About-turn for "SUSE" in the Filder Tunnel
Sep 20, 2018
In late July the moment has come: tunnel boring machine "SUSE" (Ø 10,820 mm) has completely excavated the western tube of the Filder Tunnel. Now, in a specially built cavern, the approximately 120 meter long Multi-mode TBM from Herrenknecht is disassembled into individual parts and turned around underground. From the fall of 2018 it is due to commence excavation work in the remaining 3.4 kilometer section of the eastern tube.
"Stuttgart-Ulm schneller erreicht" (Stuttgart-Ulm reached faster) is behind the acronym used to name the Herrenknecht tunnel boring machine "SUSE" (Ø 10,820 mm), which successfully finished its third shield drive in the Baden- Württemberg state capital in late July.
With the end of the advance the crew from joint venture ARGE ATCOST 21 (Porr Bau GmbH Tunnelbau, G. Hinteregger & Söhne Baugesellschaft m.b.H., Östu-Stettin Hoch- und Tiefbau GmbH, Swietelsky Baugesellschaft m.b.H.) has now completed the western tube of the approximately 9.5 kilometer long twin-tube Filder Tunnel.
For the final project breakthrough, "SUSE" still has to excavate a 3.4 kilometer long section in the eastern tube. The tunnelling work is scheduled to start in the fall of 2018. Prior to that, the approximately 2,000 tonne and 120 meter long TBM will be disassembled into several parts and turned around in a specially built cavern inside the rock mass. "Such an about-turn underground with a TBM of this size is absolutely exceptional," says Dr.-Ing. E. H. Martin Herrenknecht. "This shows what extraordinary technical feats are being achieved during the construction work on the Filder Tunnel. Hats off to the site crew!"
The tunnel section is located in heterogeneous rock strata and overcomes a total height difference of 155 meters with a slope of up to 2.5 percent. Due to the complex project requirements, initially no mechanized tunnelling was planned for the Filder Tunnel.
However, the particularly flexible and convertible Multi-mode TBM machine type from Herrenknecht has convinced the client Deutsche Bahn of the advantages of mechanized tunnelling over a large part of the tunnel route.
In the upper section of the Filder Tunnel the convertible Multi-mode TBM "SUSE" worked in EPB mode with screw conveyor muck removal, in the lower Filder Tunnel in open single-shield mode with belt conveyor discharge. The only area the machine was not used was in the geological transition zone, where miners removed the material from the rock using diggers and loosening blasting.
The Filder Tunnel is the longest on the new line between Stuttgart and Ulm, which will link the new central railway station with the Filder Plain. As a result of the railway project, travel times between Stuttgart and Ulm will be almost halved. Around ten million passengers per year will benefit from the scheme.
Contractors working on other tunnelling sections of the Stuttgart-Ulm railway project are also relying on Herrenknecht tunnel boring machines. For example, the two Herrenknecht machines "WANDA" and "Sibylle" (Ø 10,820 mm) are in operation for the Albvorland Tunnel. The EPB Shield "Käthchen" (Ø 11,340 mm) recently completed excavation of the 8.8 kilometer long Bossler Tunnel.
Text below the box.Project data About-turn for "SUSE" in the Filder Tunnel
MACHINE/PROJECT DATA S-738/S-746
Machine type: Multi-mode TBM
- Shield diameter: 10,830 mm
- Drive power: 4,200 kW
- Tunnel length: 9,468 m, Advance length 15,330 m
- Geology: heterogeneous soils (Lower Jurassic & Rhaetic, lumpy marl, sandstone with marls and clay, unleached Gypsum keuper)
- Customer: ARGE ATCOST 21 (Porr Bau GmbH Tunnelbau, G. Hinteregger & Söhne Baugesellschaft m.b.H., Östu-Stettin Hoch-und Tiefbau GmbH, Swietelsky Baugesellschaft m.b.H.)
- Client: Deutsche Bahn AG
Herrenknecht AG
Herrenknecht AG is the only company worldwide to deliver tunnel boring machines for all geologies and in all diameters – ranging from 0.10 to 19 meters. The product range comprises tailor-made machines for traffic, supply and disposal tunnels, technologies for routing of pipe lines, as well as additional equipment and service packages. Herrenknecht also manufactures excavation equipment for vertical and inclined shafts as well as deep drilling rigs.
More News and Articles
May 30, 2023
News
Trenchless contractor puts maintenance hole relining system through its paces
Civil and trenchless specialists M Tucker & Sons showcases its expertise through a UV lining project.
May 26, 2023
News
City of Toronto launches tunnel boring machine for stormwater tunnel and largest basement flooding prevention project
Today, the City of Toronto marked a major milestone for the Fairbank Silverthorn Storm Trunk Sewer System project, launching a tunnel boring machine that will work to construct a new storm sewer that will collect, store and move stormwater from …
May 24, 2023
News
Global Water and Wastewater Utilities Take Aim at Climate Change
New Survey of 100 Utilities Tracks Net-Zero Progress: 75% of Respondents to Reduce Greenhouse Gas Emissions by 2040
May 22, 2023
News
Regional San’s monumental wastewater treatment plant expansion project delivered ON schedule and UNDER budget
The EchoWater Project, one of the largest public works projects in the Sacramento region’s history, takes wastewater treatment to a whole new level
May 19, 2023
News
Haliotis 2: Wastewater recovery and treatment complex
In April the future, next-generation wastewater recovery and treatment complex for the Métropole Nice Côte d’Azur “Haliotis 2” was presented. Christian Estrosi, Mayor of Nice, President of the Métropole Nice Côte d’Azur and Deputy President of the Région Provence-Alpes-Côte d’Azur …
May 17, 2023
News
Wrapping up the challenges in SA
In December 2022, Denso Australia completed the supply of a project involving the protection of 400 lineal metres of DN250 mild steel pipeline in Bolivar, South Australia.
May 15, 2023
News
New South Wales university receives network upgrade using SAERTEX-LINER® MULTI Type S+
Australian Pipeline Management (APM) has successfully relined three separate pipelines running under a university in Sydney with UV cured-in-place technology from SAERTEX multiCom® GmbH.
May 12, 2023
News
IMPREG continues to invest in Australian and NZ market
With increasing demand of IMPREG’s unique UV pipe solution, the German company continues to invest in the Australian and New Zealand market.
May 10, 2023
Article
Yonge Street Project Combines Trenchless Rehab and New Install Practices
In the fall 2020, the Regional Municipality of York initiated a project to rehabilitate a 127 m long concrete box culvert under Yonge Street. The Region retained Jacobs Engineering to provide design and construction support services.
May 08, 2023
News
Climate adaption solutions for the water sector in the German-Danish border area
More than 60 participants met in Kolding, Denmark, from March 23 to 24 for the final conference of the INTERREG-Project NEPTUN. In the frame of this project, more than 40 partners elaborated 15 specific climate adaption solutions for the water …
May 05, 2023
News
Primus Line® flies the flag for trenchless solutions in sensitive locations
Primus Line has illustrated the benefits of trenchless technology for pipeline rehabilitation in culturally sensitive areas during two installations for one of the world’s leading mining companies.
May 03, 2023
News
Optimising chemical dosing in a challenging operating climate
Rising operating costs and tightening regulations are presenting major challenges for wastewater treatment plant operators, but better optimisation of chemical dosing can drive efficiencies, says Adeel Hassan, product manager at Watson-Marlow Fluid Technology Solutions.
Contact
Herrenknecht AG
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 7824 302-5400