An overview of Jacked Structure Techniques - Pt. 1
Nov 10, 2010
Where one form of traffic (people, cars or trains) have to intersect and cross existing highways or rail tracks, this creates a hazardous situation. Inevitably even with all the safety measures such as barriers, traffic lights at junctions and crossings there are still an unacceptable number of accidents with injuries and deaths. At best such intersecting traffic streams result in delays and congestion. The segregation of various forms of traffic one from another is going to be even higher priority as our roads and rail tracks carry ever more traffic.
The development of horizontal construction methods for subways, underpasses and other underground structures based on jacking techniques was initially pioneered in the sixties and seventies by the author and others in a number of countries.
Three main approaches were used and are still find use today:
- Box Jacking
- Advanced Support Structures
- Modular Jacking
These techniques and applications are described in this first review. The second part will look at some of the new developments.
Box Jacking
The most basic approach, which is still widely used, is box jacking where the box structure is constructed on a launch pad adjacent to where it is to be installed and is jacked into the ground with excavation taking place in the shield. The graphic at Fig 1 illustrates the concept.Many installations have been undertaken under roads, rail tracks and runways. Fig 2 gives some idea of the size and the large number of hydraulic rams that are used. This structure weighed 8,500 tonnes was 10m wide and 25m wide and requiring up to 14,500 tonnes of jacking force to install over a length of 37m.
One variation developed in Italy used below rail tracks is based on installing a supporting grid to the tracks during short possessions. The box is designed to directly slide beneath the grid picking up the load as it is jacked under the tracks. The support strapping system and a completed underpass are illustrated in figs 3 and 4.
The reality for all these systems is that however good the design and execution some small amount of settlement will still occur due to the over-break and soil consolidation. This does not occur suddenly but relatively slowly. For rail tracks on a ballast bed this can be can be compensated by track fettling of the bed.
This widely used approach has some limitations including:
- Limitations of size and drive length due to the high jacking loads involved
- Very large exposed face which may be difficult to control where soils are not ideal
- Constructing the box adjacent to the tracks requires a large launch pad area with a minimum length greater than the length of drive.
- The large jacking forces involved require substantial reaction arrangements
- If a box starts to go out of level it is difficult if not impossible to make corrections
Advanced Support Structures
This technique is based on the provision of advanced support structures where a canopy is installed as a initial support to allow the construction of the final structure. Typical approaches are shown in the graphic at Figure 5. The steel tubes which form the canopies can be installed by pipe ramming, micro-tunneling or auger boring.In this case the tubes were installed using pilot boring techniques. Microtunnelling, auger boring and pipe ramming have all been used for the installation of the canopy tubes. Once the canopy is in place excavation can progress in stages installing framing to the tubes to provide structural support. Once excavated and supported the final stage is the installation in-situ of the structural concrete walls and roof together with the road construction.
Modular Jacking
In recognition of some of the limitations the author when working for a major contractor in UK in the seventies developed and patented the modular method. The concept illustrated in Figure 7 is to create a support or foundation structure such as bridge abutments using interlinked pre-cast components which are jacked into position horizontally. Normally the final deck to the bridge is placed in a very limited occupation from the surface. The deck beams are placed on the structure that has been formed below the occupation and disruption is minimal. Final excavation of an underpass after placing the beams on the supports of course can be undertaken mechanically without any special measures as the structure is in place. A typical example would be an under bridge with abutments and central pier. The disturbance to traffic on the existing road or track is minimal. The system has the advantage that relatively small modular units are being jacked so temporary working space and jacking capacity required is lower than that required for larger boxes.During a short track possession the bridge deck can be slid-in or bridge beams placed to complete the structure. A large number of such jobs have been undertaken in UK. A typical installation is the Wandsworth under-bridge shown at Fig 6.
In part 2 of this review the author will describe some new developments and techniques...
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
Jacked Structures SA
CH1215 Geneva 15
Phone:
(41) 076 201 300