Direct Pipe ®: Latest innovation in pipeline construction - technology and references
Nov 10, 2008
Various methods have so far been applied for crossing works in order to build steel or polyethylene pipelines as pressure lines. Pipe jacking and segmental lining allow for the construction of protective tunnels with subsequent insertion of the pipe string. The HDD method, in contrast, includes the construction of a pilot bore prior to pipe pull-in. Recent developments such as the Easy Pipe method comprise jacking processes -- where tight connection interim steel pipes are pushed towards the target shaft, coupled to a pipeline and then pulled back together. All these methods include a two- or multi-step pipe installation process. The multilevelness of these methods and pertinent aspects such as costs and project duration led to the development of the DIRECT PIPE® method: Steel or polyethylene pipes can now for the first time be jacked efficiently and fast in one operation process.
The tunnel face is slurry-supported using a bentonite suspension. The excavated material is removed via a slurry circuit with separation plant in order to separate the spoil from the slurry liquid before feed pumps transport the liquid back to the tunnel face. The micromachine is controlled from the operating container. A gyro compass is used for machine surveying. The micromachine, pipes and connection pipes are designed conically, which increases the annular gap between the machine or pipe sleeve and the surrounding ground. Bentonite is injected into the annular gap for lubrication from the cutting-wheel assembly. In addition, a lubrication ring is mounted in the transition area between the connection pipe and the product pipeline, where most of the bentonite is added, in order to reduce the friction between the pipeline and the ground to a minimum. In contrast to pipe jacking, a Herrenknecht Pipe Thruster is set up in the launch pit instead of a jacking frame. The Pipe Thruster clamps the pipeline on the outside and pushes the pipes as well as the microtunnelling machine strokewise forward with its thrust cylinders.
In the rear of the Pipe Thruster, a prefabricated and tested product pipeline is positioned on pulley blocks ready to be thrust forward. Different from pipe jacking or microtunnelling, the DIRECT PIPE® method allows for an installation of the slurry circuit from the start of the project not requiring a delayed installation and successive extension of the circuit: The slurry and pump system is operated parallel to pipe jacking along the entire drive length.
Due to this site configuration, the product pipeline can be installed in one step. The direct installation of the pipeline allows for continuous drill-hole support preventing hole collapse. The DIRECT PIPE ® site configuration also allows for a basic launch and target shaft design. It is only necessary to provide a launch seal and firm foundation for the Pipe Thruster on the launch side in order to transmit the thrust forces to the soil. Upon arrival in the target shaft, only the TBM and the connection pipes have to be disassembled; the installation of the product pipeline in the ground is then already completed. Feed and slurry lines as well as control, data and power cables are led through the pipeline on special roller assemblies; they can be easily removed from the pipeline using a rope winch.
- One-step jacking method, i.e. the product pipeline is pushed into the ground in one step, in contrast to all common methods, which have so far been applied
- Permanent drill-hole support in order to prevent a drill-hole collapse, advantage over HDD
- Cutting wheel and cutting tools of the microtunnelling machine can be adapted to any geological conditions, which is particularly beneficial over HDD
- Minimum space required, only on the launch side: Advantage over other methods, which either require considerable storage space on the launch side (pipe jacking / segmental lining), which require considerable space in order to install the product pipeline on the target side (HDD) or which require space on both sides (Easy Pipe)
- Minimum slurry volume required due to the small overcut
- High performance rates - due to the deployment of the Pipe Thruster and the possibility to install and test entire pipe sections
- The microtunnelling machine, which is equipped with U.N.S. navigation technology and a north-seeking gyro compass, guarantees high-precision target control
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …
Contact
Dr. Marc Peters
77963 Schwanau
Phone:
+49 (0) 7824-302-0
Fax:
+49 (0) 7824-34-03