with small shield segments.
With the breakthrough of the Herrenknecht S-391 EPB Shield in the target shaft, the construction team of the Russian construction company OAO Mosmetrostroy successfully excavated the first tunnel beneath the Bosporus. This was the first connection between two continents created by a tunnelling machine. In view of the challenges mastered, this is an excellent reference for mechanized tunnelling.
Contact:
Herrenknecht AG
Schlehenweg 2
77963 Schwanau
Ph.: +49 (0)7824 302-540
Fax: +49 (0)7824 302-473
E-Mail: pr@herrenknecht.de
Internet: www.herrenknecht.de
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
Herrenknecht AG
77963 Schwanau
Phone:
+49 (0) 7824-302-0
Fax:
+49 (0) 7824-34-03