Case study - UV cured lining project wins the day for DALROD
Feb 23, 2016
DALROD recently ventured into new pipe-lining territory using, for the first time, UV cured lining on a project for client Peterborough City Council (PCC)
The project known as Baxters Bridge was located near Newborough, a small hamlet and civil parish in the Peterborough district, in Cambridgeshire, UK. Newborough is situated about 4.6 miles (7.5km) north of Peterborough. A crossroad near the village, adjacent to Crowland Main Dyke, was a site where a deteriorated 600 mm diameter, under-road culvert required rehabilitation over a length of some 20m.
Urgent remedial works
The culvert carries land drainage run-off waters between dykes that control the water levels in the local fenlands. The road route at the site of the culvert is a busy rat-run, particularly during rush hour and used by commuter traffic, heavy goods and farm vehicles. Inspection of the culvert by PCC showed that, due to its position with its crown at just 2m below the road surface, the structural integrity of the concrete pipe construction was compromised by multi-fractures/cracks and other defects. Had the culvert not been rehabilitated or replaced there was a significant possibility of collapse and damage to the road above.
Limited options leads to UV cured lining solution
Having decided that the culvert was in need of repair, various options were investigated including the use of open cut techniques to replace the culvert length beneath the road or to rehabilitate the culvert to reinstate its structural integrity. Consulting with PCC project’s main framework contractor Skanska, the open cut option was relatively quickly dismissed due to a number of factors. To complete the project in open cut would have required a complete road closure over some seven working days, which in turn would have led to the large volumes of traffic using a diversion route of a minimum 3-5 miles (8 km) around the works. There would also have been a need for significant numbers of works vehicles to and from the site over this time.
Given the very rural aspect of the area, the diversion route would also have required the use of several minor roads which often have steep embankment sides to bring the road level up above the level of the surrounding fens, which would have meant potentially led to significant traffic handling difficulties. With the potential also existing for a high carbon footprint on the project using open cut, it was decided to investigate the rehabilitation options.
Looking at the rehabilitation options meant selecting a lining technique that would ‘fit the bill’. Given the experience of many contractors in the field of lining works, the project was put out to competitive tender however many lining options such as hot water cure and epoxy resin use do have significant leachate from the liner during the lining process and subsequent to the liner installation. As the site was handing land drainage this was not seen as an option that could be utilised.
DALROD’s experience wins the day
The remaining option was the use of a Ultra Violet (UV) cured lining that does not have the environmental disadvantages of other systems. Ultimately, DALROD’s Cambridge franchisee (Mike Pollard’s team) was selected as the preferred bidder for the works, even though the company had not previously utilised UV cure on other operations. However, it was understood that the company’s experience on other lining works, as well as the fact that DALROD was very familiar with prevailing conditions in this part of the country, stood it in good stead for this operation.
Lining works
One of the other advantages of the UV cured lining option, over and above the environmental ones in terms of non-contamination of the ground water run-off, was that there would be no need to have a complete road closure, as the works could be completed using a four-way traffic control system at the crossroad where the culvert was located, so eliminating the major disruptive diversion route.
So, having established the works site over the culvert entrance, first the culvert was thoroughly cleaned to ensure that there was nothing within it that could impede the lining operation. The culvert was then checked and surveyed using a CCTV camera. The UV liner was then prepared for insertion. Supplied by RSM Lining Supplies of Doncaster, UK, the reinforced UV liner was delivered to site pre-impregnated with the UV sensitive resin. To install the liner a winch was set-up on the downstream end of the culvert and a winch line was passed through. Initially a pre-liner was winched into the culvert which helps to prevent any external friction wear on the final liner during its insertion. The winch was then used to pull the main liner through the culvert into position inside the pre-liner.
Once in place, the whole liner assembly was then attached to an compressor/air blower unit and inflated to ensure the liner fitted correctly. A reinforced liner system was utilised to ensure the long-term integrity of the culvert which once rehabilitated would continue to carry significant traffic loadings into the future.
UV light train
In the meantime the UV light train was set-up and connected to a towing line that ran through the liner. The light train was then placed into the liner, the ends were sealed using special fittings that allowed the light train to be pulled freely through the liner whilst maintaining it in its inflated state so as to achieve the curing process. The liner was then fully inflated against the inner culvert wall.
The UV light train was pulled through the liner in accordance with the manufacturer’s specification at a speed that would fully cure the 8 mm thick liner. On this project the cure time for the 19 m run was just about 45 minutes. Once the light train had completed its run the ends of the liner were opened up to retrieve the light unit and the liner ends were sealed at either end of the culvert. The CCTV camera was again passed through the culvert to record the completed liner for client records.
The whole lining operation was completed from arrival on site, through set-up, culvert cleaning, CCTV survey, lining and final survey in just one working day on 13 October 2015, as opposed to the seven working days that would have been required for any open cut operation. The other advantage of being able to complete the works in just the one day is that overall the cost of the project was significantly less than could have been achieved using open cut replacement techniques. The carbon footprint of the project as a whole was also considerably lower.
More News and Articles
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Mar 01, 2023
News
World-first project to ‘self heal’ cracked concrete using sludge could save $1.4 billion repair bill to Australia’s sewer pipes
Water treatment sludge could be used to prevent 117,000 kilometres of sewer pipes in Australia from cracking in future, without any intervention by humans, helping to save $1.4 billion in annual maintenance costs.
Feb 27, 2023
News
Delaware Water Treatment Plant Opts for Penetron to Protect New Concrete Structures
The final 2022 commissioning of the Doe Run Road Water Treatment Plant enables the city of Newark, Delaware (USA), to increase the quantity and quality of the city's drinking water to better meet growing demand – and EPA guidelines. PENETRON …
Feb 24, 2023
News
Aussie Trenchless: the future of pipe rehabilitation solutions
Aussie Trenchless has been passionate about progressing future infrastructure opportunities and accomplishing superior outcomes since it was founded in 2014.
Contact
DALROD (Uk) Ltd
Bryan Lord
2a Treelyn Park
PE2 7WH Peterborough
United Kingdom
Phone:
+44 (0) 1733 23 11 22
Fax:
+44 (0) 173323 44 55